geotechnical engineering ecg 503 lecture · pdf filegeotechnical engineering ecg 503 lecture...
TRANSCRIPT
GEOTECHNICAL ENGINEERING
ECG 503
LECTURE NOTE 07
TOPIC : 2.0 SLOPE RISK
ENGINEERING
AUGUST 2008
TOPIC TO BE COVERED
Slope rehabilitation works
Post mortem analysis,
rehabilitation technique such as
soil nailing, grouting,
engineered slope stability
structures
FORENSIC WORKS
• SITE INVESTIGATION (S.I.)
• SLOPE FAILURE TYPES
• SLOPE FAILURE CAUSES
• SLOPE REHABILITATION WORKS
SITE INVESTIGATION
• Slope Mapping
• Site survey by visual aspect
• Ground water observation
• Indication of geological materials
• Drainage system observation
• Water ponding
• Site Testing
SITE INVESTIGATION cont’
• Laboratory Testing
• Preparation of S.I. Report
SLOPE FAILURE TYPES
• Sliding
• Fall
• Erosion
• Toppling
• Planar
• Wedge
SLOPE TREATMENT
• Short-Term
a. Tarpaulin
• Long-Term
a. Turfing f. Masonary Wall
b. Guniting g. Sheet Pile
c. Gabions h. Rock Bolts
d. Cribwall i. Netting
e. Concrete Wall j Soil Nails
Soil Nailing In Slopes Stabilization
• Proven cost, used to cut slopes or to support deep
excavation by reinforcing the insitu ground. (Drilling,
inserting bar, grouting and nail head construction/
facing/ guniting.)
• Pull-out resistant of the reinforcing element.
– Practice : estimated based on soil data with reference
to empirical observations.
– On site : pull-out test result derived from full scale
verification/ sacrificial tests.
Soil Nailing In Slopes Stabilization
• Some slope movement is required to mobilize load
tension in the soil nail (up to 30mm).
• Lateral displacement due to stress-relief of excavated
steep soil nailed slope/ wall is about 0.1-0.3%H.
• When lateral deformation exceed 0.5%H, excessive
bending and shear in soil nails may happen, resulting in
excessive creep and tension cracks in upslope or
eventual slope failure, if left unattended.
Soil Nailing In Slopes Stabilization
• Soil nails need to extend to sufficient length beyond
the active zone or any plane of weakness to overcome
external stability including overturning, sliding,
bearing and overall slope instability, modes of failure.
• Three internal failure modes must be checked to
ensure an adequate factor of safety, i.e. nail pull-out
resistance, nail material tensile capacity and nail head/
facing capacity.
Drilling Method
• Characteristics:
– Constant straight diameter
– Stable drill hole
– Drilling debris wholly
– Cleanly removed are achievable.
• The rotary percussion method
– Using top hammer or down-the-hole hammer
– Capable of completing the drill hole within a short time (<1hour) should normally used.
Drilling Method
• Observation of the drill log
– Location
– Time/ duration
– Soil type/ strata
– Changes in penetration rate/ sound
– Flushing characteristics (wetness, color, nature and
sizes of cutting…)
Installation Of Reinforcement Bar
• For permanent works, rebars should be protected against corrosion by hot-dip galvanizing (BS729) with a minimum coat thickness of 85microns or 610gm/m2.
• Rebars only need to be protected in corrugated HDPE stealth for cases of proven aggressive soil (pH value <4.5; or sulphate >200ppm; or chlorite content >100ppm.)
Installation Of Reinforcement Bar
• Centralizers should be made from galvanized steel
or other suitably high quality material
dimensioned to fit the rebar at the centre of the
hole whilst not obstructing passage of cement
grout pipe.
Nail Head
• Guniting facing
• HDPE Geocell slope
protection system
• Grid beam system
For green vegetative
slope landscape
CASE STUDY
SLOPE FAILURE AT
KOMPLEKS IMIGRESEN,
PENGKALAN HULU,
PERAK DARUL RIDZUAN
WHAT WOULD YOU DO?
?
SITE INVESTIGATION
INTRODUCTION
The proposed site of construction for Kompleks Imigresen Pengkalan Hulu is located at the boundary of Thailand and Malaysia, about 60 km north of Grik town in the upper Perak region, through access road to Betong, Thailand.
The proposed site area is experienced slope failure and high water table problems. The landslide had occurred at the slope, close to proposed construction of Kompleks Imigresen Pengkalan Hulu
OBJECTIVE
The objectives of works to be carried out are :
– To understand subsurface condition and
geology at study area
– To understand type of slope failure.
– To determine probable causes of failure.
– To propose mitigation measures.
– To obtain soil type, soil strength
parameter for slope stability analysis.
SITE LAYOUT
GEOMORPHOLOGY OF
LANDSLIDE AREA
The original geomorphology of Pengkalan
Hulu and surrounding area is characterized
by mountainous terrain. Hills and valley in
this area can be clearly seen from the digital
terrain model (DTM) generated from the
topographic map of the area
GEOTECHNICAL
PARAMETERS
LOCATION OF BOREHOLES
AND PROBE MACHINTOSH
TO DETERMINE THE SOIL
PROFILE AND SOIL STRATA
DETERMINATION OF FOS
MOST PROBABLE CAUSE OF
FAILURE
• Presence of Geological Weak Material
The presence of Carbonaceous Shale probably mainly due to high organic carbon content. The Carbonaceous Shale are argillaceous deposits containing carbonaceous matter that induces a dark colour, between grey and black depending on the concentration of the carbonaceous matter. This is an extremely fine-grained rock consisting of quartz, sericite, chlorite, feldspar, clays and carbonaceous materials. This rock seems brittle, slickenside at the plain , dull luster and its recumbent fold.
• Increase in negative Pore Water Pressure
Based on the data obtained from the investigation
and analysis it was observed that the most
probable cause of failure is due to extensive
increase in negative pore water pressure in the
soil. The increase in this negative pore water
pressure will reduce the shear strength of the soil
thus weakening the integrity and stability of the
cut slope. The indication of seepage water from
the ground can be seen after the failure which
resulted in flow of water from the slope surface.
• Improper Drainage System
Improper drainage system on the cut slope area
may resulted in the penetration of runoff water
thus increasing the groundwater table in this area.
Some of the drainage system in this area seems to
be not functioning as required to channel the
runoff water to its outlet. Proper subsoil drainage
has not been installed on site to lower down the
groundwater table in this area.
• Characteristic and Weathering Process of Subsoil
The occurrence of weak zone in the subsoil
material which is highly decomposed as in contact
with water may have its contribution to the cut
slope failure. High groundwater table has
weakening the subsoil material thus creating a
weak layer to trigger the slip circle failure.
Completely Weathered (Grade V) of interbeded
shale and mudstone layer are very sensitive with
water. The occurrence of water in this layer may
weaken the characteristic strength of this material.
MECHANISM OF FAILURE
• Initially the cut slope was cut at a gradient of 1V : 1H with a 6m high slope and a 1.5m benches. Berm drain and cut off drain was constructed to channel out runoff water in this area. Hydroseeding was implemented to the slope surface however less than half of the surface areas were vegetated. This is due to the nature of the subsoil material which unable vegetation to growth on the soil.
• As the drainage system in this area are poorly constructed some of the drains has collapsed which enable runoff water to penetrate into the subsoil material.
• Circular type of slip failure occurred which then moves in retrogressively starting from the crest of the top slope downward to the toe of the slope. The increase in negative pore water pressure, which leads to weakening of the soil strength characteristic, has lead to the slip failure on the cut slope.
REMEDIAL AND MITIGATION
MEASURES
• Short Term Measures
Short term measures shall be carried out immediately to prevent slope failure area from getting worst. Tarpaulin sheet should immediately installed at all failure area to prevent further increase in negative pore water pressure to ensure the failure from propagate.
• Long Term Measures
Soil Nail, Allan Block 12 Wall and Green Terramesh
Reinforced Earth Slope
This comprises of installation of soil nail made up
of a 12m long Y25 bar inserted into a 100mm
diameter drilled hole which in turn will be grouted
to the full length. The spacing of the soil nail is
proposed to be at 1.5m c/c interval. The soil nail will
increase the existing factor of safety of the cut slope
by providing resistance to the overturning forces.
Horizontal drain of 75mm diameter perforated
UPVC pipe of 12m length shall be installed to reduce
the negative pore water pressure thus reducing the
groundwater along this area.
Green Terramesh system was to be installed on the
front face of the cut slope which has been installed by
soil nail. The installation of Green Terramesh will
increase the internal stability and provide aesthetical
features to the finishes of the cut slopes. Allan block wall
will also be installed on the front face of the cut slope at
the bottom portion as will increase the internal stability
of the cut slope. The drainage system within the area
shall be upgraded to ensure the surface erosion will not
take place after the treatments implemented. A new
drainage system will be introduced to integrate with the
existing drainage system.
ALLAN BLOCK
GREEN
TERRAMESH
UPGRADING
DRAINAGE SYSTEM
ALLAN BLOCK
GREEN
TERRAMESH
GREEN
TERRAMESH