jsa - crane setup

Upload: abdullah-ghannam

Post on 01-Jun-2018

432 views

Category:

Documents


18 download

TRANSCRIPT

  • 8/9/2019 JSA - Crane Setup

    1/12

    Page 1 of 12

    JOB HAZARDANALYSIS

    PFEIFFERCranes Pty LtdCONTACT: PFEIFFER CRANES

    JOB DESCRIPTION: SETTING/PACKING UP CRANE ONSITE

    Contacts:

    Delcie Pfeiffer Director 0427 936 300

    Fred Pfeiffer Director 0417 057 659Daniel Pfeiffer Crane Operator 0407 877 340

    Craig Pfeiffer Crane Operator 0407 877 334

    Jack Pfeiffer Engineer 0417 362 783

    Trinity Pfeiffer OHS 0417 545 813

  • 8/9/2019 JSA - Crane Setup

    2/12

    Job Hazard Analysis Study

    Pfeiffer Cranes Pty Ltd 2

    1.

    ISSUES/HAZARDS & RECOMMENDATIONS FOR CRANE SETUP

    The JHA study minutes are presented in the following pages. The table presents the task step, identified issue or hazard, initial risk, controls(where necessary), residual risk, to be actioned by, and completion sign off.

    Task Step Identified Issue/Hazard RiskC,H,M,L

    Controls

    (consider hierarchy of controls)

    ResidualRisk

    C H M L

    Action By CompletionSign Off

    Break down the task into itsnormal sequence of basic

    steps. Describe what is done,not the details of how it isdone.

    For each step, define the safety hazards,risks and concerns- by answering the what

    if questions about inherent processhazards.

    Leve

    lofrisk

    For each hazard or risk, define the control measures that will beimplemented to prevent injury, exposure, incident, damage etc.

    Re-a

    ssesstherisk

    (controlsinplace).

    Assign anaccountable

    person forimplementing thecontrol

    Accountable personto sign to indicate

    control is in place.

  • 8/9/2019 JSA - Crane Setup

    3/12

    Job Hazard Analysis Study

    Pfeiffer Cranes Pty Ltd 3

    Task Step Identified Issue/Hazard RiskC,H,M,L Controls(consider hierarchy of controls)ResidualRisk

    C H M L

    Action By CompletionSign Off

    1. Mobile Crane toonsite destination

    2. Pre-job meetingand Toolbox

    3. Locate crane intolifting positions onsite

    Faults with Crane

    Plant becoming bogged insand & mud

    Pedestrians

    Onsite Traffic/plant

    Inexperienced workers

    Inadequate consultation

    Inadequate understanding ofequipment

    Site hazards and emergencyprocedures not known

    Pedestrians

    M

    M

    M

    Pre-start Checks

    Plant to stick to designated roadways and turning areas

    Personnel on hand to warn others of crane movement inthe vicinity or via radio where available.

    Alternate pathway defined by bollards and reflective tape.

    Sufficiently skilled employees to complete task(competencies and Licences)

    Adequate consultation with all relevant employees

    Adequate competent supervision throughout the project

    Proper planning for equipment required for the task Site & work area inductions compulsory for all personnel

    Desired setup area should also be level, unless priorconsultation has been made with the supplier of the crane

    L

    L

    L

    PFEIFFERCRANESEMPLOYEE

    PFEIFFERCRANESEMPLOYYE ANDONSITE MANAGER

    PFEIFFERCRANESEMPLOYEE

  • 8/9/2019 JSA - Crane Setup

    4/12

    Job Hazard Analysis Study

    Pfeiffer Cranes Pty Ltd 4

  • 8/9/2019 JSA - Crane Setup

    5/12

    Job Hazard Analysis Study

    Pfeiffer Cranes Pty Ltd 5

    4. Inspect chains andor slings, shackles,

    hooks andattachment points inpreparation for use

    Pedestrians

    Traffic

    Other Plant

    Other Equipment

    Buildings

    Powerlines & undergroundUtilities

    Lift radius

    Access Ground Conditions

    Tears in Slings

    Cracks in chains, shackles,rings and hooks

    Dropping of load due to faultylifting gear or faultyattachment points

    H

    H

    The workplace is adequately prepared for the incomingmobile crane, including where possible a clear predefinedarea/crane pad for the crane to position upon

    Check and confirm exclusion areas - Barricades, witchesHats, Danger Tape, Warning Signs

    Access road are available and soundly constructed withsuitable entry points to site

    Crew should always inspect site prior to positioning cranein final position;

    Elements to observe include

    Load location and scope of lift

    Location of any overhead obstructions including wires,trees, buildings, restricted airspace (i.e. near airport)

    Location of any underground services and/or trenchesincluding utilities and drainage arrangements that mayaffect integrity of ground

    Adequate room for rigging and erection of mobile crane

    (i.e. support trucks, fly jibs) Adequate tail (counterweight/winch) swing clearance

    Ability to cordon off area with suitable barricadingresources

    Check slings for rips and tears and remove from service isfaults are found

    Check chains, shackles, hooks and rings for cracks,

    corrosion, wears, mechanism faults etc and remove fromservice if faults are found

    Lifting gear/equipment inspected and tagged withappropriate monthly colour tag

    Make certain personnel are sufficiently trained withappropriate certificates/ licences.

    L

    L

    PFEIFFER

    CRANESEMPLOYEE

    PFEIFFERCRANESEMPLOYEE

  • 8/9/2019 JSA - Crane Setup

    6/12

    Job Hazard Analysis Study

    Pfeiffer Cranes Pty Ltd 6

    5. Locate crane inlifting position on site place timbers(pads) and setoutriggers

    Crane overturning due tounstable ground conditions

    Personnel being crushed byoutriggers

    H

    Outriggers must be positioned on a flat surface, usingtimbers or suitable material for pads to evenly distribute theload to the ground

    Crane to be located within the radius for the loads beinglifted.

    Outriggers should only be extended on the side where theoperator is positioned or with a suitable spotter.

    Where space permits, outriggers shall always be fullyextended

    Where space is limited, crane should be configured tomaximum capacity this may require the use of reducedoutriggers or on rubber; when permitted by themanufacturer

    Outriggers shall always be extended to manufacturersprocedures and specifications, including the requirement tofit manual pins

    All outriggers-jacks should be utilized at all time (i.e. Front

    jack) Generally Standard Safe Working Load capacity charts are

    based on all outriggers fully extended and set with wheelsclear of ground.

    Outrigger Packing

    Additional packing should always be utilized underoutrigger floats (exceptions may include engineered setupswhere other means of distributing loads are adopted)

    Commonly used (steel fabricated or otherwise) OutriggerMats should carry design information and be subject toperiodic inspection

    When timber packing is utilized, it should be in a pig-stypacking arrangement

    L

    PFEIFFER

    CRANESEMPLOYEE

  • 8/9/2019 JSA - Crane Setup

    7/12

    Job Hazard Analysis Study

    Pfeiffer Cranes Pty Ltd 7

    6.Attaching Fly or PinJib to Crane

    7. Running wirethrough Sheeves

    8. Positioncounterweight truckin an easilyaccessible spot forthe crane to load its

    counterweights

    Working at heights/falling

    Pinch points/cut or jammed

    hands

    General Plant striking otherplant, equipment, personnel,materials etc

    Dropping counterweights

    Falls from height whilstpositioning and loadingcounterweights

    H

    H

    H

    Rule of Thumb formulae and calculations should beobserved;

    Area (m2) = 0.65 x (Cm + L)

    -------------

    V

    Cm = Total mass of crane (KN)

    L = Total mass of load (KN)

    V = maximum permissible bearing pressure of soil (kpa)

    Follow W/H permit use appropriate attachment point &safety harness when walking along crane boom

    Use an EWP or ladder for this task & follow safe workpractices

    Wear correct PPE

    Plant to be positioned in area clear of obstruction. roads

    Traffic control in place if required

    Once crane is elevated and level, a trial operation shouldbe completed by the operator; this may include

    Luffing boom to high angle, and slewing 360 degrees withspotter in position purpose to review tail swing andoutrigger packing suitability

    Executing dry-run where load is required to be picked upand placed Purpose to ensure crane is capable of taskand set required limits

    L

    L

    PFEIFFERCRANESEMPLOYEE

    PFEIFFERCRANESEMPLOYEE

  • 8/9/2019 JSA - Crane Setup

    8/12

    Job Hazard Analysis Study

    Pfeiffer Cranes Pty Ltd 8

    9. Re-assessingSituation throughoutjob

    10.Packing up and/or

    leaving crane onsite

    Changes in weatherconditions

    Changes in operators

    Changes in ground suitability

    Unauthorised person accesscrane site

    Damage to crane

    Injury to public

    H

    M

    Continual safe operation can be aided by periodicinspection throughout the project of the following;

    Outrigger Jacks Leaking oil/retraction of shaft

    Outrigger Mats excessive settlement and/or sinking intoground; i.e., loadings increasing beyond estimated capacityof ground such as unknown back-filling

    Outrigger Floats Cracking or cr itical damage

    Evidence of water content in ground i.e. Potentialruptured pipeline

    Should requirements change during operation, then crewshall re-assess and review crane capacity and widerenvironment to ensure revised work practice is within limitsand safe to continue operation

    Upon completion of project, or specific stage the craneequipment and site shall be left in a secure and safe

    manner

    If the crane is to be left onsite;

    Retract Boom, remove keys from the ignition andsecure/lock

    Outriggers should be inspected prior to next use

    Barricading should remain in place around the crane and

    any work area deemed necessary

    L

    L

    PFEIFFER

    CRANESEMPLOYEE

    PFEIFFERCRANESEMPLOYEE

  • 8/9/2019 JSA - Crane Setup

    9/12

    Job Hazard Analysis Study

    Pfeiffer Cranes Pty Ltd 9

    11.Packing up andcleaning up work site

    12. Exit site and returnto Depot

    Trip hazards Manual handling injuries Crush & Pinch injuries

    Equipment damage

    Counterweights coming offthe back of the truck

    Crush & pinch injuries

    Falls

    Overhead Powerlines Collision with

    people/personnel and othervehicles/plant when exitingsite

    Counterweights sliding offduring travel

    Traffic Accidents

    M

    M

    M

    Use correct manual handling techniques

    Wear appropriate PPE

    Rubbish to be placed in bins

    Tools & Equipment to be packed

    Lifting gear packed

    Timbers packed

    Pads loaded

    Make certain counterweights are stacked on rubber matsand correctly tied down for trip

    Guide counterweights onto the truck tray with taglines

    Where possible use EWP or Platform Ladder Accessotherwise be cautious of footing

    Crane boom to be down when traveling under power lines

    Maintain site speed limit when exiting work site

    Communicate with other vehicles onsite is necessary

    Observe road rules and take into consideration drivers andriders who dont understand the nature of cranes andtrucks.

    L

    L

    L

    PFEIFFER CRANESEMPLOYEE

    PFEIFFER CRANESEMPLOYEE

    PFEIFFER CRANESEMPLOYEE

  • 8/9/2019 JSA - Crane Setup

    10/12

  • 8/9/2019 JSA - Crane Setup

    11/12

    Job Hazard Analysis Study

    Pfeiffer Cranes Pty Ltd 11

    PLEASE SEND A COPY TO FAX NUMBER OR EMAIL ADDRESS:_________________________________________________________________________

  • 8/9/2019 JSA - Crane Setup

    12/12

    Job Hazard Analysis Study

    Pfeiffer Cranes Pty Ltd 12

    11. RISK ASSESSMENT MATRIXA B C D E

    5 Critical Critical Critical Critical High

    4 Critical Critical Critical High High

    3 Critical High High Medium Medium

    2 High High Medium Low Low

    1 High Medium Low Low Low

    Step 1 - People Consequences

    5 = Fatality or Permanent Disability

    4 = Lost Time Injury or Illness

    3 = Restricted Duties Injury

    2 = Medical Treatment Injury

    1 = First Aid Injury

    or Step 1 - Plant, Property, Process / Environmental Consequences

    5 = More than $500K Damage or production disruption. . Catastrophic environmental impact.

    4 = $100K - $500K Damage and/or production. Major environmental impact.

    3 = $50K - $100K Damage and/or production disruption. Major environmental impact.

    2 = $5K - $50K Damage and/or slight production disruption. Temporary environmental damage.

    1 = Under $5k Damage and minimal productivity disruption. Minor environmental damage.

    Step 2 Determine Probability

    A = Common or frequent occurrence (daily)

    B = Is known to occur or it has happened (weekly)

    C = Could occur or Ive heard of it happening (monthly)

    D = Not likely to occur (yearly)

    E = Practically impossible (ten yearly)

    Step 3 Calculate Risk

    Once determining the probability and consequence, the risk level can be determined by using the matrix above. Thecategories within the matrix are categorised according to the level of risk as follows;

    Critical Consider discontinuing operation

    High Immediate correction required

    Medium Correction needed

    Low Risk is perhaps acceptable as is