fnal crab cavities dec2012 oc

Upload: suphi-yueksel

Post on 03-Apr-2018

224 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 FNAL Crab Cavities Dec2012 OC

    1/32

    General specifications

    LHC Crab cavities

    O. Capatina, L. Alberty, K. Brodzinski, R.Calaga,

    E. Jensen, V. Parma CERN

    LHC Crab Cavity Engineering MeetingOC, 13/December/2012 1

  • 7/28/2019 FNAL Crab Cavities Dec2012 OC

    2/32

  • 7/28/2019 FNAL Crab Cavities Dec2012 OC

    3/32

    RF Power Coupler

    Cavity

    Helium Tank

    Tuner

    HOM Coupler

    Bi-phase helium

    tube

    Magnetic shielding

    Beam pipe

    TTC Meeting 3OC, VP, 7/November/2012

    SPL beta = 1 cavity

    assembly

  • 7/28/2019 FNAL Crab Cavities Dec2012 OC

    4/32

    Functional specification

    OC, 13/December/2012 LHC Crab Cavity Engineering Meeting 4

  • 7/28/2019 FNAL Crab Cavities Dec2012 OC

    5/32

    Parameters

    Cavity

    OC, 13/December/2012 LHC Crab Cavity Engineering Meeting 5

    Parameter Units Value

    Frequency MHz See next page

    Cavity b 1Design gradient MV 3.3 (pushed=5.0)

    R/Q W >300

    Q0 >1 x 1010

    Qext 1 x 106

  • 7/28/2019 FNAL Crab Cavities Dec2012 OC

    6/32

    Parameters

    Cavity

    OC, 13/December/2012 LHC Crab Cavity Engineering Meeting 6

    Parameter Units LHC SPS

    Beam Energy GeV 7,000 55 120 270

    Frequency MHz 400.79 400.b 400.c 400.c

  • 7/28/2019 FNAL Crab Cavities Dec2012 OC

    7/32

    Dimensions

    Cavity

    OC, 13/December/2012 LHC Crab Cavity Engineering Meeting 7

    R. Calaga, Superconducting Technologies Workshop, Dec. 2012

  • 7/28/2019 FNAL Crab Cavities Dec2012 OC

    8/32

    Dimensions

    RF design for internal shape at cold

    Design for manufacturing by scaling:

    Warm (room temperature)/cold shrinkage

    Shape modification due to EP, BCP, .. Deformation due to operation conditions

    (internal vacuum + external pressure)

    Integration specification takes into account

    external dimension (including wall thickness) of

    the cavity as manufactured, at room temperature

    Cavity

    OC, 13/December/2012 LHC Crab Cavity Engineering Meeting 8

  • 7/28/2019 FNAL Crab Cavities Dec2012 OC

    9/32

    Position of 2nd beam pipe: 4-ROD

    Vittorio Parma, Loren Wright

  • 7/28/2019 FNAL Crab Cavities Dec2012 OC

    10/32

    Position of 2nd beam pipe: RF-Dipole

    Vittorio Parma, Loren Wright

  • 7/28/2019 FNAL Crab Cavities Dec2012 OC

    11/32

    Position of 2nd beam pipe: QWR

    Vittorio Parma, Loren Wright

  • 7/28/2019 FNAL Crab Cavities Dec2012 OC

    12/32

    Dimensions

    Maximum radius external dimension

    (including wall thickness) at room

    temperature < 145 mm

    Cavities dimensions to be revisited (reduced)

    Cavity

    OC, 13/December/2012 LHC Crab Cavity Engineering Meeting 12

  • 7/28/2019 FNAL Crab Cavities Dec2012 OC

    13/32

    RF Multipoles

    Cavity

    OC, 13/December/2012 LHC Crab Cavity Engineering Meeting 13

    R. Calaga, Superconducting Technologies Workshop, Dec. 2012

  • 7/28/2019 FNAL Crab Cavities Dec2012 OC

    14/32

    SPS tests

    Frequencies at SPS tests to be adjusted with tunerduring operation (slow tuning needed only) set

    only once (between 400.c and 400.d ~ 10kHz)

    Detuning (when cavity not in use)

    Range of detuning required: + or - 1.5 kHz 200 Hz

    Time requirements: fast tuning (fast to be defined in

    more detail)

    Tuning

    OC, 13/December/2012 LHC Crab Cavity Engineering Meeting 14

    Parameter Units LHC SPS

    Frequency MHz 400.79 400.b 400.c 400.d

    Bandwidth Hz 400 400 400 400

  • 7/28/2019 FNAL Crab Cavities Dec2012 OC

    15/32

    LHC operating frequency

    Detuning (when cavity not in use)

    Range of detuning required: + or - 1.5 kHz 200 Hz

    Time requirements: fast tuning (fast to be definedin more detail)

    Tuning

    OC, 13/December/2012 LHC Crab Cavity Engineering Meeting 15

    Parameter Units LHC SPS

    Frequency MHz 400.a 400.b 400.c 400.d

    Bandwidth Hz 400 400 400 400

  • 7/28/2019 FNAL Crab Cavities Dec2012 OC

    16/32

    Frequency

    Bandwidth of 400 Hz ()

    mm/kHz (cavity specific) => cavity stability and

    shape adjustment in the order of 10 nm !

    Mech. design compromise between

    Rigidity to ensure stability (Lorentz

    detuning, )

    Flexibility to ensure tunability

    Remark: tuner to work in one direction (or

    compensate for play)

    Tuning

    OC, 13/December/2012 LHC Crab Cavity Engineering Meeting 16

  • 7/28/2019 FNAL Crab Cavities Dec2012 OC

    17/32

    Process for tuning taking into account

    Deformation during manufacturing O(MHz)

    Processing (hundreds kHz)

    Cold/warm (hundreds kHz)

    Operating conditions (< kHz)

    Tuning

    OC, 13/December/2012 LHC Crab Cavity Engineering Meeting 17

  • 7/28/2019 FNAL Crab Cavities Dec2012 OC

    18/32

    Temperature

    Operating temperature 2 K(saturated superfluid helium)

    Heat losses to be evaluated in detail

    dimensioning of helium tank, cryo-module andcryo-plant accordingly

    Static

    Dynamic

    ~ 3 W / cavity

    But exact and realistic value (especially for SPS

    tests) important to estimate and measure

    Helium tank

    OC, 13/December/2012 LHC Crab Cavity Engineering Meeting 18

  • 7/28/2019 FNAL Crab Cavities Dec2012 OC

    19/32

    Helium tank to be dimensioned correctly to

    extract maximum heat load Heat flux in He II depend on bath temp. and

    channel dimension

    Helium tank

    OC, 13/December/2012 LHC Crab Cavity Engineering Meeting 19

  • 7/28/2019 FNAL Crab Cavities Dec2012 OC

    20/32

    Helium tank to be dimensioned correctly

    to extract maximum heat load

    If helium cross section expected to

    extract (order of magnitude)1 W/cm2 => detailed calculations

    needed

    Helium tank

    OC, 13/December/2012 LHC Crab Cavity Engineering Meeting 20

  • 7/28/2019 FNAL Crab Cavities Dec2012 OC

    21/32

    Interfaces

    Ideally same helium tank and interfaces for all cavitiesnot realistic?

    Standardization of interfaces for all cavities assemblies -is a very strong requirement

    Choice of helium tank material (stainless steel /

    titanium) strong impact on transitions:

    Beam pipe (suggestion to use SS for flanges)

    Cryo-module piping

    HOM (and LOM) extraction, Main power coupler,

    Pick-up

    Helium tank

    OC, 13/December/2012 LHC Crab Cavity Engineering Meeting 21

  • 7/28/2019 FNAL Crab Cavities Dec2012 OC

    22/32

    Remark:

    Design (cavity and helium tank) to take into

    account:

    Interfaces for handling and transport

    Interfaces for cavity processing

    Interfaces for vertical tests at cold

    Interfaces for alignment in cryomodule

    Helium tank

    OC, 13/December/2012 LHC Crab Cavity Engineering Meeting 22

  • 7/28/2019 FNAL Crab Cavities Dec2012 OC

    23/32

    Pressure

    Operating helium pressure ~ 20 mbar

    Pressure stability: 1 mbar

    Design cavities for sensitivity to

    pressure fluctuation accordingly (200

    Hz/mbar would be too large)

    Cavity bandwidth 400 Hz => sensitivity

    to pressure fluctuation should be

    significantly lower.

    Helium tank

    OC, 13/December/2012 LHC Crab Cavity Engineering Meeting 23

  • 7/28/2019 FNAL Crab Cavities Dec2012 OC

    24/32

    Pressure

    Maximum pressure (transients)

    Safety valve set pressure 1.8 bar

    Rupture disc 2.2 bar

    Pressure equipment

    All the cryo-module assembly:

    cavitie(s), helium tank(s), vacuumvessel to be treated for the same risk

    category as the most critical one

    Helium tank

    OC, 13/December/2012 LHC Crab Cavity Engineering Meeting 24

  • 7/28/2019 FNAL Crab Cavities Dec2012 OC

    25/32

    CERNs safety policy regarding pressure equipment:

    The general requirements for mechanical equipment during its life-cycle are defined by

    a specific General Safety Regulation;

    A General Safety Instruction defines the requirements specific to pressure equipment;

    Some general requirements:

    A Safety File of the equipment shall be prepared and updated by the Department;

    A risk analysis shall be carried out in order to assess critical loading scenarios;

    Full traceability shall be ensured from design to commissioning;

    The following documentation applies by order of priority:

    Internal Specific Safety Instructions

    European Union Directives

    European Directive 97/23/EC on the Approximation of the laws of the

    Member States concerning pressure equipment

    Harmonised European Standards

    EN 13445, EN 13458, (...)

    Helium tank

  • 7/28/2019 FNAL Crab Cavities Dec2012 OC

    26/32

    The application of the European Directive for pressure equipment 97/23/EC:

    Covers pressure equipment with a maximum

    allowable pressure greater than 0.5 bar (gauge)

    Defines the essential safety requirements which allow to comply

    with the directive & allow free movement within the EU market

    The equipment is classified into risk categories according to

    their stored energy and the hazard of the fluid

    For each risk category, modules allow to assess conformity

    The adoption of European Harmonised Standards ensures

    conformity with the requirements of the Directive

    Table for assessment of risk category

    Front page: Directive 97/23/EC

    Higher Risk Categories require the participation of Notified Bodies

    Helium tank

    H li k

  • 7/28/2019 FNAL Crab Cavities Dec2012 OC

    27/32

    The application of the European Directive for pressure equipment 97/23/EC:

    o Harmonised European Standards for the design, fabrication and inspection of pressureequipment, which ensure conformity with the Directive 97/23/EC:

    EN 13445 Unfired Pressure Vessels

    Part 1: General

    Part 2: Materials

    Part 3: Design

    Part 4: Fabrication

    Part 5: Inspection and testing

    Other parts: 6, 7, 8 & 9

    EN 13458 - Cryogenic vessels - Static vacuum insulated vessels

    Part 1: Fundamental requirements

    Part 2: Design, Fabrication, Inspection and Testing

    Part 3: Operational requirements

    Helium tank

    H li t k

  • 7/28/2019 FNAL Crab Cavities Dec2012 OC

    28/32

    Pressure equipment

    Remark:All the cryo-module assembly: cavitie(s),

    helium tank(s), vacuum vessel to be

    treated for the same risk category as the

    most critical one

    Could be treated at CERN as special

    equipment: not necessity of the CE

    marking but same quality requirements

    For 1.8 bar pressure relieve valve =>

    design for 1.8*1.43 = 2.6 bar for cavity ext

    pressure, helium tank internal pressure

    Helium tank

    OC, 13/December/2012 LHC Crab Cavity Engineering Meeting 28

    H li t k

  • 7/28/2019 FNAL Crab Cavities Dec2012 OC

    29/32

    Pressure equipment example of safety file

    Helium tank

    OC, 13/December/2012 LHC Crab Cavity Engineering Meeting 29

    H li t k

  • 7/28/2019 FNAL Crab Cavities Dec2012 OC

    30/32

    Helium tank

    OC, 13/December/2012 LHC Crab Cavity Engineering Meeting 30

    Pressure equipmentexample of some manufacturingrequirements for a category I equipment

    Materials

    All materials have to be supplied with a certification of type

    3.1 according to EN 10204:2004 (compliance with the order

    and indication of test results attested by the manufacturer) Materials covered by Harmonised European Standards

    automatically do comply with the requirements of PED

    Remarks:

    Niobium and Titanium not covered by the HarmonisedEuropean Standards

    In the frame of special equipment it can be accepted on

    the basis of the risk analysis and of proven behavior at

    operating temperature

    H li t k

  • 7/28/2019 FNAL Crab Cavities Dec2012 OC

    31/32

    Pressure equipment example of somemanufacturing requirements for a category I equipment

    Every weld shall be identified on manufacturing

    drawings and linked to an appropriate weld

    procedure:

    Welding procedure specification (WPS) / Brazingprocedure specification (BPS);

    Welding procedure qualification record (WPQR)/ Brazing

    procedure approval record (BPAR);

    Welding operators qualification /Brazer approval;

    Radiographic inspection of 25% of the total

    circumferential seams and 100% of the total

    longitudinal seams.

    ...

    Helium tank

    OC, 13/December/2012 LHC Crab Cavity Engineering Meeting 31

    M ti hi ldi

  • 7/28/2019 FNAL Crab Cavities Dec2012 OC

    32/32

    Static magnetic field shielding required

    The field to be below 1 T at the outer

    surface of the cavity

    Numerical simulations to determine the

    material thickness and specification, aswell as geometry

    Recommended to evaluate the effect

    inside and outside the helium vessel(compatible with cavity compactness

    requirements)

    Magnetic shielding

    OC, 13/December/2012 LHC Crab Cavity Engineering Meeting 32