MARIE H. REED COMMUNITY LEARNING CENTER

DISTRICT OF COLUMBIADEPARTMENT OF GENERAL SERVICES

SIT MEETING JUNE 24th, 2015

District of Columbia Public SchoolsMarie H. Reed Community Learning Center DRAFT

OVERVIEWAGENDA

•Purpose&Objectives-thismeeting

•Communitymeetingresults

•Orderofmagnitudecostcomparison-OptionAvsB

•Recommendation

•Siteandbuildingrefinements

•Projectbudget/fundingsources/Allocatedbudget

•CollaborationwithANC

•Legacyexhibitdevelopment

•Nextsteps-Schematicdesign,summermeetings&fallcommunitymeeting

District of Columbia Public SchoolsMarie H. Reed Community Learning Center DRAFT

SUMMARYCOMMUNITY MEETING RESULTS

Option A Pro’s:•Partneringopportunitiesaregreaterwhenallcommunitypartnersremaininthesamefacility•Daylightintheclassrooms•Goodvalueforrequiredinvestment

Option A Con’s:•PhasingforthisoptionispotentiallymoredifficultcomparedtoOption B•Theschoolandcommunitypartnerswouldremainoperationalwhileconstructionishappening•Swingspacewillhavetobeprovided•IfEarlyHeadStartisnotexpanded,willdaycaremeetfutureneeds?•Dislikeofpocketparks•Dislikeusingexistingplaygroundsforparking•Cafeteriaisaloudspace,willitdisruptteaching?

Option B Pro’s:•Phasingispotentiallyeasier,lessdisruptiontothestudents•Morespaceforcommunitypartners.•Providesadditionalparking(Someattendeeswereinfavorofadd-ingparking,somewerenot)

Option B Con’s:•Buildsovertheexistingsoccerwhichwasadonatedtothecom-munity•Separatescommunitypartnersintodifferentbuildings•Noauditoriumspace•Providesadditionalparking(Someattendeeswereinfavorofadd-ingparking,somewerenot)•Eliminationofhalfofexistingbuildingiswasteful•Overbudget,mayleadtoeliminationofprogramcomponents(i.e.pool)

OtherconcernsraisedbytheattendeesforbothOptionsA&Bare:•Security•Needvehiculardrop-offs•Whereisthelibrary?•Needspaceforcommunityevents•Wouldlikemorelanesforthepool•Wouldliketoseephotovoltaicsintegratedintotheproject•Vehicularandpedestriantrafficneedstobeaddressed

District of Columbia Public SchoolsMarie H. Reed Community Learning Center DRAFT

SITECIRCULATIONOPTION A

G4-5 PLAY

G1-3 PLAY

PreK-1 PLAY

District of Columbia Public SchoolsMarie H. Reed Community Learning Center DRAFT

SITEPLANOPTION A

EXISTINGBUILDING

AGES0-5PLAYGROUND

AGES5-8PLAYGROUND

AGES8-12PLAYGROUND

PARKING

PARKING

UTILITY

PLAYAREA&PARK

SOCCERFIELDTE

NNISCOURTS

District of Columbia Public SchoolsMarie H. Reed Community Learning Center DRAFT

PRELIMINARY CONCEPTS

ALTERNATE:POOL ADDITION

ALTERNTE:KIDDIE POOL

ADDITION

OPTIONA-REUSEEXISTINGBUILDING

District of Columbia Public SchoolsMarie H. Reed Community Learning Center DRAFT

EXTERIORPERSPECTIVES

VIEWFROM18THSTREETENTRANCELOOKINGSOUTH

AERIALVIEW

OPTION A

District of Columbia Public SchoolsMarie H. Reed Community Learning Center DRAFT

BUILDINGCIRCULATIONOPTION A

SCHOO

L

ENTRY

PARTNE

RS

ENTRY

SCHOO

L

ENTRY

DPR

ENTRY

District of Columbia Public SchoolsMarie H. Reed Community Learning Center DRAFT

PRELIMINARY CONCEPTSOPTIONA-REUSEEXISTINGBUILDING

EXISTING DEMOLISHBARRELVAULTS

District of Columbia Public SchoolsMarie H. Reed Community Learning Center DRAFT

NEWLEARNINGCOMMUNITIES NEWSKYLIGHTS

PRELIMINARY CONCEPTSOPTIONA-REUSEEXISTINGBUILDING

MEDIA AND PERFORMANCE COMMONS

CAFETERIA

ART AND SCIENCE LIVING LABORATORY

District of Columbia Public SchoolsMarie H. Reed Community Learning Center DRAFT

FLOORPLANS

BASEMENTPLAN

GROUNDFLOORPLAN

OPTION A

9728.75SF

PARKING181

MiddleSchoolProgramLegend

DCPS-BuildingSupport

Parking

556.04SF

MECHANICAL182

220.21SF

UTILITY183

271.50SF

UTILITY184

509.50SF

STORAGE185

363.17SF

UTILITY186

888.56SF

UTILITY187

2586.44SF

UTILITY188

156.44SF

UTILITY189

43.00SF

UTILITY190

31.43SF

UTILITY191

23.75SF

TOILET192

45.68SF

UTILITY193

130.64SF

UTILITY194

58.06SF

STAIR195

121.00SF

STAIR196

122.81SF

UTILITY197

35.67SF

TOILET198

5037.08SF

MULTI-PURPOSEROOM

103

5858.33SF

GYMNASIUM104

962.90SF

LOCKERROOM-WOMEN

105

162.67SF

TOILET106

159.28SF

TOILET107

MiddleSchoolProgramLegend

DCPS-FoodService

DCPS-BuildingSupport

DPR-Recreation

CommunityPartners

956.15SF

LOCKERROOM-MEN

108

365.56SF

STORAGE109

355.11SF

STAGE110

412.56SF

GREENROOM111

130.33SF

FIRSTAIDCENTER112

1512.50SF

DAYCARE113

174.78SF

STORAGE114176.22SF

STORAGE115

174.06SF

TOILET116

174.06SF

TOILET117

13487.11SF

COMMUNITYOFHOPE

118

3831.83SF

WOMENINFANTS&CHILDREN

119

12507.93SF

POOL120

697.67SF

SHOWER-WOMEN

121

878.67SF

SHOWER

-MEN

122

441.22SF

RECEPTION123

321.49SF

DPROFFICE124

147.25SF

TOILET125

147.25SF

TOILET126

323.53SF

STORAGE127

321.49SF

STORAGE128

441.22SF

WARMINGKITCHEN

129

450.78SF

UTILITYROOM130

240.25SF

CHEMICALROOM131

701.79SF

STORAGE132

174.06SF

OUTDOORSTORAGE

133

174.06SF

OUTDOORSTORAGE

134

2793.45SF

LOBBY135

128.82SF

STAIR136

162.17SF

STAIR137

117.62SF

CORRIDOR138

117.62SF

CORRIDOR139

104.50SF

CORRIDOR140

158.79SF

STAIR141

164.21SF

STAIR142

163.53SF

STAIR143

163.53SF

STAIR144

155.89SF

STAIR145

165.20SF

STAIR146

194.06SF

STAIR147

BUILDINGOUTLINEABOVE

UNEXCAVATEDUNDEREXISTINGAUDITORIUMWITHHIGHFOUNDATIONS

1308.00SF

KINDERGARTEN-2

63

1308.00SF

KINDERGARTEN-3

64

1542.29SF

PREK-165

1147.50SF

PREK-267

1168.75SF

KINDERGARTEN-1

68

1168.75SF

PRESCHOOL-169

7997.94SF

CIRCULATION70

1168.75SF

PRESCHOOL-371

3180.93SF

MUSIC72

174.78SF

AFTERCARECLOSET

74

190.00SF

LAPTOPSTORAGE79

176.22SF

AFTERCARECLOSET

81

303.47SF

COMMONS-PRE-K

83

1168.75SF

PRESCHOOL-284

1168.75SF

PREK-385

296.43SF

COMMONS-PRE-S

86

174.06SF

TOILET87174.06SF

TOILET88

6260.82SF

CAFETERIA90

MiddleSchoolProgramLegend

DCPS-CoreAcademicClassrooms

DCPS-FoodService

DCPS-BuildingSupport

DCPS-ElectiveClassroom

DCPS-Administration

908.52SF

TEACHERRESOURCE

92

310.48SF

PARENTRESOURCE

93

1112.58SF

ADMINISTRATION94

162.67SF

TOILET95

159.28SF

TOILET96

333.33SF

RESOURCE97

162.17SF

STAIR148

156.04SF

STAIR149

150.14SF

TOILET150

157.32SF

TOILET151

155.89SF

STAIR152

165.20SF

STAIR153

165.57SF

STAIR154

170.93SF

STAIR155

163.53SF

STAIR156

163.53SF

STAIR157

545.85SF

VESTIBULE158

2263.31SF

CORRIDOR159

323.33SF

OUTDOORSTORAGE

179

901.52SF

FIFTHGRADE-21

901.52SF

FIFTHGRADE-32

892.22SF

WETLAB3

279.83SF

STORAGE-PRIMARY

4

289.99SF

RESOURCE-MATH

5

864.99SF

FIFTHGRADE-16

855.02SF

FOURTHGRADE-3

7

908.33SF

FOURTHGRADE-2

8

908.33SF

FOURTHGRADE-1

9

901.52SF

THIRDGRADE-210

901.52SF

THIRDGRADE-311

906.06SF

SECONDGRADE-2

17

906.06SF

SECONDGRADE-1

18

904.39SF

SECONDGRADE-3

19

880.06SF

THIRDGRADE-120

869.92SF

FIRSTGRADE-221

880.06SF

FIRSTGRADE-122

869.92SF

FIRSTGRADE-323

1017.50SF

VISUALARTSLAB24

894.17SF

FOODLAB25

137.50SF

STORAGE26

63.25SF

KILN27

154.38SF

OFFICE28

154.38SF

OFFICE29

166.75SF

RESOURCE-FOURTH/FIFTH

30

525.44SF

COMMONS-FOURTH

32

525.44SF

COMMONS-FIFTH33

1766.75SF

LIVINGLAB34

742.91SF

WORKROOM35

166.28SF

RESOURCE-SECOND/THIRD

36

413.76SF

COMMONS-THIRD

37

107.47SF

STORAGE38

209.21SF

CONFERENCEROOM

39

912.67SF

PROJECTLAB40

1819.17SF

READINGROOM41

261.09SF

RESOURCE-ESL42

385.25SF

COMMONS43

553.07SF

RESOURCE-SPEECH

45

107.33SF

AFTERCARECLOSET

46

305.52SF

RESOURCE-ESL47

268.97SF

STORAGE-INTERMEDIATE

48

190.00SF

LAPTOPSTORAGE49

304.00SF

RESOURCE-READING

51660.00SF

COMMONS-READING

52

154.26SF

RESOURCE-FIRST

53529.24SF

COMMONS-FIRST/SECOND

55

308.22SF

RESOURCE-ESL56

MiddleSchoolProgramLegend

DCPS-CoreAcademicClassrooms

DCPS-BuildingSupport

DCPS-MediaCenter

DCPS-ElectiveClassroom

DCPS-Administration

165.57SF

STAIR57

176.22SF

TOILET58

176.22SF

TOILET59

165.57SF

STAIR60

172.61SF

TOILET61

172.61SF

TOILET62

174.06SF

TOILET98

174.06SF

TOILET99

176.22SF

TOILET100176.22SF

TOILET101

4947.36SF

PERFORMANCESPACE

102

285.67SF

RECORDSROOM160

48.95SF

STORAGE161

48.95SF

STORAGE162

48.58SF

STORAGE163

48.58SF

STORAGE164

47.87SF

STORAGE165

47.87SF

STORAGE166

56.34SF

STORAGE167

56.34SF

STORAGE168

162.17SF

STAIR169

162.17SF

STAIR170

163.53SF

STAIR171

163.53SF

STAIR172

165.57SF

STAIR173

165.57SF

STAIR174

362.13SF

COMMONS175

4850.94SF

CIRCULATION176

3541.05SF

CIRCULATION177

326.63SF

WELCOMECENTER

178

LEGEND

9728.75SF

PARKING181

MiddleSchoolProgramLegend

DCPS-BuildingSupport

Parking

556.04SF

MECHANICAL182

220.21SF

UTILITY183

271.50SF

UTILITY184

509.50SF

STORAGE185

363.17SF

UTILITY186

888.56SF

UTILITY187

2586.44SF

UTILITY188

156.44SF

UTILITY189

43.00SF

UTILITY190

31.43SF

UTILITY191

23.75SF

TOILET192

45.68SF

UTILITY193

130.64SF

UTILITY194

58.06SF

STAIR195

121.00SF

STAIR196

122.81SF

UTILITY197

35.67SF

TOILET198

5037.08SF

MULTI-PURPOSEROOM

103

5858.33SF

GYMNASIUM104

962.90SF

LOCKERROOM-WOMEN

105

162.67SF

TOILET106

159.28SF

TOILET107

MiddleSchoolProgramLegend

DCPS-FoodService

DCPS-BuildingSupport

DPR-Recreation

CommunityPartners

956.15SF

LOCKERROOM-MEN

108

365.56SF

STORAGE109

355.11SF

STAGE110

412.56SF

GREENROOM111

130.33SF

FIRSTAIDCENTER112

1512.50SF

DAYCARE113

174.78SF

STORAGE114176.22SF

STORAGE115

174.06SF

TOILET116

174.06SF

TOILET117

13487.11SF

COMMUNITYOFHOPE

118

3831.83SF

WOMENINFANTS&CHILDREN

119

12507.93SF

POOL120

697.67SF

SHOWER-WOMEN

121

878.67SF

SHOWER

-MEN

122

441.22SF

RECEPTION123

321.49SF

DPROFFICE124

147.25SF

TOILET125

147.25SF

TOILET126

323.53SF

STORAGE127

321.49SF

STORAGE128

441.22SF

WARMINGKITCHEN

129

450.78SF

UTILITYROOM130

240.25SF

CHEMICALROOM131

701.79SF

STORAGE132

174.06SF

OUTDOORSTORAGE

133

174.06SF

OUTDOORSTORAGE

134

2793.45SF

LOBBY135

128.82SF

STAIR136

162.17SF

STAIR137

117.62SF

CORRIDOR138

117.62SF

CORRIDOR139

104.50SF

CORRIDOR140

158.79SF

STAIR141

164.21SF

STAIR142

163.53SF

STAIR143

163.53SF

STAIR144

155.89SF

STAIR145

165.20SF

STAIR146

194.06SF

STAIR147

BUILDINGOUTLINEABOVE

UNEXCAVATEDUNDEREXISTINGAUDITORIUMWITHHIGHFOUNDATIONS

District of Columbia Public SchoolsMarie H. Reed Community Learning Center DRAFT

1308.00SF

KINDERGARTEN-2

63

1308.00SF

KINDERGARTEN-3

64

1542.29SF

PREK-165

1147.50SF

PREK-267

1168.75SF

KINDERGARTEN-1

68

1168.75SF

PRESCHOOL-169

7997.94SF

CIRCULATION70

1168.75SF

PRESCHOOL-371

3180.93SF

MUSIC72

174.78SF

AFTERCARECLOSET

74

190.00SF

LAPTOPSTORAGE79

176.22SF

AFTERCARECLOSET

81

303.47SF

COMMONS-PRE-K

83

1168.75SF

PRESCHOOL-284

1168.75SF

PREK-385

296.43SF

COMMONS-PRE-S

86

174.06SF

TOILET87174.06SF

TOILET88

6260.82SF

CAFETERIA90

MiddleSchoolProgramLegend

DCPS-CoreAcademicClassrooms

DCPS-FoodService

DCPS-BuildingSupport

DCPS-ElectiveClassroom

DCPS-Administration

908.52SF

TEACHERRESOURCE

92

310.48SF

PARENTRESOURCE

93

1112.58SF

ADMINISTRATION94

162.67SF

TOILET95

159.28SF

TOILET96

333.33SF

RESOURCE97

162.17SF

STAIR148

156.04SF

STAIR149

150.14SF

TOILET150

157.32SF

TOILET151

155.89SF

STAIR152

165.20SF

STAIR153

165.57SF

STAIR154

170.93SF

STAIR155

163.53SF

STAIR156

163.53SF

STAIR157

545.85SF

VESTIBULE158

2263.31SF

CORRIDOR159

323.33SF

OUTDOORSTORAGE

179

901.52SF

FIFTHGRADE-21

901.52SF

FIFTHGRADE-32

892.22SF

WETLAB3

279.83SF

STORAGE-PRIMARY

4

289.99SF

RESOURCE-MATH

5

864.99SF

FIFTHGRADE-16

855.02SF

FOURTHGRADE-3

7

908.33SF

FOURTHGRADE-2

8

908.33SF

FOURTHGRADE-1

9

901.52SF

THIRDGRADE-210

901.52SF

THIRDGRADE-311

906.06SF

SECONDGRADE-2

17

906.06SF

SECONDGRADE-1

18

904.39SF

SECONDGRADE-3

19

880.06SF

THIRDGRADE-120

869.92SF

FIRSTGRADE-221

880.06SF

FIRSTGRADE-122

869.92SF

FIRSTGRADE-323

1017.50SF

VISUALARTSLAB24

894.17SF

FOODLAB25

137.50SF

STORAGE26

63.25SF

KILN27

154.38SF

OFFICE28

154.38SF

OFFICE29

166.75SF

RESOURCE-FOURTH/FIFTH

30

525.44SF

COMMONS-FOURTH

32

525.44SF

COMMONS-FIFTH33

1766.75SF

LIVINGLAB34

742.91SF

WORKROOM35

166.28SF

RESOURCE-SECOND/THIRD

36

413.76SF

COMMONS-THIRD

37

107.47SF

STORAGE38

209.21SF

CONFERENCEROOM

39

912.67SF

PROJECTLAB40

1819.17SF

READINGROOM41

261.09SF

RESOURCE-ESL42

385.25SF

COMMONS43

553.07SF

RESOURCE-SPEECH

45

107.33SF

AFTERCARECLOSET

46

305.52SF

RESOURCE-ESL47

268.97SF

STORAGE-INTERMEDIATE

48

190.00SF

LAPTOPSTORAGE49

304.00SF

RESOURCE-READING

51660.00SF

COMMONS-READING

52

154.26SF

RESOURCE-FIRST

53529.24SF

COMMONS-FIRST/SECOND

55

308.22SF

RESOURCE-ESL56

MiddleSchoolProgramLegend

DCPS-CoreAcademicClassrooms

DCPS-BuildingSupport

DCPS-MediaCenter

DCPS-ElectiveClassroom

DCPS-Administration

165.57SF

STAIR57

176.22SF

TOILET58

176.22SF

TOILET59

165.57SF

STAIR60

172.61SF

TOILET61

172.61SF

TOILET62

174.06SF

TOILET98

174.06SF

TOILET99

176.22SF

TOILET100176.22SF

TOILET101

4947.36SF

PERFORMANCESPACE

102

285.67SF

RECORDSROOM160

48.95SF

STORAGE161

48.95SF

STORAGE162

48.58SF

STORAGE163

48.58SF

STORAGE164

47.87SF

STORAGE165

47.87SF

STORAGE166

56.34SF

STORAGE167

56.34SF

STORAGE168

162.17SF

STAIR169

162.17SF

STAIR170

163.53SF

STAIR171

163.53SF

STAIR172

165.57SF

STAIR173

165.57SF

STAIR174

362.13SF

COMMONS175

4850.94SF

CIRCULATION176

3541.05SF

CIRCULATION177

326.63SF

WELCOMECENTER

178

FLOORPLANSOPTION A

FIRSTFLOORPLAN SECONDFLOORPLAN

1308.00SF

KINDERGARTEN-2

63

1308.00SF

KINDERGARTEN-3

64

1542.29SF

PREK-165

1147.50SF

PREK-267

1168.75SF

KINDERGARTEN-1

68

1168.75SF

PRESCHOOL-169

7997.94SF

CIRCULATION70

1168.75SF

PRESCHOOL-371

3180.93SF

MUSIC72

174.78SF

AFTERCARECLOSET

74

190.00SF

LAPTOPSTORAGE79

176.22SF

AFTERCARECLOSET

81

303.47SF

COMMONS-PRE-K

83

1168.75SF

PRESCHOOL-284

1168.75SF

PREK-385

296.43SF

COMMONS-PRE-S

86

174.06SF

TOILET87174.06SF

TOILET88

6260.82SF

CAFETERIA90

MiddleSchoolProgramLegend

DCPS-CoreAcademicClassrooms

DCPS-FoodService

DCPS-BuildingSupport

DCPS-ElectiveClassroom

DCPS-Administration

908.52SF

TEACHERRESOURCE

92

310.48SF

PARENTRESOURCE

93

1112.58SF

ADMINISTRATION94

162.67SF

TOILET95

159.28SF

TOILET96

333.33SF

RESOURCE97

162.17SF

STAIR148

156.04SF

STAIR149

150.14SF

TOILET150

157.32SF

TOILET151

155.89SF

STAIR152

165.20SF

STAIR153

165.57SF

STAIR154

170.93SF

STAIR155

163.53SF

STAIR156

163.53SF

STAIR157

545.85SF

VESTIBULE158

2263.31SF

CORRIDOR159

323.33SF

OUTDOORSTORAGE

179

901.52SF

FIFTHGRADE-21

901.52SF

FIFTHGRADE-32

892.22SF

WETLAB3

279.83SF

STORAGE-PRIMARY

4

289.99SF

RESOURCE-MATH

5

864.99SF

FIFTHGRADE-16

855.02SF

FOURTHGRADE-3

7

908.33SF

FOURTHGRADE-2

8

908.33SF

FOURTHGRADE-1

9

901.52SF

THIRDGRADE-210

901.52SF

THIRDGRADE-311

906.06SF

SECONDGRADE-2

17

906.06SF

SECONDGRADE-1

18

904.39SF

SECONDGRADE-3

19

880.06SF

THIRDGRADE-120

869.92SF

FIRSTGRADE-221

880.06SF

FIRSTGRADE-122

869.92SF

FIRSTGRADE-323

1017.50SF

VISUALARTSLAB24

894.17SF

FOODLAB25

137.50SF

STORAGE26

63.25SF

KILN27

154.38SF

OFFICE28

154.38SF

OFFICE29

166.75SF

RESOURCE-FOURTH/FIFTH

30

525.44SF

COMMONS-FOURTH

32

525.44SF

COMMONS-FIFTH33

1766.75SF

LIVINGLAB34

742.91SF

WORKROOM35

166.28SF

RESOURCE-SECOND/THIRD

36

413.76SF

COMMONS-THIRD

37

107.47SF

STORAGE38

209.21SF

CONFERENCEROOM

39

912.67SF

PROJECTLAB40

1819.17SF

READINGROOM41

261.09SF

RESOURCE-ESL42

385.25SF

COMMONS43

553.07SF

RESOURCE-SPEECH

45

107.33SF

AFTERCARECLOSET

46

305.52SF

RESOURCE-ESL47

268.97SF

STORAGE-INTERMEDIATE

48

190.00SF

LAPTOPSTORAGE49

304.00SF

RESOURCE-READING

51660.00SF

COMMONS-READING

52

154.26SF

RESOURCE-FIRST

53529.24SF

COMMONS-FIRST/SECOND

55

308.22SF

RESOURCE-ESL56

MiddleSchoolProgramLegend

DCPS-CoreAcademicClassrooms

DCPS-BuildingSupport

DCPS-MediaCenter

DCPS-ElectiveClassroom

DCPS-Administration

165.57SF

STAIR57

176.22SF

TOILET58

176.22SF

TOILET59

165.57SF

STAIR60

172.61SF

TOILET61

172.61SF

TOILET62

174.06SF

TOILET98

174.06SF

TOILET99

176.22SF

TOILET100176.22SF

TOILET101

4947.36SF

PERFORMANCESPACE

102

285.67SF

RECORDSROOM160

48.95SF

STORAGE161

48.95SF

STORAGE162

48.58SF

STORAGE163

48.58SF

STORAGE164

47.87SF

STORAGE165

47.87SF

STORAGE166

56.34SF

STORAGE167

56.34SF

STORAGE168

162.17SF

STAIR169

162.17SF

STAIR170

163.53SF

STAIR171

163.53SF

STAIR172

165.57SF

STAIR173

165.57SF

STAIR174

362.13SF

COMMONS175

4850.94SF

CIRCULATION176

3541.05SF

CIRCULATION177

326.63SF

WELCOMECENTER

178

LEGEND

9728.75SF

PARKING181

MiddleSchoolProgramLegend

DCPS-BuildingSupport

Parking

556.04SF

MECHANICAL182

220.21SF

UTILITY183

271.50SF

UTILITY184

509.50SF

STORAGE185

363.17SF

UTILITY186

888.56SF

UTILITY187

2586.44SF

UTILITY188

156.44SF

UTILITY189

43.00SF

UTILITY190

31.43SF

UTILITY191

23.75SF

TOILET192

45.68SF

UTILITY193

130.64SF

UTILITY194

58.06SF

STAIR195

121.00SF

STAIR196

122.81SF

UTILITY197

35.67SF

TOILET198

5037.08SF

MULTI-PURPOSEROOM

103

5858.33SF

GYMNASIUM104

962.90SF

LOCKERROOM-WOMEN

105

162.67SF

TOILET106

159.28SF

TOILET107

MiddleSchoolProgramLegend

DCPS-FoodService

DCPS-BuildingSupport

DPR-Recreation

CommunityPartners

956.15SF

LOCKERROOM-MEN

108

365.56SF

STORAGE109

355.11SF

STAGE110

412.56SF

GREENROOM111

130.33SF

FIRSTAIDCENTER112

1512.50SF

DAYCARE113

174.78SF

STORAGE114176.22SF

STORAGE115

174.06SF

TOILET116

174.06SF

TOILET117

13487.11SF

COMMUNITYOFHOPE

118

3831.83SF

WOMENINFANTS&CHILDREN

119

12507.93SF

POOL120

697.67SF

SHOWER-WOMEN

121

878.67SF

SHOWER

-MEN

122

441.22SF

RECEPTION123

321.49SF

DPROFFICE124

147.25SF

TOILET125

147.25SF

TOILET126

323.53SF

STORAGE127

321.49SF

STORAGE128

441.22SF

WARMINGKITCHEN

129

450.78SF

UTILITYROOM130

240.25SF

CHEMICALROOM131

701.79SF

STORAGE132

174.06SF

OUTDOORSTORAGE

133

174.06SF

OUTDOORSTORAGE

134

2793.45SF

LOBBY135

128.82SF

STAIR136

162.17SF

STAIR137

117.62SF

CORRIDOR138

117.62SF

CORRIDOR139

104.50SF

CORRIDOR140

158.79SF

STAIR141

164.21SF

STAIR142

163.53SF

STAIR143

163.53SF

STAIR144

155.89SF

STAIR145

165.20SF

STAIR146

194.06SF

STAIR147

BUILDINGOUTLINEABOVE

UNEXCAVATEDUNDEREXISTINGAUDITORIUMWITHHIGHFOUNDATIONS

District of Columbia Public SchoolsMarie H. Reed Community Learning Center DRAFT

LIVINGLABOPTION A

District of Columbia Public SchoolsMarie H. Reed Community Learning Center DRAFT

MEDIACENTER&STAIRSOPTION A

District of Columbia Public SchoolsMarie H. Reed Community Learning Center DRAFT

SECTIONPERSPECTIVEOPTION A

District of Columbia Public SchoolsMarie H. Reed Community Learning Center DRAFT

CONSTRUCTIONPHASINGOPTION A

1 8 T H S T R E E T

C H A M P L A I N S T R E E T

S O C C E R F I E L D

Core Academic

L E G E N D

Existing

Recreation

Children’s Hospital

Health Center

Parking/Support

Under Construction

Summer 1

School Year #1 (2015-16)

Summer 2

School Year #2 (2016-17)

School Year #3 (2017-18)

1 8 T H S T R E E T

C H A M P L A I N S T R E E T

S O C C E R F I E L D

Core Academic

L E G E N D

Phase 1

Recreation

Children’s Hospital

Health Center

Parking/Support

Under Construction

Summer 1

School Year #1 (2015-16)

Summer 2

School Year #2 (2016-17)

School Year #3 (2017-18)

1 8 T H S T R E E T

C H A M P L A I N S T R E E T

S O C C E R F I E L D

Core Academic

L E G E N D

Phase 2

Recreation

Children’s Hospital

Health Center

Parking/Support

Under Construction

Summer 1

School Year #1 (2015-16)

Summer 2

School Year #2 (2016-17)

School Year #3 (2017-18)

( P O O L :A L T E R N A T E )

( C O M M U N I T Y P A R T N E R S :P O T E N T I A L O F F S I T E )

( C L A S S R O O M T R A I L E R S :2 N D - 5 T H G R A D E )

1 8 T H S T R E E T

C H A M P L A I N S T R E E T

S O C C E R F I E L D

Core Academic

L E G E N D

Phase 3

Recreation

Children’s Hospital

Health Center

Parking/Support

Under Construction

Summer 1

School Year #1 (2015-16)

Summer 2

School Year #2 (2016-17)

School Year #3 (2017-18)

1 8 T H S T R E E T

C H A M P L A I N S T R E E T

S O C C E R F I E L D

Core Academic

L E G E N D

Proposed

Recreation

Children’s Hospital

Health Center

Parking/Support

Under Construction

Summer 1

School Year #1 (2015-16)

Summer 2

School Year #2 (2016-17)

School Year #3 (2017-18)