training report ktps-final

66
MAHARANA PRATAP UNIVERSITY OF AGRICULTURE AND TECHNOLOGY UDAIPUR, (RAJ) INDIA A Practical Training Report On KOTA SUPER THERMAL POWER STATION TRAINING HELD FROM (10 June 2009 to 09 July 2009) 1

Upload: rahulj567

Post on 09-Mar-2015

599 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Training Report Ktps-Final

MAHARANA PRATAP UNIVERSITY OF AGRICULTURE AND

TECHNOLOGY

UDAIPUR, (RAJ) INDIA

A

Practical Training Report

On

KOTA SUPER THERMAL POWER

STATION

TRAINING HELD FROM

(10 June 2009 to 09 July 2009)

GUIDIED BY SUBMITTED BY

Er. Vinod Yadav Kishan Bhushan Sahay

Electrical Department BE 2nd Year (EE)

1

Page 2: Training Report Ktps-Final

PREFACE

The rise in civilization is closely related to improvements in transportation

and requirement of energy that is not readily available in large quantities but is also readily

transportable. A very peculiar fact about electrical energy is that neither it is directly

available in nature nor it is directly used finally in this form, yet it is so widely produced and

is the most popular high grade energy.

The purpose behind training is to understand the difficult concepts in a better

way with gain of knowledge. Report starts with a brief introduction of KSTPS followed by

Generator, Turbine, switch gear, switch yard etc.

While writing the report and while I was on my training I was wondering that

science is as ever expanding field and the engineers working hard day and night and make the

life a gift for us.

2

Page 3: Training Report Ktps-Final

ACKNOWLEDGEMENT

It is a matter of great pleasure and privilege for me to present this report of 30

days on the basis of practical knowledge gained by me during practical training

at KOTA SUPER THERMAL POWER STATION (KSTPS),

KOTA (Raj.) during June-July-2009.

I use this opportunity to express gratitude and debtness to Er.

Vinod Yadav sir, Training Incharge (Electrical Engg.), CTAE, UDAIPUR.

I want to express my thanks to Chief engineers of KSTPS to give

their valuable time and kind co-operation, other staff members for their further

co-operation to gain the better knowledge about the Power Plant.

Kishan Bhushan Sahay

2nd YEAR(EE)

Electrical Engg.

3

Page 4: Training Report Ktps-Final

INDEX

4. INTRODUCTION 5

5. GENERATOR 6

6.TRANSFORMER 10

7. SWITCH YARD 14

8. SWITCH GEAR 16

9. PROTECTION 18

10. CONTROL ROOM 20

11. AUXILIARY SUPPLY 21

12. TURBINE 23

13. BOILER 24

14. WATER TREATMENT PLANT 26

15. COAL HANDLING PLANT 28

16. COOLING TOWER 31

17. BEARING COOLING WATER 32

18. PUMPS 32

19. H2 GENERATING PLANT 33

20. ELECTROSTATIC PRECIPITATOR 34

21. ASH HANDLING PLANT (A.H.P.) 35

22. SOOT BLOWING 35

23. EFFICIENCY 36

24. CONCLUSION 38

4

Page 5: Training Report Ktps-Final

INTRODUCTION

The “KOTA SUPER THERMAL POWER STATION” is ideally located on

the left bank of Chambal River at the upstream of “KOTA BARRAGE”. Thermal power

station to produce electrical power for supply undertakings K.S.T.P.S. is designed for

ultimate capacity of 1045 MW. First two units of 110MW each, another three units of

210MW each and further the sixth unit of 195MW have been completed.

The state Rajasthan is predominantly rural and agricultural .While Rajasthan

mineral sources are immense, its sources for power generation weren’t commensurable with

its requirements. The large expense of water, stored by the “barrage” provides, as efficient

direct circulation cooling system for the power station thus avoiding installation of cooling

towers. For bringing in coal for power station and machinery and equipment etc. a 15Km

long private siding from the Gurla Railway Station on Delhi-Bombay broad gauge line has

been laid-up to the power station.

INSTALLATION AND COMMISSIONING OF UNITS:-

The units in K.S.T.P.S. are as:

Stage I - (Two units each of 110 MW)

Stage II- (Two units each of 210 MW)

Stage III- (one unit of 210 MW)

Stage IV- (one unit of 195 MW)

ENERGY GENERATED IN KSTPS

Total generation Capacity

= (2 x 210+2 x 210+1 x 210+ 1 x 195)

= 1045MW

Total generated Electricity (in one hour)

= 1045MW x 1=10.45Lakh units

Total generated Electricity (in 24hours)

= 10.45 x 24= 250.8 Lakhs units

Amount of Coal required (per day) in KTPS is

= 0.5 x 250.8 x 100000 Kg.

= 125.4 x 100000Kg.

= 125.4 million Kg.

This amount of coal is supplied by 5 trains of coal

5

Page 6: Training Report Ktps-Final

GENERATOR

Generator is the main part of thermal power station or any power plant. A

generator is a machine which converts mechanical energy into electrical energy.

The generator has gas cooling construction enclosing the stator winding, core

and hydrogen coolers .The cooling medium hydrogen is contained within the frame and

circulation by fans mounted on either ends of the rotor .The generator is driven by directly

coupled steam turbine at a speed of 3000 rpm.

Provision has been made for circulating the cooling water in order to maintain

a constant temperature of the coolant i.e. H2 as measured at the fan section side which is in

touch with the temperature of the winding, core and other parts as per load.

Each of the 2 units under stage-1 have been provided with BHEL make 3-phase

turbo generator rated 137.5 MVA, 11KV, 0.8 pf, 7220 Amp, 3000 rpm and 50

cycles/sec .The generator has closed loop of hydrogen gas system for cooling of the stator

and rotor at a pressure of 2.0 atm. is filled in a gas tight outer casing of the generator. H2 gas

circulates inside the casing by two single stage rotor mounted fans on either side of the

rotor .The heated H2 is in turn cooled by six surface type water coolers axially mounted inside

the generator casing .The cooling water is supplied to H2 coolers from the BCW over head

tank.

Each generator has terminal led out of its casing and a star point is formed by

sorting the neutral side terminals by a sorting bar. The neutral is grounded by a 1-phase

11000/220V, 37.5 KVA. Neutral grounding transformer, whose secondary coil is laminated

by laminated strip with mechanical ventilating holes, is connected across a 650V, class 0.4

ohm, 50 kW neutral grounding resistors and relays for protection of generator against stator

earth faults and stator in turn faults (rating 1 amp).

The H2 gas inside the generator casing is prevented from leaking in between

the rotor and shields, by a continuous oil film maintained between the rotor and sealing

rings .The shaft sealing system have two independent oil sources associated pumps,

regulators, coolers filters, electrical controls and alarm system. Two independent oil sources

are provided for air side and H2 side sealing rings. The oil circuit of the H2 side of the shaft

seal is closed and the oil is vacuum treated.

6

Page 7: Training Report Ktps-Final

TURBO GENERATOR SPECIFICATIONS:-

(a) STAGE –I

Make Russian

Manufacturer BHEL

Type T.G.P.

Apparent Output 137.5MVA

Active Output 110 MW

Power factor 0.8 lagging

Rated voltage 11 KV

Rated current 7200 Amp.

Rated speed 3000 rpm

Frequency 50 Hz

Phase connections Double gen. star

No. of generator terminals 6

Max. Output with air cooling 68.75MVA

Excitation voltage 230V

(b) STAGE –II & III

Make KWVC Craftworks, Germany

Manufacturer BHEL

Rated capacity 247 MVA

Rated Output 210 MW

Rated current 9050 Amp.

Rated terminal voltage 15.75 KV

Rated speed 3000 rpm

Power factor 0.8 lagging

Excitation voltage 310V

Phase sequence Double star

Insulation class B

No. of turns per phase/pole 10

Short circuit ratio 0.49

7

Page 8: Training Report Ktps-Final

(c) STAGE –IV

Make KWVC Craftworks, Germany

Manufacture BHEL

Rated Capacity 247 MVA

Rated Output 210 MW

Rated Current 9050 Amp.

Rated Terminal Voltage 15.75 KV

Rated Speed 3000 Rpm

Power Factor 0.8 Lagging

Excitation Voltage 310 V

Phase Sequence Double Star

Insulation Class B

No. of Turns per Phase/Pole 10

Short Circuit Ratio 0.49

DESCRIPTION OF THE GENERATOR PARTS:-

1. STATOR BODY:-

Armature of a generator formed of laminations having slots on its inner

periphery to accommodate armature conductors and is known as stator .The stator body is a

totally enclosed gas tight fabricated structure suitably internally to rigidity . The function of

stator frame is to contain and support the stator core winding , hydrogen coolers and also path

for distribution of cooling hydrogen through the generator .

2. STATOR CORE:-

The rotating magnetic field flow with the core .In order to reduce the

magnetizing (eddy) current losses in the active portion of the stator core due to rotation of

field structure in between the stator the entire core is built up of thin laminations .The

segments are stamped out from CRGO .The core contain several pockets separated by steel

spaces for radial cooling of the core by hydrogen.

3. STATOR WINDING:-

The stator has 3 phase double layer, short pitched and bar type of winding

having two parallel paths .Each slot accommodates two bars .The lower and upper bars are

displaced from each other by one winding pitch and connected at their ends so as to form coil

groups .Each bar consists of solid as well as hollow conductors with cooling water passing

through the later alternator

8

Page 9: Training Report Ktps-Final

4. DISTILLATE HEADER:-

Ring type header, made up of copper are provided separately for distillated

inlet and outlet min the stator of turbine side .The headers are support on insulator and

insulated from stator body .At turbine side each individual bar is connected with inlet/outlet

header .The vent pipe connection are at the top of the both inlet and outlet header .The vent

pipes are connected to gas trap desire to measure the extent of hydrogen leakage into water

circuit.

5. TERMINAL BUSHING:-

Three phases and six neutral terminals are brought out from the stator through

bushings which are capable of withstanding high voltage and provided with gas tight

joints .The bushing is assembled and tested for flow, leakage to ensure tightness and

continuous flow of water.

6. END SHIELD:-

To make the stator body air tight the end shield are fitted .Gas tightness is

achieved by putting a rubber sealing cord .The end shields are made3 in two halves

convenience during erection and installation.

7. ROTOR:-

The field structure is the largest & heaviest component of generator and is

called the rotor. The rotor houses the static excitation winding and the exciting current is

supplied to the rotor through the slip rings & brushes. The rotor shaft is a single piece forging

the longitudinal slot for inserting the field winding. The slots are distributed over the

circumference so that two field solid poles are obtained .

8. BEARINGS:-

The generator bearings are of pedestal type with spherical seating. It allows

self alignment and is supported on a separate pedestal on slip ring side. The bearing has a

provision of hydraulic shaft lifting during start up and turning gear operation to eliminate

shaft current. Shaft bearing and its pipes are insulated from earth.

9. BRUSH GEAR:-

The current carrying gear assembly is rigidly fixed on the extent part of the

bearing pedestal on the exciter side. There are two brushes gear stand for (+) ive and (-) ive

supply. The field to stator wdg. Provide the brush gear. The designs of brushes during normal

operation condition have low coefficient of friction and are self lubricating.

9

Page 10: Training Report Ktps-Final

TRANSFORMER

Transformer is made up of following parts:-

1. Core

2. Winding

3. On load tap changer

4. Tank

5. Bushing

6. Auxiliary equipment

7. Insulating Oil

8. Cooling system

In KSTPS there are various transformers for various purposes. They are:-

1. Generating Transformer

2. Unit auxiliary Transformer

3. Station Transformer

4. Capacitor voltage Transformer

1. GENERATING TRANSFORMER:-

In KSTPS, there is one generating transformer for each unit of it. There rating are different

depend upon capacity of each unit. The generated electricity from main generator is being

feed into transformer, so it is known as generating transformer. It is three phase power

transformer. It is also known as main transformer. There is a provision of movement of

transformer on rail in the power station during erection and for repair and maintenance.

SPECIFICATIONS:-

Unit 1 & 2:-

Manufacture BHEL

No. /unit One

Type of construction Core type

No. of phases 3

Type of connections HV star, LV delta

No. of Taps 9

Rating 125 MVA, 11/240 KV

Type of winding HV Shielded multilayer

Type of cooling ON/OB/OFB

10

Page 11: Training Report Ktps-Final

On load losses 78KW

Maximum efficiency 99.72

Oil Temp. Rise 40oC

Core lamination material Cargo sheet steel

Core to LV wdg. Insulation Bakelite

HV to LV wdg. Insulation Paper, press board

Vol. of Air for initial 5750 Lt.

Unit 3,4,5 &6:-

Manufacture BHEL

No. /unit One

Rating 250 MVA

Bushing voltage 240KV

Transformer Ratio 15.75/220KV

Type of cooling ON/OF/AF

Rating OF Cooling 250MVA

ON Cooling 125MVA

Percentage impedance 14%

Winding Temp. Rise 50oC

Line Current HV 602.12A/ LV 9175.15A

UNIT AUXILLIARY TRANSFORMER:-

Power required for all units auxiliary are met by UAT, one for each unit and

there are five units, so five UATs are for five units. This transformer normally

needs the power requirement for all units auxiliary when the unit is synchronies

with the grid and has become stable. It works when load is 40% or more.

SPECIFICATIONS:-

Unit 1 & 2:-

Manufacture BHEL

Type Oil filled natural cooled step down xmer

Type of cooling ON/AN

Rating 15 MVA

Rated Primary Voltage 11 KV

Rated Secondary voltage 6.6 KV

11

Page 12: Training Report Ktps-Final

Phases 3

Rated Current HV-787 A, LV-1237A

Frequency 50 Hz

Impedance ratio 7%

Oil Temp. Rise 40oC

Winding Temp. Rise 50oC

Core & Winding weight 18320 Kg

Weight of Oil 8220 Kg

Oil quantity 9670 liters

Unit 3 & 4:-

Manufacture BHEL

Type Oil filled natural cooled step down Xmer

Type of cooling ON/AN

Turns Ratio 15.75 KV/ 7 KV

Oil Temp. Rise 40oC

Winding Temp. Rise 50oC

Phases 3

Rated Current HV-550.51A, LV-1238.65A

Frequency 50 Hz

Connection symbol Dd

Customer R.S.E.B

2. STATION TRANSFORMER:-

The station transformer is rated for 50 /25/ 25MVA, 220/7/7MVA, Yd1d1

and is provided with an on load tap changer on HV winding. This permits a voltage

variation of up to 10% in 16 equal steps of 1.25% each.

SPECIFICATIONS:-

Manufactured Crompton Greaves Ltd, Bombay

Total no. provided 2

Type of construction Core type with three limbs

Type of cooling ON/AN,ON/AF

Rated output ON/AF 50/25/25 MVA

Rated voltage at no load HV side 220 KV LV side 7KV

frequencycy 50 Hz

12

Page 13: Training Report Ktps-Final

Oil Temp. Rise 40oC

Winding Temp. Rise 50oC

Type of HV winding Disc

Type of LV winding Helical

INSTRUMENT TRANSFORMER:-

In KSTPS instrument transformer have wide range in application such as

measurement of voltage, current, power & energy power factor, frequency. It is also used for

protection circuit of the power system for operation of over current, under voltage, earth fault

and other type of relays, The instrument transformer can be classified as

(a). Current Transformer

(b). Potential Transformer

(a). Current Transformer:-

Current transformer is used for monitoring the current for the purpose of

measuring and protection. They can be classified as Dead tank & Inverter type. The dead

tank current transformer accommodate the secondary cores inside the tank which is at ground

potential. The insulated primary passes through the porcelains and the tank and the terminals

into the top chamber. The primary used in such type of construction is of ‘U’ type.

(b). Potential Transformer:-

The function of P.T. is to step down the voltage so that it can be measured by

standard measurement. In three phases P.T. there is 3&5 limbs core construction. The P.T.

may be dry or oil field. The P.T. above 66KV is essentially sealed with inert gas cushion

provided in the top chamber to take care of expansion & construction. The transformer is

generally core type and form Y-Y group and having the insulation as oil and paper

4. CAPACITOR VOLTAGE TRANSFORMER:-Each of the four line

feeders provided with three capacitor vol transformer for metering and synchronizing.

SPECIFICATIONS:-

Manufacture W.S. Insulators of India Ltd., Madras

Type CVE 245/1050

Rated voltage Nominal 220KV

Maximum 245KV

No. of phases 1

Rated primary voltage 220/sqrt 3 KV

Rated secondary voltage 110/sqrt 3 KV

13

Page 14: Training Report Ktps-Final

SWITCH YARD

The 220KV switch yard has conventional two buses arrangement with a bus

coupled breaker. Both the generator transformer and line feeder taking off from switch yard

can be taken to any of the two buses, similarly two station transformer con be fed from any

two buses. Each of these line feeders has been provided with by pass isolators connected

across line isolators and breaker isolators to facilitate the maintenance of line breaker. Each

220KV line has provision of local break up protection. In event of breaker which

corresponding to bus bar differential protection scheme and trips out all the breakers and

connected zone bus bars differential protection scheme for bus I & II. All the breaker of the

connected zone and bus coupler, breaker will trip in event of fault in that zone.

Each of the two bus bars has one P.T. one for each phase connected to it.

Potential Transformer are make in BHEL oil filled, nitrogen sealed have two core rated for

220KV /110KV. One cores each for metering & protection. Each time line feeders has three

nos. Core for each phase capacitor voltage Trans. for metering and protection are multicored

single phase, oil filled, nitrogen sealed and are provided at rate of one per phase. A described

of electrical equipment at 220KV system are as follows: -

1. Circuit Breaker(MOCB & SF6)

2. Isolators

3. Current Transformers(C.T.)

4. Potential Transformers(P.T.)

5. Lighting Arresters

6. Earthing Arresters

7. Capacitor Voltage Transformers(C.V.T.)

CIRCUIT BREAKER:-

A circuit Breaker is a piece of Equipment which can:-

1. Make or break a circuit either manually or by remote control under normal conditions.

2. Break a circuit automatically under fault condition.

MOCB provided for each stage are BHEL made and rated for 245KV,

2500A , 134MVA. Each pole has three interrupters which are oil filled with nitrogen gas at

7.5 Kg/sq. cm. The three pole of MOCB are designed for single phase individual operation of

any pole. Breaker operate can be done only from respective pole operating mechanism by

putting selector switch on local. And now a days SF6 Circuit Breakers are also used.

Interlock Scheme of Circuit Breaker: -

14

Page 15: Training Report Ktps-Final

1. Generator Breaker

2. Station Transformer Breaker

3. Line Feeder Breaker

4. Bus Coupler Breaker

ISOLATERS:-

It is essentially a knife switch and is designed to open a circuit under no load.

Its main purpose is to isolate one portion of the circuit from the other and is not intended to

be opened while current is flowing in the line. Such switches are generally used on both sides

of circuit breakers in order that repairs and replacement of circuit breakers can be made

without any danger. They should never be opened until the circuit breaker in the same circuit

has been opened and should always be closed before the circuit breaker is closed.

LIGHTENING ARRESTER:-

An electric discharge between cloud and earth, between clouds or between the

charge of the same cloud is known is as Lightening.

A Lightening Arrester or a surge diverter is a protective device which

conducts the high voltage surges on the power system to the ground.

SPECIFICATIONS OF LIGHTENING ARRESTER:-

Type CPC-II

Maximum Voltage 198 KV / unit

Maximum Current 10KA

No. of Units 6

EARTHING ISOLATORS:-

The term ‘Earthing’ means connecting of the non-current carrying parts of the

electrical equipment or the neutral point of the supply system to the general mass of earth in

such a manner that all times an immediate discharge of electrical energy takes place without

danger.

An Earthing isolator is a large value of capacitance. This can be charged up to

line voltage. Earthing isolator is used to discharge the line capacitance and work on it.

15

Page 16: Training Report Ktps-Final

SWITCH GEAR

The apparatus used for switching, controlling and protecting the electrical

circuits and equipment is known as switchgear.

A switch gear is one which makes or breaks electric circuit. Numerous

problems arise in erection, testing and commissioning of switch gear and various precautions

are to be made in operating and maintenance of switch gear.

Essential Features of Switch Gear:-

1. Complete Reliability

2. Absolutely certain discrimination

3. Quick operation

4. Provision for manual control

5. provision for instruments

The Switch Gears used at KSTPS are indoor types. The main components of indoor

switchgear are given below:-

1. Bus-Bars 2. Isolating Switches

3. Current Transformers 4. Potential Transformers

5. Circuit Breaker 6. Earthing arrangement

7. Relays 8. Inter-Locking arrangements

BUS-BARS:-

Bus bars are defined as the conductors to which several incoming and

outgoing lines are connected. They are essential component of Switchgear. They are made up

of Cu. and Al. The type and designers of Switchgear depends upon rated normal current and

short circuit capacity. The Bus bars are enclosed in bus bar chamber. The bus bar of

neighboring link units is connected by Al links. The incoming and outgoing cables are

provided for metering purposes. The C.T. normally of ring type is fitted on insulated primary.

The insulation is provided by cast resin fittings.

In KTPS there are two types of indoor type switch gear:

1. 6.6 KV or High tension

2. 415 KV or Low tension

16

Page 17: Training Report Ktps-Final

ISOLATING SWITCHING:-

1. They are capable of-

a. Interrupting the Transformer Magnetizing Current.

b. Interrupting line charging Current.

c. Interrupting load Transformer Switching.

2. The main application is in connection with feed or bank Transformer feeders

& there units make it possible to switch out one Transformer while the other is still on load.

CIRCUIT BREAKER:-

They are capable of breaking the circuit on faults. It is heavy duty equipment

mainly utilized for protection of various circuit and separation of loads.

The Circuit Breaker uses on a relay or by manual signal. The Circuit Breakers

which are used in Switchgear are MOCB type.

EARTHED SWITCHES:-

Earthed switch is connected between line conductor and earth. Normally it is

open when line is disconnected. The Earthing switched is closed so as to discharge the

voltage trapped on line for high voltage and so the capacitor between line and earth is

charged to high voltage. For maintenance work their voltage are discharged to earth by

closing the earth switch.

INTER-LOCKING:-

The following type of inter- locking are provided

1. The Circuit Breaker must be in open position before it is lowered in this

position.

2. The Circuit Breaker can be closed only raising the final plug in position.

3. The Circuit Breaker can be closed before raising plug in position.

4. Inter-locking between isolators, Earthing switches and Circuit Breakers are

provided.

RELAYS:-

A Protective Relay is a device that detects the fault and initiates the operation

of the circuit breaker to isolate the defective element from the rest of the system.

17

Page 18: Training Report Ktps-Final

PROTECTION

The fault, which may occur in stator winding are-

1. Phase to phase fault.

2. Phase to ground fault.

3. Short circuit between lines.

4. Over heating.

These faults are due to-

1. Over voltage is because of system transients, lightening switching

surges or sudden loss of load.

2. Insulation deterioration due to any matter, moisture, corona discharge, Hardening

of solid and vibration.

It is very necessary to minimize the tripping time during any fault so that the

lamination is not damaged. The repairing being affected by replacing the faulty stator bar.

A delayed clearance may damage the lamination, so fire may be caused and

partial re-insulation of core may be necessary.

GENERATOR PROTECTION:-

The Generator is required to be tripped or isolated on following types of fault:

1. Failure of generating insulation.

2. Failure of prime mover turbine or boiler.

3. Failure of generating auxiliaries such as hydrogen gas system,

seal oil system, cooling system, and cooling water system.

4. Failure of grid.

The tripping command to the GT breaker is given by master trip relay 866, 86GT, and

86GB. To make it feasible the master trip relay is connected to a common bus. All the

protection relays are connected in between the position of 220V.

D.C. PROTECTION AND THIS COMMON BUS:-

Protection device are that detect abnormal condition in electrical circuit by

measuring the electrical quantity which are different under normal and fault condition. The

basic electrical quantities are voltage, current, phase angle and frequency. The relay doesn’t

operate for normal voltage, normal current, normal phase angle and normal frequency.

Different type of protection can be listed as:

1. Current operated protection.

18

Page 19: Training Report Ktps-Final

2. Different protection.

3. Voltage operated protection.

4. Impedance type protection.

5. Frequency type protection.

1. CURRENT OPERATED PROTECTION:-

a. Generated differential protection.

b. Generative negative sequence protection.

c. Generator output current protection.

d. Generator stator earth fault protection.

e. Generator REF protection.

f. Generator standby earth fault protection.

g. UAT o/c protection.

h. Generator o/c and short circuit protection.

i. L.B.B. protection.

2. DIFFERENTIAL PROTECTION:-

a. Generator overall differential protection.

b. UAT differential protection.

3. VOLTAGE OPERATED PROTECTION:-

a. Generator over voltage protection.

b. Generator stator E/F protection.

c. GT over voltage protection.

d. PT’s voltage supervision protection.

e. Generator inter-turn fault protection.

4. IMPEDANCE TYPE PROTECTION:-

a. Generator back up impedance protection.

b. Generator loss of exact protection.

c. Generator pole slip protection.

5. FREQUENCY TYPE PROTECTION:-

a. Generator under protection Frequency.

19

Page 20: Training Report Ktps-Final

CONTROL ROOM

Various measurements can be taken at the control room simultaneously. The

second important part of the control room is relay part. Various relays are provided here. I.L.

Kota provides the instruments for control rooms.

CONTROL ROOM PANELS:-

CP-I:-

1. FAN CONTROL DESK: -

a. ID Fan (Induced draft fan, 3 nos.) at full load.

b. FD Fan (Forced draft fan, 2nos.) at full load.

c. PA Fan (Primary air fan, 3 nos.) at full load.

2. PRESSURE CONTROL DESK: -

a. Furnace pressure (5-10mm.)

b. Primary air header pressure (750-800mm.)

CP-II:-

1. FUEL CONTROL DESK:-

a. Coal oil flow.

b. Oil pressure.

c. Temperature of mill (inlet or outlet)

d. Flow of air (54 tones per hour)

CP-III:-

a. Drum level control, flow of steam water

b. Pressure of steam and water.

c. Temperature of steam and water.

CP-IV:-

1. TURBINE DESK:-

a. Pressure control, load mode control.

b. Speed control.

c. Ejector, control valves, stops valves and deviators.

CP-V:-

1. GENERATOR CONTROL PANEL:-

a. Voltage, current, MVAR.

b. Stator, rotor temperature.

c. For stator cooling.

20

Page 21: Training Report Ktps-Final

AUXILIARY SUPPLY

Electrical supply system is the most important part of the thermal power

station. The failure of even comparatively small equipment could result in the losing of load

or being put out of commission.

SOURCE OF SUPPLY: -

1. URGENT AUXILLARY: -

Those are associated with running of units whose loss would cause an

immediate reduction unit output.

2. SERVICE AUXILLARY: -

These are common auxiliaries associated with one or more units. There loss

would not affect the output of the unit after considerable time of interval.

SELECTION OF SERVICE VOLTAGE: -

The selection of service voltage at which the large number of auxiliaries in a

station to be supplied has to be made at very early stage in the design. Accordingly the rating

of the unit service voltages is selected. These service voltages for different ratings are:

(1)Above 210MW Three service voltage may be required

415V, 6.6KV & 11KV.

(2)Up to 210MW Two auxiliary voltage of 415V & 6.6KV

are required.

ELECTRICAL AUXILLARY SYSTEM: -

The KSTPS auxiliaries are operated at two voltages that are 6.6KV and 415V.

In respect of 6.6KV system, auto change over facility is provided for change over of source

of supply from unit station in the case of unit trip out. The station is having the following

auxiliary system: -

1. Three phase, 6.6KV, 50 HZ. Underground system for motors

rated above 170KW.

2. Three phase, 4-Wire, 415V, 500HZ. Solidly grounded system

for motor rated up to 170KW.

3. Single phase, 240 V, 50 HZ. System for single phase motors,

AC control circuits and space heaters for motors above 37.5

KW and all switch gear /MCC panels.

4. 220V D.C. underground system for use in control and

protection system.

21

Page 22: Training Report Ktps-Final

3-, 6.6 KV SYSTEM: -

For the running unit, the unit auxiliaries are normally fed from gen’r itself

through 11/7 KV, 15 MVA unit auxiliary transformers, which is, connected to the unit

switchgear viz. USA and USB. Power to station auxiliaries and by unit auxiliary is fed from

220/7 KV, 50 MVA station transformers through two switchgear viz. 55-1A and 55-1B.

415 V SYSTEMS: -

For driving ten 100W motors and other accessories, we need 415V supply. For

this purpose various transformer are used to step down 6.6 KV to 415V at various places. Oil

circuit breaker is provided between 6.6 KV bus and primary winding of transformer.

This system is three phase, 4-wire solidly grounded system is made available

for 1000 KVA, 6.6 KV/ 433V transformer. All 415 circuit breakers are Air Circuit Breaker.

240 V SYSTEMS: -Single - , 240 V, 50 HZ. System is provided for control circuits of

contactors modular of all 415 V switchgear or MCC space heating of various switchgears and

space heating of all motor above 37.5 KW rating. Each of modules with power contactor in

415 V 24 V SYSTEMS: -Single - , 24 V, 50 HZ. Supply is used for winding heating of

motors up to 37.5 KW. This is made available by one or more 1- 415 V/24 V, 4 KVA

transformers. Three transformers are provided with 415 V switchgear/MCB.

220 KV SYSTEMS: -Two 220 KV buses have been provided in switchyard and are inter

connected through a bus coupler. Each of the 2X110 MW generators are connected to this

system through a step up 125 MVA 240/11 KVYDI generator.

220 V A.C. SYSTEMS: -1- 24 V, 50 cycles supply is used for winding heating of

motors up to 37.5 MW. This is made available by 415V/24 V, 4KVA transformer provided

for each 415 V switchgear /MCC. The control circuitry of the motors feeders up to 37.5 KW

ensures that the winding heating supply in switch head off before the main power supply to

motor is switched on.

220 V D.C. SYSTEMS: -

The station 220V D.C. system is used for control, interlocks, and protection

indication and annunciation circuit of various equipments. In addition some critical unit and

station auxiliary also operate on 220 V D.C. e.g. D.C. emergency oil pump for turbine

lubrication D.C. SOP D.C. lightning etc.

22

Page 23: Training Report Ktps-Final

TURBINE

Turbine is an m/c in which a shaft is rotated steadily by the impact of reaction

of steam of working substance upon blades of a wheel. It converts the potential energy or

heat energy of the working substance into mechanical energy. When working substance is

steam it is called ‘Steam Turbine’

In the steam turbine the pressure of the steam is utilized to overcome external

resistance and the dynamic action of the steam is negligibly small.

PRINICIPLE:-

Working of the steam turbine depends wholly upon the dynamic action of steam.

the steam is caused to fall with pressure in a passage of nozzle, due to this fall in pressure, a

whole amount of heat energy is converted into mechanical energy & steam is set moving with

the reactor velocity. The rapidly moving particle of steam enter the moving part of turbine and

here suffers a change in the direction of motion which gives rise to change of momentum and

therefore to a force. This constitutes a driving force to a machine.

The passage of the m/c through the moving part of the turbine commonly

called the blade, may take place in such a manner that the pressure at the outlet sides of the

blade is equal to that of the inlet side. Such a turbine is broadly termed as outlet turbine or

Impulse Turbine.

On the other hand, the pressure of the steam at outlet from the moving blade

may be less than that at type inlet side of the blade. The drop of pressure suffered by the

steam during its flow through the moving blades causes a further generation of kinetic energy

within the blades and adds to the propelling force which is applied to the turbine rotor, such a

turbine is broadly termed as Reaction Turbine.

TURBINE SPECIFICATION: -

Rated output 110 MW

Economic output 95 MW

Rated speed 3000 rpm.

Direction of rotation viewing front pedestal Clockwise

Maximum pressure of steam before the stop valve 145atm.

Maximum temperature of steam before the stop valve 545oC

Maximum pressure of steam before MP Casing 35atm.

Maximum temperature of steam before MP Casing 545oC

23

Page 24: Training Report Ktps-Final

BOILER

A boiler is an enclosed that provides a means for combustion heat to be transfer into water

until it becomes heated water or steam. Its volume increases 1600 times. The process of

heating a liquid until reaches its gaseous states its called evaporation.

The boiler system comprises of

1. feed water system

2. steam system

3. Fuel system

1. Feed Water system:-

It provides water to the boiler and regulate feed according to demand.

2. Steam system:-

It collects and controls the steam produced in the boiler steam are directed

through a piping system to a point of use. Steam pressure is regulated using valves and

checked with pressure gauges.

3. Fuel system:-

Fuel system includes all equipments used to provide fuel to generate the

necessary heat for higher boiler efficiency feed water is preheated by economizer using the

waste heat in the flue gases.

ECONOMIZER:-

The purpose of the economizer is to preheat the boiler feed water before it is

introduced into the steam drum, and to recover some of the heat from the flue gases leaving

the boiler. Economizer is located in the boiler near gas pass below the rear horizontal super

heater. Each section is composed of a number of parallel tube circuits. All tube circuit’s

originate from the inlet header & discharge into the outlet header & economizer header tubes.

SUPER HEATER:-

The super heater is composed of 5 basic stages of sections:

1. Pendant Section

2. Platen Section

3. Rear Horizon Section

4. Steam Cooled Wall

5. Roof Section

1. Pendant Section:-

24

Page 25: Training Report Ktps-Final

It is located directly behind the screen tubes. It absorbs heat by convection.

2. Platen Section:-

It is located directly above the furnace in front of the furnace or arcs. It

absorbs heat mainly by radiation.

3. Rear Horizon Section:-

It is located in the rear vertical gas pass above the economizer. It is the

primary super heater of the convulsive counter flow type.

4. Steam Cooled Wall Section:-

It is from the side front and rear walls and roof of the vertical gas pass.

REHEATER:-

It is composed of two stages or sections the front pendant vertical spaced and

the rear spaced. Rear pendant is located above the furnace arcs between the water cooled

screen tubes and the rear water wall hanger tubes.

AIRPREHEATER:-

The function of an air preheater is similar to that of an economizer. It recovers

some portion of heat of flue (exhaust) gases and transfers the same to the air before it passes

into the furnaces for combination purposes. Air preheater is generally placed after the

economizer, so that the flue first pass through the economizer and then to the air preheater.

Air preheater is of two types, recuperative and regenerative type

TANGENTIAL FIRING SYSTEM:-

In the tangential firing system the furnace itself constitutes the burner. Fuel

and air are introduced to the furnace through four windows assembly located in the furnace

corners. The fuel and air steams from the wind box’s nozzles are directed to a firing circle in

the centre of furnace.

COMPRESSED AIR SYSTEM:-

The following are:

1. Intake air fillers:- In take air filler is used to prevent dust from entering

compressors.

2. Inter stage coders:-Reduce temp of air before it enters the next stage to reduce work

of compression and increase work efficiency. They are normally water Cooled.

3. Air Dryers:-The remaining moisture is removed by using air dryers as air forged

instrument & pneumatic equipments has to be relatively free from any moisture

25

Page 26: Training Report Ktps-Final

WATER TREATMENT PLANT

The principal problem in high pressure boiler is to control corrosion and steam

quality. Internal corrosion cost power station crores of rupees

WATER TREATMENT STAGE:-

River (raw water) → Clarification → Filtration → Demineralization

CLARIFICATION AND FILTERATION OF WATER:-

River water contains different impurities i.e.

Suspended impurities

Biological impurities

Soluble impurities

Colloidal impurities

WORKING:-

The raw water enters through valve and than chemicals is added. Chlorine and

alum are added. Chlorine is added to remove bacteria etc. Alums are added to make the

impurities heavier, once the impurities become heavier than a no. of flocs are formed. By

mixing the alums, heavy impurities are settle down due to gravity and later removed. The

time required for the formation of floc is called retention time which is generally 3 hours but

this can’t be achieved as it require large tank.

In order to cope up the limitation CLARRIFOCCULATION TANK is used.

This flocculation tank is consist of

1. Clarification zone

2. flocculation zone

After the addition of chemical the basic requirement arises is of mixing. Thus

flash mixers are used. Normally the chemicals mix naturally but when the raw water contains

much impurity than agitators are used to mix them.

Clarrifocculation tank has a central pillar which has four windows at 90

degree. The outer circle is half of windows so that level of water is arise then it flows down

through these windows into overflow channel. After mixing from flash mixer, the water

passes on to central pillar and follows the path as shown in fig. i.e. it moves to max. floc area

and comes out from window at 3.5 m height. The downward flow is through perforated wall

which sinks the raw water. Due to the long path a retention time of 4 hour is easily available.

The capacity of water in this plant is 1000*1000 lt./hr. In flocculation zone

max. floc is formed and after removing it, the clear water moves into clarifier. Some

26

Page 27: Training Report Ktps-Final

impurities are weightless and do not settle down so they are passed through filter beds. There

are two types of filter beds.

1. Gravity filter bed.

2. Forced filter bed.

In FORCED FILTER BEDS raisins are added to settle down the impurities.

In GRAVITY FILTER BEDS graded gravels are arranged. At bottom gravels of big size are

there and above other gravels are arranged according to size. Above it grit and most of the

above is sand.

The clarified water enters into sump. Sump is fully closed leaving one window

to see the level. Since it is fully closed hence no foreign matter can enter into it.

DEMINERALIZING PLANT

Water is mainly used for cooling purpose of different parts like bearing winding etc. in

KSTPS. For this water should be Demineralized (D.M. water).

In this plant process water is freed from all dissolved salts. Equipments for

demineralization cum softening plant is supplied and erected by M/S WANSON (India) Ltd.

Pune. This plant consists of two streams, each stream with activated carbon filter, weak acid,

carbon exchanger and mixed bed exchanger. The filter water goes to DM water plant through

250 dia header from where a header top off has been taken off to softening plant. Two

filtered water booster pumps are provided on filtered water line for meeting the pressure

requirement in DM plant.

When pressure drop across filter exceeds a prescribed limit from the activated carbon

filter enter works acid carbon unit. The dilation water enter the weak base anion exchanger

unit water then enters degassifier unit where free CO2 is scrubbed out of water by upward

counter flow of low pressure air flow through degassifier lower and degassed water is

pumped to strong base exchanger(anion –exchanger).

Arrangement for designing ammonia solution into dematerialized water after mixed bed unit

has been provided for pH correction before water is taken into the condensate transfer pump

the DM water to unit condenser as make up. The softening plant is a plant designed to

produce 100 cubic m/hr. of softened water per stream. It is using for bearing cooling.

PH VALUE OF WATER:-

This is recommended to feed the water in the boiler at 25 degree centigrade

and pH value is 8.2 to 9.2 up to 28 days and the pressure is 59 Kg \cm2.

27

Page 28: Training Report Ktps-Final

COAL HANDLING PLANT

INTRODUCTION:-

The term coal handling plant means to store and to handle the coal which is

transported by the train and convey to the bunkers with the help of belt conveyers. Through

the bunkers coal is transferred to the coal mill and drifted to the furnace. The coal handling

plant includes wagon tippler, conveyer belt, crusher house, stacker & reclaimer, bunkers &

coal mill.

Coal Supply in KSTPS:-

The coal for KSTPS is received from BHARAT COKING COAL,

DHANBAD & SOUTH EASTERN COAL FIELD LTD. BILASPUR by train.

Technical Data:-

Wagon Tippler:-

Nos. Two

Capacity 12 box/hr

Tippler motor:-

Make Siemens

Type Slip ring induction motor

Output 71 KW

Vibrating feeders:-

Type Electro magnet

Capacity 350 T /hr

Method of operation Pulsating direct current

Belt weightier type Electromagnetic

Magnetic separator type DC operated electromagnet

Metal Detector:-

Type Two channel power unit

Power supply 230 V

Bunker level indicator:-

Nos. 4 per bunker

Type Mechanical

28

Page 29: Training Report Ktps-Final

Crusher:-

Type Drive ring granulator

Capacity 550 T/hr

Feed size to crusher 300 mm

Type of crusher cleaning Water jet cleaning

Motor rating 500 HP

Vibrating screens:-

Type mechanical vibrating screens

Location crusher house

Capacity 675 T/Hr

Stacker type Reversible stacker

Effective stack pile height 9 m

Travel speed 7.5 to 15 m/min

Location crusher house (a) at loading &

discharge point

(b) At vibrating ends

(c) At ring granulator

2. STAGES OF COAL HANDLING PLANT:-

Wagon Tippler:-

The term Wagon Tippler contains two words WAGON & TIPPLER .Wagon

means the compartment of train which is just like a container which is used to carry the coal

from mines to generating stations & the word Tippler means a machine, which is used to

unload the wagon into the hopper. Hopper is just like a vessel which is made of concrete &

it is covered with a thick iron net on its top. Here big size coal pieces are hammered by the

labors to dispose it into the hopper.

Convey of coal to crusher house:-

After unloaded the coal wagon into the concrete hopper, the supply of coal is

control by Apron Feeder and Scrapper. Apron feeder is made of iron .After passing through

the scrapper conveyor the coal is fed into the Roll Crusher where the crushing of coal takes

place. In the roll crusher there are two shafts on which metal hammer are mounted, these two

rollers rotates in opposite direction to each other. When the coal comes in between these two

rollers it gets crushed into small pieces and then convey to the separator through belt

29

Page 30: Training Report Ktps-Final

conveyor. In Pent house there is a belt weightier which is used to weight the belt which carry

the coal and feed into the separator with the help of Flap Gate .

Primary Crusher house:-

Coal crusher house is a part of coal handling plant where the coal is crushed

with the help of a crusher machines .In crusher machine there is pair of two shafts on which

hammer are fixed. Both shafts rotates in opposite direction due to which when coal comes

between the two shafts crushed into the small pieces and conveyed to the bunkers or open

storage (stacker) according to the requirement through the belt conveyor.

Stacker & reclaimer:-

Stacker is a place where the open storage of a coal takes place. Reclaimer

means the unloading of coal from the stacker.

Coal Mill:-

In coal mill, coal is pulverized or crushed properly into the powdered form.

Hot air is mixed with powdered coal to remove the moisture from the coal, which increases

the efficiency of plant. Pulverization is done to increase the surface area of coal. From coal

mill coal is drift to the furnace with the help of air. There are four main equipment of coal

mill, which are as follows:-

Bunkers:-

These are basically used to store crushed coil which comes from crusher

house.

Feeders:-

These are used to control the supply of crushed coal to the mill depending

upon load condition.

Feeder pipe:-

Feeder pipe are used to convey the crushed coal to the Tube mill or Bowl

mill.

Tube mill:-

Tube mill is used to pulverize the crushed coal. In the tube mill there is a

cylinder which continuously rotates with 17 to 20 rpm. Around the cylinder there are steel

balls which are around of 70 tones in weight and 50 mm in diameter. These balls are known

as thicrome grinding media ball. Coal is pulverized when it comes between the stationary

surface of the shell & the steel ball. Then this pulverized coal is drifted to classifier where

30

Page 31: Training Report Ktps-Final

filtration of coal takes place. In unit 3 to 6 Tube mill is used.

31

Page 32: Training Report Ktps-Final

COOLING TOWER

It is used to reject heat into the atmosphere. There are two types of the cooling

tower.

(1) Natural draft

(2) Mechanical draft

Natural draft tower used vary large concrete chimney to introduce air

through the media. They are generally used for water flow rate about 45000 m3 /hour. It is

used in utility power station.

Mechanical draft tower utilize large fans to force or suck air through

circulating water. The water falls downward over fills surface which helps in increase the

contact time between the water and air. This held maximize heat transfer between two media.

Cooling rates depend upon fan diameter and speed. This type of tower much wider used.

Mechanical draft towers are available in a capacity from approximately 10

tones, 2.5 m3/hour flow to several thousands tones and m3/hour. Many towers are constructed

so that they can be grouped to achieve the desired capacity.

Fills may be horizontal. Water falls over successive layers, splash bars

continuously breaking into smaller droplets. Plastic is better than wood splash filling.

Circulating water pump house has pumps for condensing the steam for condenser. Five

pumps are used for condensing unit no. 1 & 2 and after condensing this water are discharged

back into river.

Each pump has capacity of 8275vcubic m/hr. develop the pressure about 1.94

kgf/sq.cm. Three seal water pumps are used sealing CW pumps shaft at pressure 4.5

kg/sq.cm.

Two pumps for unit 1 and 2 with one stand is used for supplying raw water to

clarified chemical dosing is done in between and clarified water is taken through main line.

From main line water passes through filter bed to filter the water. Clarified water is pumped

to 42 m. elevation by two pump of capacity 270 cubic m/hour at the discharge pressure of 6.9

kg/sq.cm. At 42 meter elevation the water is stored in tank and used for cooling the oil

coolers and returned back to river. Oil coolers are situated at ground and are three in no. each

unit.

32

Page 33: Training Report Ktps-Final

BEARING COOLING WATER

Water from river comes in plant heat exchanger, where its temperature cools

down and that goes in AHP to make slurry. There are 480 plates’ exchangers. BCW

requirements of boiler and turbine auxiliaries of both the units is meet from BCW soft water

overhead tank with the capacity of 2000 cubic meter

DEAERATOR

DEAREATION OF FEED WATER:-

In deareation dissolve gases such as oxygen & CO2 are expelled by preheating

the feed water before it enters the boiler. All natural water contains dissolve gases in solution

(i.e. oxygen + CO2) are released when water heated.

CONDENSER

In condenser steam changes into water. The basic requirement is to remove

latent heat from the steam which is removed by another water (clarified water) when it

accepts the latent heat and becomes hot, than it is passed to cooling tower. In cooling tower

the water is cooled and then mix with river water.

PUMPS

The entire green colored instrument is pumps which are 18 in no.

to further pass the water.

1. FILTER WATER TRANSFER PUMP:-

It is soft section consisting two types:-

(a) BEARING COOLING WATER PUMP:-

All the bearing temperature is controlled through oil bath and filter water is

used. Oil is used to cool the supplied water. Here doesn’t used raw water because at the time

of puncture it enters in the machinery part and small impurity may stop the operation.

(b) CONDENSATE WATER PUMP:-

This pump is coupled with blue colored motor. In order to couple it with

motor a little opening is left through which water leaks out when pumped

2. FILTER WATER TRANSFER PUMP:-

This pump transfers water to D.M. plant. These pumps are in D.M. section.

33

Page 34: Training Report Ktps-Final

3. POTABLE WATER PUMP:-These pump pumps clear water for potable

purpose for whole plant.

H2 GENERATING PLANT

Hydrogen gas is used for cooling purpose for rotor of the generator. For cooling

purpose we have to use 99.9% pure hydrogen. To avoid fire so we have to apply Hydrogen

cooling. It is very difficult to generate and store the Hydrogen gas because it is very

explosive. Hydrogen as a coolant has the following advantages over air:

1. More efficiency and less noise.

2. Better Cooling.

3. More life and less maintenance.

4. Less chance of fire hazard.

5. Better rating.

GENERATING PLANT:-

Hydrogen gas is produced by electrolytic dialysis by mixing KOH in D.M. water.

This reaction is done in electrolyser where Anode and Cathode are applied. Anode plate is

used for collecting H2 and Cathode plate is used for collecting O2. For electrolytic dialysis

3000 Ampere current is passed into electrolyser. O2 is released to atmosphere and H2 is sent

to next machinery for further treatment.

COLLECTING PROCESS:-

H2 Gas from electrolyser → Refrigerator for cooling → Separator to separate the

moisture → Compressor → Catalytic purifier → Dryer (Al2O3) → H2 cylinder. In compressor

H2 is treating in three steps where pressure is raised up to 130 Kg/cm2. In dryer Alumina is

used to absorb moisture.

CAPACITY:-

In KSTPS the full day capacity of H2 generating is 40 cylinders per day. But in plant

per day utilization are of 15 cylinders. Per cylinder capacity is 200-250 kg and stored H2 is

99.8% pure.

PRECAUTION:-

H2 is very explosive gas so we have to take precautionary steps in order to avoid any

accident these steps are as follows

1. To avoid any accident plant timing is fixed 9 A.M. to 5 P.M.

34

Page 35: Training Report Ktps-Final

2. In generating plant underground wiring is used and spark proof lamination bulbs are

employed.

3. Siren:-H2 ppm is kept maintain if it has some variation than Siren will start.

4. Special roof is made for H2 plant so if gas is leakage than it will escape out easily.

35

Page 36: Training Report Ktps-Final

ELECTROSTATIC PRECIPITATOR

If suspended particles are not removed from the flue glass, and it is allowed to be released in

environment, then it would cause a serious threat to the environment, so it becomes necessary

to extract suspended particles from the flue glass and for this purpose ESP is widely used.

WORKING PRINCIPLE:-An electrostatic precipitator is defined as a device

which utilizes electrical forces to separate suspended particles. The electrostatic

precipitator consists of two sets of electrodes , one in form of thin wire called

“discharge or emitting electrode” and other set is called “collecting electrode” in there

form of plate .

CONSTRUCTION:-

The main parts of ESP are as follows:-

Casing

Hoppers

Collecting system

Emitting system

Rapping mechanism for collecting system

Rapping mechanism for emitting system

Insulator housing

CASING:- It is designed for horizontal gas flow to provide for heat expansion, the

casing is supported by roller bearing support.

HOPPERS:-They are of pyramidal shape .Angle between hopper corner and Hz is

never less than 55 degree.

COLLECTOR SYSTEM:-The profiled collecting electrode is based on the

concept of dimensioned electrode stability .The upper plates have hooks and lower

edge has a receiving plate.

EMITTING SYSTEM:- The framework is thoroughly braced and forms a rigid

box like structure, the emitted electrode is made of hard stainless steel wires.

RAPPING MECHANISM FOR COLLECTING SYSTEM:-The system

employs fumbling hammer which are mounted on an Hz. Shaft in a staggered

fashion .A uniform rapping effect is provided for all collecting plates in one

row .Rapping frequency is very low to minimize the dust loss. The hammers are

operated by motor, so that they strike the plate at fixed frequency.

36

Page 37: Training Report Ktps-Final

ASH HANDLING PLANT(A.H.P)

The ash handling system is provided for continuous collection of bottom ash from the furnace

hearth and its intermittent removal by hydro ejectors to a common slurry sump .It is also

provided for removal of fly ash to the common slurry sump. Each boiler is provided with ash

precipitator for collecting the fly ash from the flue gases with high efficiency of collection to

minimize the dust mains and to reduce the wear of induced draft fan .The fly ash separated

from flue gases in the ash precipitator is collected in hoppers at the bottom from where it is

mixed with water to form slurry, and disposed off to pumping area by means of hydro ash

pumps .Bottom ash from the boiler furnace is passed through slag crushers and then slurred to

the slurry chamber at the suction of the ash disposal pumps .These are high pressure and low

pressure pumps for this purpose .At a time one pump is working and other two are stand by .

From the ash disposal pump house ash slurry is pumped through pipe lines to

the ash damp area within about 1.5 km away from the disposal pump house .two separate

discharge lines are provided one for each unit but only one line is used .The ash slurry from

the two units is taken in one discharge line through electrically operated valves.

SOOT BLOWING

Soot blowing is the process by which we clean the boiler tubes with the help

of steam .A large number of tubes are present inside the boiler .Slowly the fine ash particles

get collected on the tube surface and form a layer, this layer of ash particles is called soot. It

reduces the thermal conductivity.Mainly three types of soot blowers are used in KSTPS.

1. Water wall

2. Super heater soot blower (S.H.S.B)

3. Airpreheater soot blower (A.P.S.B)

1. WATER WALL:-They are 40 in no. and have travel time of 1.5

minute .Initially these are outside the boiler ,when soot blowing process start ,the

glance of the soot blower enter inside the boiler and then rotate and come outside

again .

2. SUPER HEATER SOOT BLOWER:-They are 28 in no. and travel time 6

minute .It has transverse of 5 m inside the boiler .It enters and come out in rotated

motion ,so it rotates in both the cases .

3. AIR PREHEATER SOOT BLOWER:-

37

Page 38: Training Report Ktps-Final

There are only 2 A.P.H.S.B and has 55 minute traveling time .It is like a disc ,and

have only rotary motion and takes 55 minute for completing the cycle.

38

Page 39: Training Report Ktps-Final

EFFICIENCY

In KSTPS we convert potential energy or chemical energy of the fuel into heat

by the process of combustion. The heat is given to the water and it converts its form into

steam. The pressure of steam rotates the turbine, which is now in the form of kinetic energy.

Generator producing electrical energy, which is sand to different localities for utilization,

consumes this kinetic energy.

Enthalpy is defined as the thermodynamic property of a system, is equal to

the sum of the sum of its internal energy and the product of its pressure and volume.

Enthalpy is an ancient Greek word meaning evolution and many eminent

scholars have been attempted to define it. It is a mathematical concept of available energy in

the steam.

Efficiency in the case of electrical generator process can be expressed as the

amount of heat energy librated in the boiler compared with the amount of electrical energy

generated with it.

PLANT EFFICIENCY: -

We will divide whole plant efficiency in four-component efficiency:

(1). Cycle efficiency

(2). Turbo generator efficiency

(3). Boiler efficiency

(4). Auxiliary power efficiency

Overall = Boiler x Turbine x Cycle x Generator

1. CYCLE EFFICIENCY: -

Cycle efficiency being the maximum possible heat energy that could

be obtained from any particular set of steam conditions employed. The operation of heat

reduction of condenser, which is almost 50% of the total available heat, makes ranking cycle

relatively inefficient.

39

Cycle = energy available for conversion in work Energy given in boiler as heat

Page 40: Training Report Ktps-Final

It can be controlled by: -

(a). Condenser vacuum.

(b). Steam conditions of CV and LV

(c). Regenerative feed heating.

2. ALTERNATOR EFFICIENCY: -

The alternator is a efficient machine at about 98 % efficiency. The losses are:

(a). Copper and iron loss

(b). Wind age losses

Operationally the plant is governed by the grid requirements. For voltage we

use the set out from generator transformer.

3. BOILER EFFICIENCY: -

It depends upon:

(a). Dry flue gas loss: Increase by excess air in boiler.

(b). Wet flue gas loss: Moisture in coal.

(c). Moisture in combustion loss: Hydrogen loss.

(d). Radiator and in accounted loss.

4. TURBINE EFFICIENCY: -

It means the efficiency of steam turbine in converting the heat energy made

available in the cycle into actual mechanical work.

Turbine losses falls into one or two groups either losses external to the turbine

or losses directly related to the expansion of the steam in the cylinder.

40

Page 41: Training Report Ktps-Final

CONCLUSION

The first phase of Practical Training has proved to be quite fruitful.

It provides an opportunity for encounter with such huge machines like wagon tippler,

110MW & 210MW Turbines and Generators.

The architecture of the power plant, the way various units are linked and the

way working of whole plant is controlled make the student realize that engineering is not just

learning the structure description and working of various machine but the great part is of

planning proper management.

It also provides an opportunity to lean low technology used at proper place

and time can cave a lot of labor e.g. Wagon tippler (CHP).

But there are few factors that require special mention. Training is not carried

to its true spirit. It is recommended that there should be some project specially meant for

students where presence of authority should be ensured. There should be strict monitoring of

the performance of students and system of grading be improved on basis of work done.

However training has proved to be quite fruitful. It has allowed an opportunity

to get an exposure of the practical implementation to theoretical fundamentals.

41