Date : May 27, 2011Project : Sea Residences Phase 3Subject : COST ESTIMATE
CORNER UNITS
ITEM DESCRIPTIONORIGINAL PLAN ADDITIONAL TRENCH DRAIN AT ROOFDECK
QTY UNIT UNIT COST TOTAL COST QTY UNIT UNIT COST TOTAL COST
1 MECHANICAL NO COST IMPLICATION
PhP0.002 PLUMBING NO COST IMPLICATION
3 FIRE PROTECTIONa. B.I. Pipes
50mm 4.50 lm PhP678.00 PhP3,051.00 5.50 lm PhP678.00 PhP3,729.0040mm 10.00 lm PhP515.00 PhP5,150.00 4.00 lm PhP515.00 PhP2,060.0025mm 8.00 lm PhP298.00 PhP2,384.00 3.50 lm PhP298.00 PhP1,043.00
b. Sprinkler HeadSidewall 4.00 pcs PhP336.00 PhP1,344.00 2.00 pcs PhP336.00 PhP672.00Pendent 5.00 pcs PhP613.00 PhP3,065.00 7.00 pcs PhP613.00 PhP4,291.00
TOTAL AMOUNT PhP14,994.00 PhP11,795.00
TOTAL (DEDUCTIVE) AMOUNT Php 3,199.00
Prepared by:;Design Coordinates, Inc.Construction Project Managers
Arch. Cid V. OrbetaConstruction Project Manager
Cost EstimatePer SRP3-WAO-CP01-006