qwertyuiopasdfghjklzxcvbnmq wertyuiopasdfghjklzxcvbnmqw ......proposed project for provision of safe...
TRANSCRIPT
0
qwertyuiopasdfghjklzxcvbnmq
wertyuiopasdfghjklzxcvbnmqw
ertyuiopasdfghjklzxcvbnmqwer
tyuiopasdfghjklzxcvbnmqwerty
uiopasdfghjklzxcvbnmqwertyui
opasdfghjklzxcvbnmqwertyuiop
asdfghjklzxcvbnmqwertyuiopas
dfghjklzxcvbnmqwertyuiopasdf
ghjklzxcvbnmqwertyuiopasdfgh
jklzxcvbnmqwertyuiopasdfghjkl
zxcvbnmqwertyuiopasdfghjklzx
cvbnmqwertyuiopasdfghjklzxcv
bnmqwertyuiopasdfghjklzxcvbn
mqwertyuiopasdfghjklzxcvbnm
qwertyuiopasdfghjklzxcvbnmq
wertyuiopasdfghjklzxcvbnmqw
ertyuiopasdfghjklzxcvbnmrtyui
opasdfghjklzxcvbnmqwertyuiop
Social Screening Report
Proposed Project for Water Transmission Line from WTP to Heerassagala Junction and along
Heerassagala Road
2/2/2015
1
Contents 1. Background ................................................................................................................................... 3
2. Sub project description ............................................................................................................... 4
3. Subproject Justification ............................................................................................................... 5
4. Socio Economic profile of the subproject impact area ........................................................ 6
5. Objectives ....................................................................................................................................... 7
6. Methodology .................................................................................................................................. 7
7. Sub project description ............................................................................................................... 7
8. Subproject Justification ............................................................................................................... 8
9. Identified Adverse Social Impacts and Mitigation Measures ................................................... 8
10. Positive Social Impacts .......................................................................................................... 10
11. Action Plan for Implementation of Social Safeguards ................................................... 10
11. Estimates of Specific Impacts ........................................................................................................ 11
12. Information on Affected persons ................................................................................................. 11
13. Conclusion ...................................................................................................................................... 12
Annex 01: Details of stakeholder consultation .............................................................................. 13
Annex 02: Social Impact Screening Check List: .............................................................................. 14
Annex 03: Tracers of the pipelines ................................................................................................ 15
Annex 04: Heeressagala Road Layout-1 ....................................................................................... 17
Annex 05: Heeressagala Road layout-2 ........................................................................................ 18
Annex 06: Heeressagala Road Layout-3 ....................................................................................... 19
Annex 07: Heeressagala Lane II Layout ........................................................................................ 20
Annex 08: Heeressagala Lower – Heeressagala Middle Reservoir site .......................................... 21
Annex 09: Heeressagala Transmission Line ................................................................................ 22
Annex 10: : Heeressagala Road Transmission Line-1 ................................................................ 23
Annex 11: Heeressagala Road Transmission Line -2 ................................................................. 24
Annex 12: : Heeressagala Transmission Line -Richmand Road ............................................... 25
Annex 13: NWS & DB letter .............................................................................................................. 26
Annex 14: NWS & DB permission letter for Railway ..................................................................... 28
Annex 15: Provincial Road Development Authority ....................................................................... 29
Annex 16: SCDP GRC appointment letter ....................................................................................... 30
2
Tables
Table 1: Commercial, residential and service Centers 06 Table 2: Beneficiary families of the proposed sub project 06 Maps
Map 1: Location Map –Heerassagala 04
3
1. Background
Provision of safe drinking water is one of the key objectives of the Millennium
Development Goals. Sri Lanka too is heading towards achieving the target of providing
safe drinking water for all. Bearing a share for the contribution to the National and
Global objectives, the Strategic Cities Development Program (SCDP) has identified the
proposed project for provision of safe drinking water for Heerassagala and Dangolla
Grama Niladari Divisions in the Greater Kandy City in collaboration with the Kandy
Municipal Council (KMC).
The general objective of the project is to provide uninterrupted safe drinking water for
the people of the key areas in the Kandy City Region. The other objectives are to
increase the carrying capacities of the existing water schemes enabling to expand the
coverage where the present carrying capacity is badly insufficient. Furthermore, the
project aims at introducing a systematic and efficient operation and maintenance system
which does not function well at present. One of the reasons is because of the old
structures and distribution networks that were built 60 years ago leading to continuous
maintenance issues. Finally, the project anticipates increasing and improving the level of
service delivery by providing technical and machinery support to the KMC to ensure
the sustainability of operation and maintenance services.
Map 01: Location of Transmission Line- From WTB to Heeressagala Middle
4
2. Sub project description
The SCDP has given priority to reconstruct and rehabilitate the water supply schemes
of the KMC area, and to expand and increase the existing capacities of the schemes
operated and maintained by the KMC at present. In order to achieve the above objective,
the project(SCDP) proposes laying a transmission line from Water Treatment Plant
(WTP) located in Gatambe ,to Heerassagala junction through the railway crossing and to
link this line to reservoir tanks to be constructed in the lower division of the Heerassagala
Gramaniladari Division,(GND) along the Heerassagala Road. Another transmission line
will be laid from the Heerassagala lower division reservoir to the reservoir tank to be
built under the project in the middle division of the Heerassagala GND. In the meantime,
a distribution line will be laid parallel to the transmission line from the Heerassagala
Middle and lower reservoir tanks to the Heerassagala Junction along the Heerassagala
road.
Water Treatment Plant (WTP) at Gatambe is the KMC’s main water purification unit
situated 200 m from Gatembe junction along the left side of the Sirimavo Bandaranayake
Mawatha. This has been established in 1956 and has been undergone rehabilitation from
time to time. The present capacity of the WTP is 35,000 cubic meters. The half an acre land
on which the WTP is built belongs to the KMC. Heerassagala lower division is situated 220
m from the second lane of the Heerassagala road at 561 M msl. Heerassagala middle
is situated 150 m along the third lane of the Heerassala road 613 M. The length of the
transmission line from WTP to Heerassagala junction is 1260 m and the length from the
Heerassagala junction to reservoir tanks is 1444 m .
The proposed development project consists of two components i.e. laying a transmission
line from Water Treatment Plant at Gatambe to Heerassagala Junction through the
railway crossing and then continuing the transmission line to Heerassagala lower reservoir
first and from there to Heerassagala middle reservoir. Furthermore, a distribution line
will be laid parallel to transmission line from the two reservoirs up to the Heerassagala
Junction. Transmission line from WTP to Heerassagala junction is planned to lay beneath
the walking passage on the right side of the road. From Heerassagala Junction to
reservoirs along the Heerassagala Road, both transmission and distribution lines are
planned to be laid along the road. The cost for restoration of the road after laying pipes
has been included in the Engineer’s estimate of BoQ bill No 01, in the General Items
(Items no 1.26 provision for payments to the Ceylon Government Railways.). A copy of the
engineering designs are included in Annex-02
The design and estimates have been prepared by the NWS&DB and the operation and
maintenance will be carried out by the KMC after commissioning the project.
5
3. Subproject Justification
The existing water schemes of the KMC were constructed 50 to 60 years ago targeting
the population at that time. With expansion of the residential areas and the increase of
the population in manifolds, the original capacity was severely insufficient to meet the
current water demand . As a result, consumers of the proposed project area are provided
with an intermittent water supply delivered by the KMC. Due to absence of reservoir
tanks, these water schemes are being operated at present through distribution of water
directly from the intake where water pressure in the distribution system is very high. As
a result of this high pressure, water lines are subjected to frequent damages and interruptions
causing severe hardships to consumers and particularly to women and children . The water
carrying capacity of the existing distribution line is far below the expected requirements.
Furthermore, all existing water schemes of the KMC are linked to one single operational
system where detections of any water leakages are difficult. This causes enormous water losses
estimated to be in the range of 40%-45% (non-revenue water Losses)., The proposed project
aims at introducing a zonal monitoring system where the KMC water scheme will be
fragmented to 11 sub sections called Zones enabling each zone to operate and maintain
their respective schemes separately. This would contribute to enhancing the efficiency of
water supply, reducing the operation and maintenance costs and minimizing the water
losses. The present operation and maintenance system of the KMC lacks advanced
equipment, computerized accounting packages, a monitoring system to assess its profits
and losses and a human resource capacity building plan . The proposed project focuses
on addressing the above deficiencies targeting 6778 beneficiaries comprising 981
households and to ensure the sustainability of the KMC water supply services. The final
goal of the project is to improve the living standards and the quality of life of the people
in the Kandy Municipal Council Area.
6
4. Socio Economic profile of the subproject impact area
The Socio economic profile of the project impact area comprise the left and right hand
sides of the Sirimavo Bandaranayake Road along which the transmission line starting from
the WTP to the reservoir tanks would be laid. In the project impact area, there are several
commercial and service centres located either side of the road from WTP to Heerassagala
Junction while a large number of residential units are located from Heerassagala junction
and along the Heerassagala road up to the locations identified for the construction of reservoir
tanks.
Table 01: Commercial, residential and service centres from WTP to Heerassagala
Junction & from Heerassagala Junction to reservoir tanks
S.N Item Number
1 Residential units 115
2 Land lots 19
3 Private medical centres 04
4 Religious Institutions 05
5 Government buildings 02
6 Social welfare centres 02
7 Preschools 04
8 National Schools 02
9 International schools 02
10 Private tuition classes 03
11 Medium scale commercial centres 55
12 Small scale business units 28
13 Single shop units 27
14 Bus halts 13
15 Access roads 44
16 Community centres 01
17 Educational centres 01
Table 02: Beneficiary families of the proposed subproject
Beneficiaries from the reservoir tanks
No. of beneficiaries
No. Households
Heerassagala Middle 2974 373
Heerassagala Lower. 3804 608
Total 6778 981
7
5. Objectives
The general objective of the proposed project is to provide uninterrupted safe drinking
water for 6778 beneficiaries (981 households). The project aims at building two water
storage tanks in the Heerassagala Lower Division and in the Heerassagala Middle division with
each having the capacity of storing 250 cubic meters. Furthermore, the project would establish
two operation and maintenance zones for the two divisions so that they need not depend
on the central operation and maintenance system which is not efficiently managed at
present. The project will also build the technical capacities of the staff affiliated to the
water works department of the KMC.
6. Methodology
Data for this social screening has been gathered through multiple sources such as individual
and focus group discussions with households living adjacent to the reservoir tanks and
pumping mains, discussions conducted with the technical staff of the National Water
Supply and Drainage Board (NWS&DB) which is responsible for the overall design and
contract supervision and also provide consultancy services to implement of the project , land
officials of the NWS&DB and the KMC. Secondary data was collected from the
NWS&DB and the Water Works Department of the KMC. Field visits were undertaken
to each project site and the distribution area to ensure that the subproject does not
involve any land acquisitions . The details of the stakeholder consultations are given in
Annex 01.
7. Sub project description
The proposed development project consists of two components i.e. laying a transmission
line from Water Treatment Plant at Gatambe to Heerassagala Junction through the
railway crossing and then continuing the transmission line to Heerassagala lower reservoir
first and from there to Heerassagala middle reservoir. Furthermore, a distribution line
will be laid parallel to transmission line from the two reservoirs up to the Heerassagala
Junction. Transmission line from WTP to Heerassagala junction is planned to lay beneath
the walking passage on the right side of the road. From Heerassagala Junction to
reservoirs along the Heerassagala Road, both transmission and distribution lines are
planned to be laid along the road. The cost for restoration of the road after laying pipes
has been included in the Engineer’s estimate of BoQ bill No 01, in the General Items
(Items no 1.26 provision for payments to the Ceylon Government Railways.). A copy of the
engineering designs are included in Annex-02
The design and estimates have been prepared by the NWS&DB and the operation and
maintenance will be carried out by the KMC after commissioning the project.
8
8. Subproject Justification
The existing water schemes of the KMC were constructed 50 to 60 years ago targeting
the population at that time. With expansion of the residential areas and the increase of
the population in manifolds, the original capacity was severely insufficient to meet the
current water demand . As a result, consumers of the proposed project area are provided
with an intermittent water supply delivered by the KMC. Due to absence of reservoir
tanks, these water schemes are being operated at present through distribution of water
directly from the intake where water pressure in the distribution system is very high. As
a result of this high pressure, water lines are subjected to frequent damages and interruptions
causing severe hardships to consumers and particularly to women and children . The water
carrying capacity of the existing distribution line is far below the expected requirements.
Furthermore, all existing water schemes of the KMC are linked to one single operational
system where detections of any water leakages are difficult. This causes enormous water losses
estimated to be in the range of 40%-45% (non-revenue water Losses)., The proposed project
aims at introducing a zonal monitoring system where the KMC water scheme will be
fragmented to 11 sub sections called Zones enabling each zone to operate and maintain
their respective schemes separately. This would contribute to enhancing the efficiency of
water supply, reducing the operation and maintenance costs and minimizing the water
losses. The present operation and maintenance system of the KMC lacks advanced
equipment, computerized accounting packages, a monitoring system to assess its profits
and losses and a human resource capacity building plan . The proposed project focuses
on addressing the above deficiencies targeting 6778 beneficiaries comprising 981
households and to ensure the sustainability of the KMC water supply services. The final
goal of the project is to improve the living standards and the quality of life of the people
in the Kandy Municipal Council Area.
9. Identified Adverse Social Impacts and Mitigation Measures
Adverse Social
Impacts Mitigation Measures
Approximately 150 households
will have access difficulties
temporarily during
underground pipe laying along
the road
Inform the community in advance and get their feedback
to minimize the difficulties.
Laying of pipes at night in a demarcated stretch of area
at a time Since contractor agreed to work during the night
time (9.00pm to 5.00am) and repair all the damages to
prevail condition at the same time, temporary displacement
also would not be affected any parties.
Households will have access
difficulties in emergency
situations such as taking patients
to hospitals during
Construction.
Services of an ambulance/vehicle will be made available
full-time to be used in such emergency situations.
9
Possible damages to physical
assets
Contractor will obtain an insurance package covering
restoration of all damages. This will be included to the
contract agreement. Provincial Road Development Authority
has been agreed to give a No objection letter to use the
Road .-Annex 13 (page no 24)
Insecurity to pedestrians and
vehicles due to excavation of
trenches on the middle of the
hilly and narrow access roads
for laying pipes.
Contractor is responsible to cover the excavated trenches
with soil on the same day without keeping trenches
opened during day time.
Implement a sound communication strategy. For example
displaying of sign boards, regular public address system etc.
Contractor will obtain an insurance package covering the
restoration of damages to vehicles, structures and any
injuries to people during construction period
There will be a traffic
congestion along the
Peradeniya - Kandy main road
and along Heerassagala road,
causing inconvenience to
commuters.
Police officials will be informed to prepare a
systematic traffic management plan and deploy sufficient
number of officials during entire construction period.
Stakeholders consultation was helped to developed weekly
traffic management plan that will intend to inform residents
of the area in advance when the construction work will start,
decided to discuss further propose traffic plan.
Contractor will deploy required manpower to assist the
police.
Construction will be carried out at nights as much as
possible
Display notice boards to inform the general public about
construction schedule, project basic information ,
interruption of water supply etc.
Safety of vehicle and people
would be at risk during
constructions at the rail way
crossing.
Railway department will be informed to get adequate
mitigation measures to arrest the risk. The NWS&DB
has already discussed with the Railway Department
officials and the laying of pipe lines under the railway
line will be carried out by the Rail way Department.
NWS&DB has been requested permission to lay pipe line it
crosses the railway line at Heerasssagal Junction (Attached
request permission letter – Annex 12 (page no 23) The
required budgetary provision has been allocated to the
Railway Department for the implementation of special
mitigation plan. Restoration cost has been allocated the
Engineer’s estimate of the BOQ.
Consumers will experience
interruptions to their water
supplies.
The subproject will be implemented without interrupting
the existing water supply scheme until the new pipe lines
are laid.
Consumers will be informed in advance if any short term
interruptions were anticipated
Parking of excavating
equipment on the road or in
residential areas or putting up
workers camps will cause
inconveniences to road users
and residents.
Contractor will be informed to rent out suitable land
area away from the construction sites to place their
heavy machinery and workers residential camps.
10
Dust and noise during
construction period and work at
nights would cause
inconveniences and disturbances
to residents and road users
Contractor will be early informed to take mitigation
measures to counteract the short term impacts.
Separate allocation will be provided to the contractor for
regular watering of the construction sites
Inform the residents about the complexity of this
development project to be implemented in a densely
residential area. Establish a Grievance Redress
Mechanism to address complaints from the affected parties
Contractor will be requested to use modern technologies
and machinery for minimizing sound pollution
10. Positive Social Impacts
The project will ensure an uninterrupted safe supply of drinking water for an estimated
population of 6778 persons while improving their quality of life. Subproject beneficiaries will
also receive timely operation and maintenance services from the KMC as a result of
improved operation and maintenance services and staff capacity building. Reduced
maintenance costs and water losses would in turn benefit the consumers in terms of reduced
tariff rates.
11. Action Plan for Implementation of Social Safeguards
This water supply subproject contract is planned to be awarded in February,2015. The
construction work will commence in March, 2015 and will be completed in March, 2016.
Adverse Social impacts were identified during the community consultation and propose
mitigation measures have been already submitted to the contractor, The contractor should be
hand over his construction plan before implement the activities in the construction site, based
on the contractor’s plan Local PMU will prepare weekly advance work plan and submit KMC
to monitor compliance with the social safeguard mitigation measures of the sub project. At the
construction awarding meeting which was held on 23rd of March 2015 in Kandy, project team
we were presented and discussed both social and environment safeguard issues Mr.Chandana
Thennakoon the Commissioner of KMC, has suggested all the construction related complain
and incident they will expect directly report to them through propose field level Grievance
Redress Committee and site Safeguard Officer, apart from that the project has been requested
to appoint the commissioner or his nominee from MC Kandy to work as a chairmen of the
GRC filed level committee and also he will be a focal appoint of KMC and coordinate above
mention responsibilities.-Annex 16
11
11. Estimates of Specific Impacts
Co
mp
on
ents
o
f th
e Su
b
Pro
ject
Pri
vate
lan
d r
equ
ired
In S
q. m
.
No
of
Lan
d o
wn
ers
losi
ngm
ore
than
10
%
of
Lan
d a
rea
Go
vern
men
tal a
nd
re
qu
ired
in S
q. m
.
Fore
stla
nd
req
uir
ed
in S
q. m
.
No
of
ho
use
s af
fect
ed
No
of
sho
ps
affe
cte
d
No
of
oth
er
stru
ctu
res
affe
cte
d
No
of
squ
atte
rs
affe
cte
d
Pu
blic
uti
litie
s af
fect
ed
Construction of Water
Transmission Line
None None 508 perch
None None None None None None
12. Information on Affected persons
Any estimate of the likely number of households that will be affected by the sub project?
[ ] No.[ ] Yes. If yes, approximately how many? …………NO……………………….
No. of HHs losing <10% of their productive assets
(land/cowshed/shops)……NO…………………
No. of HHs losing 10% or more of their productive assets?......NO.............................
Are any vulnerable households affected? [NO] No. [ ] Yes. If yes, please briefly describe their situation with estimate numbers of HHs? What are the needs and priorities for social and economic betterment of vulnerable people who are affected by this project? Not relevant
12
13. Conclusion The overall assessment of the social screening is that it is ensured that there is no
violation of the World Bank Safeguard policies OP 4.10 and OP 4.12 and Government
policies in the implementation of the proposed water transmission schemes.
Prepared by:
S. Gunasekera
(Assistant Project Director /Social, SCDP)
Date: 31st March 2015
Recommended by:
Mr. Pradeep Hettiarachchi
(Deputy Project Director /Social, SCDP)
Date: 01st April 2015
Approved by:
Archt. Anura Dasanayake (Project Director, SCDP)
Date: 02nd April 2015
13
Annex 01: Details of stakeholder consultation
Institution/Stakeholders Officials Met Matters discussed
Provincial Road Development Authority (PRDA)
Chief Engineer Damages to road and strategy to reinstate the road after pipe laying along the Heerassagala road. It was requested that the a copy of implementation plan be submitted to the PRDA.
Railway Department Explained the proposed project and the task of Rail way department for laying pipes through the railway crossing. Further discuss how to minimized and prevailed to improve condition of the damage railway line
KMC Hon. Mayor, Municipal Commissioner, Chief Engineer
Explained the design and estimates of the proposed project and obtained comments to the Social Safeguard Implementation Plan and discussed to develop effective mechanism to monitor the contractor’s compliance with propose social safeguard in SSR
National Water Supply & Drainage Board
Chief Engineer, Land Officer, staff of the consultancy project office
Details of the estimate and design, implementation arrangement and potential social impacts and mitigation arrangements. Decided to issues No objection letter from the NWS & DB.-Annex 11(page no 21 & 22).
Police Department Assistant Superintendent of Police/Traffic Division
Informed about the project and ensured the deployment of traffic police staff for managing the traffic congestion during the construction period.
General Public Residents of the impact area and business community of the main street, teachers of tuition classes and students
Explained about the project and potential impacts of the proposed project. The feedback from the majority was to implement constructions during nights.
14
Annex 02: Social Impact Screening Check List:
Probable Involuntary Resettlement Effects Yes No Not Known
Details
Will the sub-project include any physical construction work?
Does the sub-project include upgrading or rehabilitation of existing physical facilities?
Is the sub-project likely to cause any damage to or loss of housing, other assets, resource use?
Is the site for chosen for this work free from encumbrances and is in possession of the government/Municipality?
If the site is privately owned, will this be purchased or obtained through voluntary donation?
If the land parcel has to be acquired, is the actual plot size and ownership status known?
No need of any lands to be acquired. both transmission and distribution lines are planned to lay on the road
Is land for material mobilization or transport for the civil work available within the existing plot/ Right of Way?
Are there any non-titled people who living/doing business on the proposed site for civil work?
Will there be loss of /damage to agricultural lands, standing crops, trees?
Will there be loss of incomes and livelihoods? Will people permanently or temporarily lose access to facilities, services, or natural resources?
Temporary interruption of Accessibility
Does the Urban Local Body have its own procedures for land acquisition?
Not relevant
Are there any previous land acquisitions I under this subproject?
Are any indigenous people affected? Whether the affected land/structure owners likely to lose less than 10% of their land/structure area. If so, are these land / structure owners willing to voluntarily donate the required land for this sub-project?
Is any temporary impact likely?
Considerable number of households will experience difficulties in access and transport difficulties & exposure to noise and dust particle pollution.
15
Annex 03: Tracers of the pipelines
i. WTP - Heeressagala Junction
16
ii. Heeressagala Junction – Heeressagala lower Reservoir site
17
Annex 04: Heeressagala Road Layout-1
18
Annex 05: Heeressagala Road layout-2
19
Annex 06: Heeressagala Road Layout-3
20
Annex 07: Heeressagala Lane II Layout
21
Annex 08: Heeressagala Lower – Heeressagala Middle Reservoir site
22
Annex 09: Heeressagala Transmission Line
23
Annex 10: : Heeressagala Road Transmission Line-1
24
Annex 11: Heeressagala Road Transmission Line -2
25
Annex 12: : Heeressagala Transmission Line -Richmand Road
26
Annex 13: NWS & DB letter
27
28
Annex 14: NWS & DB permission letter for Railway
29
Annex 15: Provincial Road Development Authority
30
Annex 16: SCDP GRC appointment letter