ADMINISTRATIONBUILDING:
In Progress
EDITION NO. 7, October 20, 2008
-
8/14/2019 KSPC Newsletter Vol7_final
2/92
Progress in Construction
of the Administration Building
In early October, the concrete for the 1st lift of basement floor was placed.
The works like rebar and form installation for the 2nd lift of basement and 1st
floor and water curing of the placed concrete were the major activities
during the middle of October.
Simultaneously, construction works for the Boiler, Turbine and Control
Buildings are on-going. Preparations for the chimney stack area have also
been done while the design calculations have been prepared by the
contractor.
Next months major activity will be the rebar, form and staging works for the
1st floor of the superstructure of the Administration Building.
On-going works for Administration Building
(October 14, 2008)
-
8/14/2019 KSPC Newsletter Vol7_final
3/93
Boiler and Turbine Bldg Foundation Progress
In the month of September 2008, the bored piling works for Boiler No. 1 has
been finished. Excavation works around the bored pile have proceeded
during October. After the piles have been exposed, cutting or removing the
concrete material of that exposed portion will be done. Soil backfilling
compaction is done to make the excavated ground uniform.
The installation of re-bars for the foundation will be proceeded. Concrete
pouring will be done after all necessary installations are placed for the
foundation. A curing period for the concrete foundation will be observed
before structural works could be proceeded.
For Boiler Unit No. 2, bored piling works are still on-going and is projected
to be finished by the end of October 2008.
For the Turbine Building, pile works for building foundation are still on
going. PC piles are used to bear the load of the turbine building. For the
turbine generator, pedestal bored piles are used and the works has been
started in October, 2008.
On-going excavation & pile cutting works for Boiler # 1
foundation (October 10, 2008)
-
8/14/2019 KSPC Newsletter Vol7_final
4/94
Signing of MOA for MMT, EMF and EGF
On September 22, 2008, a Memorandum of Agreement (MOA) was mutually
signed byKEPCO SPC Power Corporation (KSPC) and the Department of
Environment and Natural Resources Environmental Management
Bureau (DENR-EMB) at the City Hall of Naga, Cebu, creating the KSPC
Multi-Partite Monitoring Team (MMT) and establishing the
Environmental Monitoring Fund (EMF) and Environmental Guarantee
Fund (EGF) in coordination with the City of Naga-LGU and SPC Power Corp.
The KSPC-MMT, being a multi-sectoral committee, is represented by DENR-
EMB, City of Naga LGU, Barangay LGUs, Public Organizations, SPC Power
Corp. and KSPC with the primary task of monitoring on the environmental
compliance of the project during construction stage and all throughout the
operation stage as well as the implementation of various Social Development
Plan/Corporate Social Responsibilities Program of KSPC.
One of the contents of the MOA is the Environmental Guarantee Fund
(EGF) which shall be earmarked for the immediate rehabilitation and
compensation of affected communities in cases of any damages or accidents.
Signing of MOA for the creation of MMT, EMF and EGF at the
City Hall of Naga, Cebu (September 22, 2008)
-
8/14/2019 KSPC Newsletter Vol7_final
5/95
Project Progress
Close-up of Excavation and pile cutting for Boiler Building #1
(October 2, 2008)
Concrete Pouring of Administration Building basement wall
October 3 2008)
-
8/14/2019 KSPC Newsletter Vol7_final
6/96
Project Progress
Wall Chipping of Administration Building basement
October 7 2008)
Administration Bldg. basement wall after concrete pouring
(October 3, 2008)
-
8/14/2019 KSPC Newsletter Vol7_final
7/97
Project Progress
Perimeter Fence of construction siteOctober 7 2008)
Main Gate of construction site
(October 14, 2008)
-
8/14/2019 KSPC Newsletter Vol7_final
8/98
Project Progress
Automatic Truck and Heavy Equipment washing facility
(October 14, 2008)
On-going construction works
(October 14, 2008)
-
8/14/2019 KSPC Newsletter Vol7_final
9/99
Project Information
PROJECT PROPONENT : KEPCO SPC Power Corporation (KSPC) CAPACITY : 100 MW x 2 Units PLANT TECHNOLOGY : CFBC (Circulating Fluidized Bed
Combustion)
LOCATION : Colon, City of Naga (20 Km from Cebu City) TARGET COMPLETION : Unit #1: February 2011; Unit #2: May 2011