Geometallurgical capability at Ausenco and
how it might support Process Design
Presented by Simon Michaux | 8 August 2012
Geometallurgical capability at Ausenco and how it might support Process Design | 8 August | 2
Geometallurgy is about cross-
discipline integration..
a team-based approach to support a rock-based manufacturing process
Everyone has to change their perception and their language describing
the mining process to create a new discipline
Economic justification of geomet
More intelligent full scale test (DWT) sampling to produce
a result that works well as opposed to works OK
Fit for purpose quantification of variability in a processing
context
Used as a design tool to determine the most efficient style
of circuit
Risk management of process performance of designed
plant
More sophisticated modeling of economic net position
Geometallurgical capability at Ausenco and how it might support Process Design | 8 August | 3
Geomet can be used to turn a Type 4 into a Type1 operation
NPV makes the first few years critical to successful operation
Plant design
capacity
Fast run up to
full capacity
Slow run up to
partial capacity
Geometallurgical capability at Ausenco and how it might support Process Design | 8 August | 4
The efficiency in which capital, labour, materials,
services, and energy are utilised to generate a
unit of product
Multifactor productivity
Australian Bureau of Statistics 2011, Experimental Estimates of Industry Multifactor Productivity, 2010-11, ABS, Cat no:
5625.0.55.002, Canberra.
50
60
70
80
90
100
110
Ind
exe
d 2
00
0-0
1 =
10
0
Topp et al. (2008) ABS (2011)
It now takes 40% more inputs to generate a single unit of
mineral product
Australian Bureau of Statistics 2011, Experimental Estimates of Industry Multifactor Productivity, 2010-11, ABS, Cat no: 5625.0.55.002, Canberra.
Geometallurgical capability at Ausenco and how it might support Process Design | 8 August | 5
About 2-3% grade was the operational threshold
Bingham Kennecott
(Grade=0.2-0.57%)
Geometallurgical capability at Ausenco and how it might support Process Design | 8 August | 6
Economic goal posts are shifting for future deposits (compared to 30 years ago)
Huge low grade deposits
Operating on an economy of scale never been seen
before (4MT blasted rock a day, 60% of which is
ore!)
Energy & water shortages
Penalty minerals present in deposit that prevent
efficient processing
Ever decreasing grind sizes
Economic penalties for carbon footprint
Challenging site locations with social issues are
influencing decision making of final outcome
Geomet in the short term is about risk mitigation, reducing costs and extracting more profit.
In the long term it could be used for mine sites to start at all and to stay in business.
Geometallurgical capability at Ausenco and how it might support Process Design | 8 August | 7
The pickle and the rub for our clients
NPV
Capital Cost
If this ratio is too low, then the project doesnt start
Projects are paid for by net profit from high grade parts of
the deposit processed in the short term. There seems to
be no Plan B if there are no high grade parts!
So what is the
real NPV?
What is the real
needed plant
size?
Geometallurgical capability at Ausenco and how it might support Process Design | 8 August | 8
Geometallurgy is about cross-
discipline integration..
The rock is the Rosetta Stone for the mining process. All stages of
mining measure it and design from those measurements.
Geometallurgical capability at Ausenco and how it might support Process Design | 8 August | 9
Rename Geometallurgy: Leveraging Rock Properties
(LRP)
The geologists view of rocks
Geologists have a predisposition to describe rocks in terms of their genesis.
The language is interpretative, often influenced by exploration and at times
poetic..
Geometallurgical capability at Ausenco and how it might support Process Design | 8 August | 10
The mineral processing view of rocks
A bulk feed material for a manufacturing process that should be described in
terms of its processing characteristics and variability relative to specification.
Tell me what my feed is relative to size not what the rock used to be
Geometallurgical capability at Ausenco and how it might support Process Design | 8 August | 11
Challenge of scale-dependent views W
ha
t th
e g
eo
log
ists
se
e a
t co
re s
ca
le
Wha
t the
grin
din
g a
nd
flota
tion
circ
uits
se
e
Geometallurgical capability at Ausenco and how it might support Process Design | 8 August | 12
Geometallurgy is process defined data relationships
The Holy Grail:
the multi-shell geomet
block model as
a stand alone complex
Everyone has a definition
Geomet is ore response behaviour
data interrelationships
Rename Geometallurgy: Leveraging Rock Properties
(LRP)
Geometallurgical capability at Ausenco and how it might support Process Design | 8 August | 13
Trends Rankings Calibrations Behaviors
Assays
Rock type
Alteration
Hardness
Mineralogy
Texture..
Ci Index
A*b values
Grind Index
Recovery
Texture-based
finite element
modelling
Turning data into processing attributes
Geometallurgical dataset building
Indirect
proxies
Direct
Proxies Direct
Measures
Linking
Models
Geometallurgical capability at Ausenco and how it might support Process Design | 8 August | 14
For a given job, where are you in the mining cycle?
Very different approaches
& methodologies
Resource Model
Geomet passed into block models
Issues of additivity and intrinsic vs.
derived attributes
Process Mill Design
Key output built on long term models
Crucial decisions usually driven by
engineering
Deposit Valuation
Understanding economic implications
of geomet changes to resource
model and operational outcomes
Linking geomet variability with
conditional simulation
Risk mitigation
Life of Mine Simulation
Total site footprint
Mine closure and environmental
rehabilitation
Geomet for long term variability
Conceptual Study
Pre-feasibility
Feasibility
Process Design
Life of Mine Footprint Simulation
Geomet for scheduling
Scheduling & Life of Mine Planning
Geomet for operations
Detailed Study Process Design
Commissioning start up
Operation and production
Expansion
Life of Mine Simulation
Total site footprint
Mine closure and environmental
rehabilitation
Process Operation
Show stoppers & penalties in feed
stream (clay, Cl, Fl, As, etc)
Predicted variability in ore hardness
Metal reconciliation
Maintenance schedule
Environmental site impact & rehabilitation
Dust generation
Acid Mine Drainage
Tailings management
Geomet for Enviro Impact
Geometallurgical capability at Ausenco and how it might support Process Design | 8 August | 15
Support Mine Design
Sup
po
rt M
ine
Sch
ed
ulin
g
Economic Scenario Assessment
Blo
ck M
od
el
Ge
ne
rati
on
Process Design
Envi
ron
men
tal
Imp
act
The geomet plan..
Conceptual Study
Pre-Feasibility Study
Feasibility Study
Detailed Study
Geomet Study
Economic Scenario Study
Geometallurgical capability at Ausenco and how it might support Process Design | 8 August | 16
Geomet test scope 1500-2000m of half drill core
siteDiscontinuous destructive tests
Develop process defined efficiency ranking
1000s of data points for a single study
Each sample has multiple
tests/signatures from the same spatial
point (2m interval of core)
Data collected by client and assay lab
(ALS Chemex)
Each comminution Ci test is of the
order of $50
Data analysis is a couple of weeks
once data collected
Geometallurgical capability at Ausenco and how it might support Process Design | 8 August | 17
0
20
40
60
80
100
120
140
160
180
6.00 8.00 10.00 12.00 14.00
Axb
BMWi @212 mm cls
Ernest Henry
18
A*b as a function of BMWi Ernest Henry
KSpar dominant
324
Carbonate-magnetite
236
246
377
428
211 481
290