    ADMINISTRATIONBUILDING:

    In Progress

    EDITION NO. 7, October 20, 2008

  • 8/14/2019 KSPC Newsletter Vol7_final

    2/92

    Progress in Construction

    of the Administration Building

    In early October, the concrete for the 1st lift of basement floor was placed.

    The works like rebar and form installation for the 2nd lift of basement and 1st

    floor and water curing of the placed concrete were the major activities

    during the middle of October.

    Simultaneously, construction works for the Boiler, Turbine and Control

    Buildings are on-going. Preparations for the chimney stack area have also

    been done while the design calculations have been prepared by the

    contractor.

    Next months major activity will be the rebar, form and staging works for the

    1st floor of the superstructure of the Administration Building.

    On-going works for Administration Building

    (October 14, 2008)

  • 8/14/2019 KSPC Newsletter Vol7_final

    3/93

    Boiler and Turbine Bldg Foundation Progress

    In the month of September 2008, the bored piling works for Boiler No. 1 has

    been finished. Excavation works around the bored pile have proceeded

    during October. After the piles have been exposed, cutting or removing the

    concrete material of that exposed portion will be done. Soil backfilling

    compaction is done to make the excavated ground uniform.

    The installation of re-bars for the foundation will be proceeded. Concrete

    pouring will be done after all necessary installations are placed for the

    foundation. A curing period for the concrete foundation will be observed

    before structural works could be proceeded.

    For Boiler Unit No. 2, bored piling works are still on-going and is projected

    to be finished by the end of October 2008.

    For the Turbine Building, pile works for building foundation are still on

    going. PC piles are used to bear the load of the turbine building. For the

    turbine generator, pedestal bored piles are used and the works has been

    started in October, 2008.

    On-going excavation & pile cutting works for Boiler # 1

    foundation (October 10, 2008)

  • 8/14/2019 KSPC Newsletter Vol7_final

    4/94

    Signing of MOA for MMT, EMF and EGF

    On September 22, 2008, a Memorandum of Agreement (MOA) was mutually

    signed byKEPCO SPC Power Corporation (KSPC) and the Department of

    Environment and Natural Resources Environmental Management

    Bureau (DENR-EMB) at the City Hall of Naga, Cebu, creating the KSPC

    Multi-Partite Monitoring Team (MMT) and establishing the

    Environmental Monitoring Fund (EMF) and Environmental Guarantee

    Fund (EGF) in coordination with the City of Naga-LGU and SPC Power Corp.

    The KSPC-MMT, being a multi-sectoral committee, is represented by DENR-

    EMB, City of Naga LGU, Barangay LGUs, Public Organizations, SPC Power

    Corp. and KSPC with the primary task of monitoring on the environmental

    compliance of the project during construction stage and all throughout the

    operation stage as well as the implementation of various Social Development

    Plan/Corporate Social Responsibilities Program of KSPC.

    One of the contents of the MOA is the Environmental Guarantee Fund

    (EGF) which shall be earmarked for the immediate rehabilitation and

    compensation of affected communities in cases of any damages or accidents.

    Signing of MOA for the creation of MMT, EMF and EGF at the

    City Hall of Naga, Cebu (September 22, 2008)

  • 8/14/2019 KSPC Newsletter Vol7_final

    5/95

    Project Progress

    Close-up of Excavation and pile cutting for Boiler Building #1

    (October 2, 2008)

    Concrete Pouring of Administration Building basement wall

    October 3 2008)

  • 8/14/2019 KSPC Newsletter Vol7_final

    6/96

    Project Progress

    Wall Chipping of Administration Building basement

    October 7 2008)

    Administration Bldg. basement wall after concrete pouring

    (October 3, 2008)

  • 8/14/2019 KSPC Newsletter Vol7_final

    7/97

    Project Progress

    Perimeter Fence of construction siteOctober 7 2008)

    Main Gate of construction site

    (October 14, 2008)

  • 8/14/2019 KSPC Newsletter Vol7_final

    8/98

    Project Progress

    Automatic Truck and Heavy Equipment washing facility

    (October 14, 2008)

    On-going construction works

    (October 14, 2008)

  • 8/14/2019 KSPC Newsletter Vol7_final

    9/99

    Project Information

    PROJECT PROPONENT : KEPCO SPC Power Corporation (KSPC) CAPACITY : 100 MW x 2 Units PLANT TECHNOLOGY : CFBC (Circulating Fluidized Bed

    Combustion)

    LOCATION : Colon, City of Naga (20 Km from Cebu City) TARGET COMPLETION : Unit #1: February 2011; Unit #2: May 2011

    DATE

    Contact us

    Mr. Bag Woon ChoiMr. Beach Padogdog

    KEPCO SPC Power CorporationColon, City of Naga, Cebu

    Tel. No. (032) 272 6290~91, 93

    Fax No. (032) 489 7010