Kota Thermal Power Station
Training Session May,09 ± June,09
Submitted By:-
Ankit Kulshreshtha
EC-1
Roll No. 06/N/028
8/2/2019 55481377 Ankit KTPS Training
http://slidepdf.com/reader/full/55481377-ankit-ktps-training 2/22
Industry at a glance :-
Location:- On the bank of river Chambal in Kota
(Rajasthan)
Produce electricity by coal
Having 6 units (presently) producing continuouslyProduce almost 1024 MW energy ,second to
Suratgardh power plant
Get coal from Madhya Pradesh coal fields
Have 4 big 180 meters height chimneys to controlsuspended particles
Record of having 85% power factor, get clearance
from CEA
8/2/2019 55481377 Ankit KTPS Training
http://slidepdf.com/reader/full/55481377-ankit-ktps-training 3/22
Unit Details of KTPS
Units Date of synchronization
on oil
Date of synchronization on
coal
Date of declaration
of Commercial
Operation
Unit-1 17.1.83 20.1.83 01.04.83
Unit-2 17.7.83 05.8.83 01.04.84
Unit-3 25.9.88 11.12.88 11.03.89
Unit-4 01.5.89 16.10.89 06.03.90
Unit-5 26.3.94 11.10.94 18.07.95
Unit-6 30.07.2003 30.7.2003 01.08.2004
8/2/2019 55481377 Ankit KTPS Training
http://slidepdf.com/reader/full/55481377-ankit-ktps-training 4/22
Basic Process of Thermal Power plant
8/2/2019 55481377 Ankit KTPS Training
http://slidepdf.com/reader/full/55481377-ankit-ktps-training 5/22
The KTPS working is based on four
Sections
Coal and Ash
Air and gas
Feed water and steam
Cooling water
8/2/2019 55481377 Ankit KTPS Training
http://slidepdf.com/reader/full/55481377-ankit-ktps-training 6/22
Coal and ash
Air and gas
Feed w
ater
Coolingtower
8/2/2019 55481377 Ankit KTPS Training
http://slidepdf.com/reader/full/55481377-ankit-ktps-training 7/22
Detail Working of KTPS
8/2/2019 55481377 Ankit KTPS Training
http://slidepdf.com/reader/full/55481377-ankit-ktps-training 8/22
Coal Handling
Coal is supplied
Through railTrack by own trains
By wagon tripler The coal is drawn
Into underground hopper
By means of twoBelts coal is transferred
To the Conveyer
Now coal is transferred toCrushing house and
storedto bunkers
Now coal is fed to MillsWhere coal is
Crushed in pulverizedform
Coal is takento Coal nozzle
In wind box assembly
From nozzlecoal Is
discharged tofurnace
8/2/2019 55481377 Ankit KTPS Training
http://slidepdf.com/reader/full/55481377-ankit-ktps-training 9/22
There are two types of Mills in KSTPS
Bowl Mills-
Grinding chambers in form of Bowl
Centrifugal force is used to movecoal against grinder
FD fan is used to dry the coal &
drive it to furnace
Tube mills-
Constantly rotating tube around 20rpm
Side at which gas gear is mountedis known as driving end
3 balls of diff. size is used FD fan is used to dry the coal &
drive it to furnace
Here hot air is used to remove moisture from coal and cold air is used to keep temp below flash point
Power consumed by Coal Mill Motor is 340 MW. There are total 8 motor are installed 6 running 2 on
stand by
PA fans = 820 KwID fans = 850 kw
FD fans = 300 kw
8/2/2019 55481377 Ankit KTPS Training
http://slidepdf.com/reader/full/55481377-ankit-ktps-training 10/22
Burner :- Tangential type
discharge the fuel air mixture tangentially
to an imaginary circle in the center of the
furnace
burners are placed at the four corners of
the furnace
Firing Mechanism-Fuel is introduced from
wind nozzle located at lower corner inside
the boiler
8/2/2019 55481377 Ankit KTPS Training
http://slidepdf.com/reader/full/55481377-ankit-ktps-training 11/22
Boiler :- A apparatus where water is being converted into steam
The water in the tube of boiler get vaporized by heat energy &steam is generated
The boiler weighs about 6000 Mega tons ,height about 50 to 60meters
Whole height is divided in 13 diff. levels as per burning materials
8/2/2019 55481377 Ankit KTPS Training
http://slidepdf.com/reader/full/55481377-ankit-ktps-training 12/22
Boiler Auxileries- To increase efficiency
Economiser ±Used to preheat boiler feed water, before entering to boiler
Deriving heat from the flue gases
The economizer is placed in the main flue gas path between the boiler and the chimney.The waste flue gases flow outside the tubes and heat is transferred to the water flowing inside
Air Preheater ±Tubular type heat exchanger
The flue gases coming out of the economizer is used to preheat the air before supplyingit to the combustion chamber. An increase in air temperature of 20 degrees can beachieved by this method. The pre heated air is used for combustion and also to drythe crushed coal
Useful to increase efficiency (20% flue gas incrs 1% capacity)
In KTPS Regenerative type is used (Having rotor move at 2.4 RPM )
Boiler Drum ±To separate water from steam
It is located 54 meter from ground
Feed water coming out of Economiser enter to the Boiler Drum
8/2/2019 55481377 Ankit KTPS Training
http://slidepdf.com/reader/full/55481377-ankit-ktps-training 13/22
Turbine :- A machine which convert Kinetic energy
to Mechanical energy
Steam is passedthroughnozzle
Steam nowfalls onTurbine blade
movesthe turbine
Parts of Turbine
A.) Nozzle
B.) Blade
C.) Rotor shaft
Flow chart
for turbine
The rotor shaft is made of steel, blade is fixed on it
Steam is entered from left and right inlets
Two stage turbine is used
Steam is recycled
8/2/2019 55481377 Ankit KTPS Training
http://slidepdf.com/reader/full/55481377-ankit-ktps-training 14/22
Auxiliaries of turbine :-
Condenser ±Here steam is exited by creating vaccum or very low atm pressure ,the cooling water is directly taken fromchambalrequirement ± as discharge from LPT is Liquid+vapour
Hotwell ±It is located below the condenser ,to store condensate ,tank of size 5m in depth & 2 to 3m in dia.makeup of leakage of demineralised water also processed
Deaerator ±It removes the dissolved gases like O2 , CO2 etc by means of pagging.requirement- As dissolved gases may corrode Boiler Drum
High Pressure Heater ±It raise the temp & pressure of water which is requiredfor further processing i.e. 165 kg/cm and 2500 C
8/2/2019 55481377 Ankit KTPS Training
http://slidepdf.com/reader/full/55481377-ankit-ktps-training 15/22
Generator :-Machine that coverts Mechanical energy to the
Electrical energy
Principle-Based on faraday¶s law of electromagnetic induction
Statistics of generator at KTPSKW : 210 Kw
PF : 0.85
KVA : 247000
RPM : 3000
Hz : 50hz
Coolant :Water + H2
8/2/2019 55481377 Ankit KTPS Training
http://slidepdf.com/reader/full/55481377-ankit-ktps-training 16/22
Parts of Generator
Stator Frame ±Welded construction of plate
Used to contain and support the stator core winding, also provide H2 as coolant
Stator core ±Built of Segmented ,annealed ,insulated ,high quality ,Silicon Sheet ,to give min electrical
lossStator Bars ±Each stator half coil bar is composed of alternate strip of double glass covered and bars
copper transposed in straight position, each strip occupies every radial position
Rotor ±It is forged on a single piece of special Cr, Ni & Mo alloy steel ,to get required mech prop.
Rotor WindingIt consist of two poles each having concentric coils of several turns
Semi hold silver alloy copper of rectangular cross section is used, insulated by epoxy
Glasses laminated stripes CONT««
8/2/2019 55481377 Ankit KTPS Training
http://slidepdf.com/reader/full/55481377-ankit-ktps-training 17/22
Rotor bearing-Specially designed bearing electronic apparatus to indicate the location of unbalance
pole in magnitude and direction.
Slip Ring ±Made of forged steel they are located side by side on exciter side of generator shaft
Generator Terminal Bushing ±Have six output 3 larger and 3 shorter ,coming out of bottom, short terminals used for
External connection ,conduction is through a Cu tube ,H2 as coolant is used.
Bush Gear Assembly ±Made of natural composition of Graphite and winding materials, have low friction , self lubricating
8/2/2019 55481377 Ankit KTPS Training
http://slidepdf.com/reader/full/55481377-ankit-ktps-training 18/22
Control Room:- Where controlling of various equipment taken
place
Setup is done by Instrumentation Limited, kota
From one unit control 2 adjacent unit can be controlled + local CS for boilers ,turbo jets,boilers
CR shows and record various parameters
Automatic Scheme for feed water regulation and reheat temp computation is provided
One CR have five desks as follows :-
CP ± I
1 FAN CONRTOL DESKa. Induced Fan draft
b. Forced Fan
c. Primary air Fan
2. PRESSURE DESK
a. Furnace pressure
b. Primary Air Heater Pressure
CP ± II
1 FUEL CONTROL DESKa. Coal air flow
b. oil pressure
c. temp of mill
d. flow of air
e. differential pressure of mill CONTD«..
8/2/2019 55481377 Ankit KTPS Training
http://slidepdf.com/reader/full/55481377-ankit-ktps-training 19/22
CP ± III
1. STEAM AND WATER DESK
a. Drum Level control
b. Flow of Steam and Water
c. Pressure of steam and water
d. Temp of steam and water
CP ± IV
1. TURBINE DESK
a. Pressure Control
b. Load control
c. Speed control
d. Valves control
CP ± V
1. GENERATOR CONTROL DESK
a. Voltage Control MVAR
b. Stator rotor Temp
c. For stator cooling a) Water
b) H2
8/2/2019 55481377 Ankit KTPS Training
http://slidepdf.com/reader/full/55481377-ankit-ktps-training 20/22
Facts about KTPS
Kota Thermal Power Station has performedoutstanding, from the very beginning, produced
outstanding results and has continuously
earned cash prizes and shields. Power station
has received meritorious productivity awards
given by the Ministry of power, Government of India, in the years 1984,1987, 1989, 1991 and
continuously thereafter.
The 6th unit of Kota Super TPS was
commissioned and synchronized with the gridon 30.7.03 and full load was achieved on coal
firing in less than 10 Hrs. The project was
completed in 24 months which is a national
record for this type of generating unit.
8/2/2019 55481377 Ankit KTPS Training
http://slidepdf.com/reader/full/55481377-ankit-ktps-training 21/22
Conclusion :-
K.S.T.P.S. is the main super thermal power plant
located in principle industry city, Kota.
It has established a record of excellence &
earned various productivity award from TheMinistry of power, Government of India.
8/2/2019 55481377 Ankit KTPS Training
http://slidepdf.com/reader/full/55481377-ankit-ktps-training 22/22
Thank youQuery Please