extreme contingency analysis 2006 & 2016 4 th bta presentation

11
Extreme Contingency Analysis 2006 & 2016 4 th BTA Presentation Bob Smith Manager Transmission Planning June 6, 2006

Upload: hilel-carter

Post on 03-Jan-2016

33 views

Category:

Documents


0 download

DESCRIPTION

Extreme Contingency Analysis 2006 & 2016 4 th BTA Presentation. Bob Smith Manager Transmission Planning June 6, 2006. Study Assumptions. Utilize the 2006 heavy summer power flow case and re-run worst outage for 2016 Severity of outage determined by the ability to serve Phoenix load - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Extreme Contingency Analysis 2006 & 2016 4 th  BTA Presentation

Extreme Contingency Analysis2006 & 20164th BTA Presentation

Bob Smith

Manager Transmission Planning

June 6, 2006

Page 2: Extreme Contingency Analysis 2006 & 2016 4 th  BTA Presentation

June 6, 2006 4th BTA 2

Study Assumptions Utilize the 2006 heavy summer power flow case and re-

run worst outage for 2016 Severity of outage determined by the ability to serve Phoenix

load Corridors were chosen based upon exposure to forest fires

Cholla-Saguaro and Coronado-Silverking 500kV lines Navajo South 500kV lines Four Corners-Cholla-Pinnacle Peak 345kV lines Glen Canyon-Flagstaff-Pinnacle Peak 345kV lines PV East corridor not studied because there is no forestation

Page 3: Extreme Contingency Analysis 2006 & 2016 4 th  BTA Presentation

June 6, 2006 4th BTA 3

Study Assumptions Transformer banks studied

Kyrene 500/230kV Browning 500/230kV

Transformer banks not studied Westwing 500/230kV transformers have additional spacing, fire

walls, fire suppression, and oil retention pits Rudd 500/230kV transformer outage is equivalent to outage of

Palo Verde-Rudd 500kV line Pinnacle Peak 345/230kV transformer outage is equivalent to

outages of the 345kV lines into Pinnacle Peak.

Page 4: Extreme Contingency Analysis 2006 & 2016 4 th  BTA Presentation

June 6, 2006

4th BTA

4

ARIZONA STATE EHV MAP

SELIGMAN

ROUNDVALLEY

POWER PLANT

115KV & ABOVE SUBSTATION (EXISTING)

LEGEND

NORTH

SAGUARO

N.GILA

PALO VERDE-HASSAYAMPA

YUCCA

GILA BEND

TO CALIF.500KV

REDHAWK

JOJOBA

GILA RIVER

RUDD

LIBERTYKYRENE

SANTAROSA

DESERTBASIN

WESTWING

YAVAPAI VERDE

PINNACLE PEAK

PREACHERCANYON

CHOLLA

TO CALIF.

TOCRYSTAL

TO MEAD /MARKETPLACE

MOENKOPI

NAVAJO

FOURCORNERS

TUCSON

5/23/06Transmission Planning

COCONINO

Substation locations and line routings depict an electrical connection only anddo not reflect any assumed physical locations or routing.

CASAGRANDE

TAT MOMOLI

KNOX

GAVILANPEAK

FLAGSTAFF

GLEN CANYON

EXISTING 500 KV LINESEXISTING 345 KV LINESEXISTING 230 KV LINESEXISTING 115 KV LINES

NUCLEAR POWER PLANT

CORONADO

BROWNINGSILVERKING

Page 5: Extreme Contingency Analysis 2006 & 2016 4 th  BTA Presentation

June 6, 2006

4th BTA

5

ARIZONA STATE EHV MAP

SELIGMAN

ROUNDVALLEY

POWER PLANT

115KV & ABOVE SUBSTATION (EXISTING)

LEGEND

NORTH

SAGUARO

N.GILA

PALO VERDE-HASSAYAMPA

YUCCA

GILA BEND

TO CALIF.500KV

REDHAWK

JOJOBA

GILA RIVER

RUDD

LIBERTYKYRENE

SANTAROSA

DESERTBASIN

WESTWING

YAVAPAI VERDE

PINNACLE PEAK

PREACHERCANYON

CHOLLA

TO CALIF.

TOCRYSTAL

TO MEAD /MARKETPLACE

MOENKOPI

NAVAJO

FOURCORNERS

TUCSON

5/23/06Transmission Planning

COCONINO

Substation locations and line routings depict an electrical connection only anddo not reflect any assumed physical locations or routing.

CASAGRANDE

TAT MOMOLI

KNOX

GAVILANPEAK

FLAGSTAFF

GLEN CANYON

EXISTING 500 KV LINESEXISTING 345 KV LINESEXISTING 230 KV LINESEXISTING 115 KV LINES

NUCLEAR POWER PLANT

CORONADO

BROWNINGSILVERKING

Page 6: Extreme Contingency Analysis 2006 & 2016 4 th  BTA Presentation

June 6, 2006 4th BTA 6

SUMMARY OF RESULTS (2006) For all outages studied all load can be served &

local Phoenix reserve requirements met Some outages from remote generation would require

redispatching from other available sources Maximum redispatch requirement is ~800MW @ Navajo Generation made up from available AZ and CA units

Some outages would require some system reconfiguration to alleviate overloads

Without system reconfiguration load reduction of up to 200MW is required for outages of corridors into Pinnacle Peak

Page 7: Extreme Contingency Analysis 2006 & 2016 4 th  BTA Presentation

June 6, 2006 4th BTA 7

SUMMARY OF RESULTS (2016) Outages of the lines coming into Pinnacle

Peak were re-examined For Glen Canyon to Pinnacle Peak outages, Glen

Canyon remote generation needs to be redispatched; independent of Phoenix load

No system reconfiguration required Phoenix local reserve requirement met TS9 to Raceway 500kV line mitigates those

outages

Page 8: Extreme Contingency Analysis 2006 & 2016 4 th  BTA Presentation

June 6, 2006

4th BTA

8

ARIZONA STATE EHV MAP

SELIGMAN

ROUNDVALLEY

POWER PLANT

115KV & ABOVE SUBSTATION (EXISTING)

LEGEND

NORTH

SAGUARO

N.GILA

PALO VERDE-HASSAYAMPA

YUCCA

GILA BEND

TO CALIF.500KV

REDHAWK

JOJOBA

GILA RIVER

RUDD

LIBERTYKYRENE

SANTAROSA

DESERTBASIN

WESTWING

YAVAPAI VERDE

PINNACLE PEAK

PREACHERCANYON

CHOLLA

TO CALIF.

TOCRYSTAL

TO MEAD /MARKETPLACE

MOENKOPI

NAVAJO

FOURCORNERS

TUCSON

5/23/06Transmission Planning

COCONINO

Substation locations and line routings depict an electrical connection only anddo not reflect any assumed physical locations or routing.

CASAGRANDE

TAT MOMOLI

KNOX

GAVILANPEAK

FLAGSTAFF

GLEN CANYON

EXISTING 500 KV LINESEXISTING 345 KV LINESEXISTING 230 KV LINESEXISTING 115 KV LINES

NUCLEAR POWER PLANT

CORONADO

BROWNINGSILVERKING

RACEWAY

Page 9: Extreme Contingency Analysis 2006 & 2016 4 th  BTA Presentation

June 6, 2006 4th BTA 9

PHOENIX LOAD DURATION & RMR CONDITION (2006)All Lines In-Service

0

1000

2000

3000

4000

5000

6000

7000

8000

9000

10000

11000

12000

13000

0 1000 2000 3000 4000 5000 6000 7000 8000 9000 10000

HOURS

LO

AD

(M

W)

VALLEY LOAD

PEAK = 11,434 MW

569 HOURS

Total Valley Energy = 50,873 GWH

Import = 9,250 MW

397 GWH2,184 MW

LSC = 12,800 MW

Page 10: Extreme Contingency Analysis 2006 & 2016 4 th  BTA Presentation

June 6, 2006 4th BTA 10

PHOENIX LOAD DURATION & RMR CONDITION (2006)Worst Case outage w/load reduction and generation redispatch

0

1000

2000

3000

4000

5000

6000

7000

8000

9000

10000

11000

12000

13000

0 1000 2000 3000 4000 5000 6000 7000 8000 9000 10000

HOURS

LO

AD

(M

W)

VALLEY LOAD

PEAK = 11,434 MW

1,209 HOURS

Total Valley Energy = 50,873 GWH

Import = 8110 MW

1,406 GWH3,200 MW1

LSC = 11,310 MW

1 AF Generation reduced by 405 MW

Page 11: Extreme Contingency Analysis 2006 & 2016 4 th  BTA Presentation

June 6, 2006 4th BTA 11

PHOENIX LOAD DURATION & RMR CONDITION (2006)Comparison

0

1000

2000

3000

4000

5000

6000

7000

8000

9000

10000

11000

12000

13000

0 1000 2000 3000 4000 5000 6000 7000 8000 9000 10000

HOURS

LO

AD

(M

W)

VALLEY LOAD

PEAK = 11,434 MW

640 HOURS

Total Valley Energy = 50,873 GWH

Import = 9,250 MW 1,009 GWH1,140 MW

Import = 8110 MW