glassboro state college swimming pool
DESCRIPTION
Repairs to olympic size swimming pool with TecSealtm utilizing cement grout curtainTRANSCRIPT
T
E
C
H
N
I
C
A
L
R
E
P
O
R
T
TecSealtm
Negative Force
Leak Repair Process
is
An Improved Method of Repairing
Leaks in Concrete, Masonry & Stone
Report of Cementitious Grouting of Leaking Fractures and
Cavitation Filling Sealing With
TecSealtm
Glassboro State College
Glassboro, NJ
TECVAC, Inc. ¤ 39482 Rickard Road Lovettsville, VA 20180
Office 703.742.9186 ¤ FAX 703.742.9231 TECVAC, Inc.
1998 © ALL RIGHTS RESERVED
1
Leak Repairs to Swimming Pool
Glassboro State College
Glassboro, NJ
In the final stage of completion, the general contractor was defaulted by
the bonding company and its incompleted construction of the student activities
center was left in disarray. Among other things, ground water was leaking
profusely into the olympic size swimming pool that was constructed within the
student activities building facility and nearly completed.
Careful evaluation of the condition of the shotcrete construction of the
pool by the bonding company and their engineers, coupled with the concerns of
the College Administration Board and their intent to receive a finished product
conforming to the very stringent standards of NCAA, leaned the reconciliation
talks toward total tear out and re-construction of the entire pool. This action
presented a formidable and costly proposition for the bonding company and any
completion contractor.
Vacuum Technicians were summoned to evaluate the conditions and
whether or not the Vacuum Injection/Impregnation Processes could be capable
of restoring the originally intended construction quality of the pool. More
importantly, whether or not the Vacuum Processes would be capable of
producing a water-tight structure.
After an attentive review of the as-built conditions, a plan was developed
and proposed a turn-key repair. A repair that would guarantee the employed
methods would meet the requirements of the bonding company and that would
be acceptable to the Administration of the college.
An Impact-Echo survey was first performed on the floor and walls of the
swimming pool that accurately located the defects. These defects were
identified as including delaminations, fractures and voids and were mapped
upon a grid chart for later repair reference.
To combat the high water table, evident to within five feet of the top of the
pool, and to relieve the hydrostatic pressures, a deep well and large pumping
system were installed and located on the exterior of the student activities
building. After the water table was receded well below the bottom elevation of
the pool floor, grouting crews accessed the exterior sides of the walls and floor
of the pool and installed a cementitious grout curtain. This cement curtain
completely enveloped the pool structure with a three-four inch layer of
waterproofing cement.
2
Then, after each of the located defects in the structure were repaired
using the Vacuum Injection/Impregnation Process, another independent Impact-
Echo survey was performed to inspect the extent and integrity of the repairs
completed, and to ensure no other defects had been missed.
Upon completion of the cementicious grout curtain installation, repairs of
the mapped defects in the pool walls and floor, and the final independent survey
of the repairs, an ultimate test of the entire work was at hand; the pumps were
turned off, allowing the ground water to again seek its high level surrounding the
pool.
After fourteen hours, the water was determined to be within five feet of the
top of the pool and the repairs to walls and floors were inspected for leaks.
There were none.
After thirty-six hours of continuous exposure to the hydrostatic pressures
of the high water table, there was not one single leak discovered within the pool.
The repairs were deemed a success and the pool finishing operations, coatings
and tile, were then completed.
The repairs performed were estimated to have saved the bonding
company over $1 million when compared with their only other alternative,
complete tear out and replacement of the structure.
Tecvac, Inc.
39482 Rickard Road
Lovettsville, VA 20180
Office 703 742-9186
Fax 703 7429231
Toll Free 800 847-9324