Government of India (:\<01 C1 cH:;j I (>I <01 ',j Ministry of Power 3ITR C1 fi fJl f8 ',j Northern Regional Power Committee /108/04/2017 /Cjj71-Cj.Q..o<) No. NRPC/OPR/108/04/2017/ #err it I To, lAs per list attached : 08.08.2017 Date:08.08.2017 fctrsn.r: 'F..-j 'ti I 'C, 3TR "2Al dJ ;jCf cfiT "RfRCff m Subject: 11th meeting of Telecommunication, SCADA& Telemetry Sub Committee 'iui"'ll ;S, fCfim * "2:<Jlikfl (R) cfiT"RfRCff m 10.07.2017 cf.r \3". 1ff. fcr. , it 3l1'4IRid cf,r ml CfiT Cfl141'd \3". 1ff. fcr. cf,r 4Clfll'.S2. (www.nrpc.gov.in) 1R The 11th meeting of TeST sub-committee was held on 10 th July 2017 at NRPC, New Delhi. Minutes of this meeting have been hosted on NRPC website (www.nrpc.gov.in). \ ;.;=cT Lj \ t, " 7', - () (Hemant Kumar Pandey) (anft. arRr. & m;jCf I SE &Member Convener TeST sub-committee) .. C!/17 -181;[, fitn "lllT'hc<Ii!l:41 m:r<r , .,-{ - 046 it<m: 011-26865206 f-it'f: [email protected] mw: www.nrpc.gov.in

Upload: others

Post on 07-Apr-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ~~ ;.;=cThpaldc.org/NRPC_TeST/11/11_Minutes.pdf(ii) Regarding Noida (Sector 20) – Greater Noida 400 kV line under package -V, POWERGRID representative informed that due to non-availability

~fF{chl{

Government of India

~ (:\<01 C1 cH:;j I (>I <01 ',j

Ministry of Power

3ITR ~ ~(:\<OI C1 fi fJl f8 ',j

Northern Regional Power Committee

"ff.\3"~/~"'l1~1 /108/04/2017 /Cjj71-Cj.Q..o<) No. NRPC/OPR/108/04/2017/

#err it I To, ~ ~ ~ ~ lAs per list attached

~ : 08.08.2017 Date:08.08.2017

fctrsn.r: 'F..-j 'ti I 'C, ~ 3TR "2Al ~ dJ ;jCf ~ cfiT "RfRCff m Subject: 11th meeting of Telecommunication, SCADA& Telemetry Sub Committee

'iui"'ll ;S, fCfim * "2:<Jlikfl (R) cfiT"RfRCff m 10.07.2017 cf.r \3". 1ff. fcr. ~ , ~ ~ it 3l1'4IRid cf,r ~ ml ~ ~ CfiT Cfl141'd \3". 1ff. fcr. ~ cf,r 4Clfll'.S2. (www.nrpc.gov.in) 1R ~ ~~~~I

The 11th meeting of TeST sub-committee was held on 10th July 2017 at NRPC, New Delhi. Minutes of this meeting have been hosted on NRPC website (www.nrpc.gov.in).

\ ~~ ;.;=cT Lj \ t, ~.'~:'

" 7',

- () (~)

(Hemant Kumar Pandey) (anft. arRr. & ~ fi~I\JjCfl m;jCf ~ I

SE &Member Convener TeST sub-committee)

~ ..

C!/17

-181;[, ~rtT5;;fTIr fitn "lllT'hc<Ii!l:41 m:r<r , .,-{ ~110016 - ~:011-26521 046 it<m: 011-26865206 f-it'f: [email protected] mw: www.nrpc.gov.in

Page 2: ~~ ;.;=cThpaldc.org/NRPC_TeST/11/11_Minutes.pdf(ii) Regarding Noida (Sector 20) – Greater Noida 400 kV line under package -V, POWERGRID representative informed that due to non-availability

List of Members of TeST sub-committee:

1. Chief Engineer(SLDC), PTCUL, Dehradun-248001, (Fax-0135-2530336) 2. Dy Chief Engineer (SO) BBMB, Chandigarh-160019, (Fax-0172-2549548) 3. Chief Engineer (GM), CEA, R. K. Puram, New Delhi-11 0066, (Fax-011-261 09750) 4. Chief Engineer, UT of Chandigarh, Chandigarh-160009, (Fax-0172-2740276) 5. General Manager (SLDC) , DTL, New Delhi-110002, (Fax-011-23221012) 6. Chief Engineer (SO),HPGCL, Panchkula-1341 09, (Fax-0172-2560622 & 2565042) 7. Chief Engineer, HPPTC Ltd., Shimla-171004, (Fax-0177-2626284) 8. Superintending Engineer, SLDG, HP Load Dispatch Society, Totu, Shimla, (Fax-0177-

2837543) 9. Chief Engineer (SO&P)HPSEB Ltd, Shimla-171004, (Fax-0177-26163554) 10. Chief Engineer (SLDC) PSTCL, Patiala, (Fax-0175-2304017) 11. Chief Engineer (Distribution), PSPCL, The Mall, Patiala, (Fax- 0175-2212069) 12.Dy. Chief Engineer(PLCC), RVPNL, Heerapura, Jaipur-302005, (Fax-0141-2250967) 13. Chief Engineer (TO), UPRVUNL, Lucknow-226001, (Fax-0522-2287861) 14. General Manager (RMU), UJVNL, Dehradun-248006, (Fax-0135-2530708) 15.Chief Engineer (O&M), NHPC, Faridabad-121003, (Fax-0129-2255706) 16. General Manager (OS)(NCR), NCR-HQ, NTPC, Noida-201301, (Fax-0120-241 0052) 17. General Manager(ULDC) & General Manager (LD&C) PGCIL, New Delhi-110016,

(Fax-011-26564849) . 18.General Manager (C&SO), SJVNL, Sharma Niwas, Below BCS, New Shimla-171009,

(Fax-0177 -2673283) 19. General Manager (Electrical Design),THDC, Rishikesh-249201, (Fax-0135-2438682) 20.Addl. Chief Engineer Jaiprakash PVL, Noida, (Fax-0120-4516101/4516201) 21. General Manager (Technical), IPGCL, New Delhi-110002, (Fax-011-23270590) 22.GM(0&M) DTL, New Delhi-110002, (Fax-011-23232721) 23. General Manager, NRLDC, New Delhi-110016, (Fax-011-26853082) 24. Chief Engineer (SO&C), SLDC, HVPNL, Sewah, Panipat , (Fax-0172-2560622) 25. Dy. General manager, Rosa PSCL , (Fax-05842-300003) 26. Chief Engineer(SLDC), UPPTCL, Lucknow.(Fax 0522-2287880) 27. Chief Engineer(Transmission), NPCIL, Mumbai-400094, (Fax-022-

25993570/25991258) 28.DGM, Electrical, Jhajjar Power Ltd., Haryana, (Fax-01251-270155 29. Director, Lanco Anpara Power Ltd., (Fax-124-2341627 30. GM (Comml.), Aravali Power Company Pvt. Ltd., NOIDA, (Fax-0120-2425944) 31. Development Commissioner (P) , POD, Srinagar, J&K, (Fax-0194-2452173) 32. Managing Director, J&K State Power Dev. Corp., Srinagar, J&K, (Fax-0194- 2500145) 33. HOG power system control , TATA Power Delhi Distibution Limited, New Delhi, (Fax-

011-66050601), CENNET building, Opp to PP Jewellers Netaji subhsh place" New Delhi ( Kind Attn Sh.P Devanand)

34. Sr. Vice President, JSW Energy Ltd., New Delhi-11 0066 (Fax: 46032343/26183546) 35. Managing Director, UPCL, Dehradun-248006, (Fax-0135-2768867)

-181;[, ~~;;ftcr fmPH'YificCl if{4i m:r<:r • 3i ~110016 - 'liR:011-26521046~: 011 -26865206 {-it<1: [email protected] ~ www.nrpc.govin

Page 3: ~~ ;.;=cThpaldc.org/NRPC_TeST/11/11_Minutes.pdf(ii) Regarding Noida (Sector 20) – Greater Noida 400 kV line under package -V, POWERGRID representative informed that due to non-availability

1

Minutes of 11th meeting of Telecommunication, SCADA & Telemetry (TeST) Sub-

Committee

1. Confirmation of Minutes:

The minutes of 10th meeting of TeST sub-Committee held on 22.03.2017 were issued on

13.04.2017. Comments from UPPTCL were received. After discussion, as per request by UPPTCL,

following amendments to MOM of 10th TeST meeting is made in the minutes Item no 2.2.4 d and

3.3.6:

(i) Following sentence is added after last sentence at para (d) of item no. 2.2.4:

“Powergrid representative also informed that congestion, buffering or loop formation

may be the probable reasons and suggested that as a first step bandwidth may be

increased from existing 2MBPS and then latency issues, if persists may be examined

further.”

(ii) Following sentence is added after last sentence of Item no. 4.5.1:

“But UPPTCL asserted that difference between SEM & SCADA data of all the

mentioned points is more than 3% and the same may be reviewed and rectified at

NRLDC/POWERGRID end in view of commercial importance on the matter.”

With the above amendments the MOM was approved by the TeST sub-Committee.

2.1 OPGW installation under central and state sectors:

2.1 OPGW installation under Central and State sectors:

2.1.1 Latest status of OPGW installation progress under Central sector:

2.1.1.1 POWERGRID informed that out of 5203 Kms. of OPGW under Central sector, OPGW of 5085

Kms had been completed. The details of balance OPGW, which was on under - construction

lines are as under:

i) Abdullapur – Dehradun – 64.6/89 Kms (Balance 24.4 Kms.)- Expected to be completed by

Sept’ 2017

ii) Kishenpur – Dulhasti – 36/119 Kms (Balance 83 Kms.)-Expected by Sept’ 2017

iii) Uri-II to Uri-I line - 10Kms. (Deleted due to sever ROW)

1. Confirmation of Minutes

2. Telecommunication related issues

Page 4: ~~ ;.;=cThpaldc.org/NRPC_TeST/11/11_Minutes.pdf(ii) Regarding Noida (Sector 20) – Greater Noida 400 kV line under package -V, POWERGRID representative informed that due to non-availability

2

2.1.1.2 Representative of POWERGRID, NR-II intimated that transmission line construction work of

Abdullapur-Dehradun and Kishenpur-Dulhasti lines was hampered due to sever ROW

problems. The completion of lines as well as OPGW laying is expected by Sept’ 2017.

2.1.1.3 Regarding, commissioning of Uri-I line, POWERGRID informed that equipment has been

installed and due to higher losses in OPGW between Kishenpur-Wanpoh link, Uri-I could not

be commissioned. OPGW rectification work is going on and most likely this link will be

commissioned by end of July, 2017. On enquiry by NRLDC regarding wideband link

availability of Uri – II, it was informed that one link for this station will be on PLCC and the

other link will be through NHPC network which is on BSNL network.

2.1.1.4 Replying to NHPC representative regarding status of OPGW for Parbati-III, POWERGRID

informed that during last NRPC meeting held on 02nd May,2017 OPGW connectivity for

Parbati-III had been approved under Reliable Communication Scheme for Northern Region.

However, POWERGRID had considered Parbati-III under SDGI package. FAT had been

completed for this OPGW and materials would be delivered by end of August’ 2017.

2.1.1.5 On enquiry of NRLDC for balance links which were approved in last RPC meeting,

POWERGRID informed that 5474 kms. of OPGW had been approved for which DPR was

under approval stage. It was informed that these links would be completed in next 3 years.

Member secretary, NRPC opined that important links should be completed on priority.

POWERGRID agreed on the same.

2.1.2 Latest status of OPGW installation progress under State sector:

2.1.2.1 The progress as updated in the meeting, by POWERGRID, are as under:

Sl.

No.

Name of Package Award Date Completion

schedule

Status

1 OPGW for State sector

(Package-V)

M/s ZTT/ECI/Steel Product

July, 2015 Sept, 2017 Out of total 1669 Kms,

1613 Kms. Completed.

Balance OPGW - 56 Kms.

2 OPGW for State sector

additional requirement

(Package-I a) (supply Pkg)

M/s SDGI-Offshore

contract

Oct, 2015 Dec,2017 Initial Scope: 2800 Kms.

Scope at Present: 3374

Kms.

Supply completed: 2068

Kms.

FAT for additional 700

Kms completed.

3 OPGW for Additional

requirement for CS and SS

Sept, 2015 Dec,2017 Revised scope: 706 Kms.

under central sector lines.

Page 5: ~~ ;.;=cThpaldc.org/NRPC_TeST/11/11_Minutes.pdf(ii) Regarding Noida (Sector 20) – Greater Noida 400 kV line under package -V, POWERGRID representative informed that due to non-availability

3

(Package-III a)

M/s Prem Power

Supply completed.

Installation work is under

progress.

2.1.2.2 Regarding Package –V following was deliberated:

(i) POWERGRID informed that OPGW on UPPTCL’s Muradnagar-Loni line could not be laid

due to severe ROW issues since One and half year. It was also informed that

POWEWRGRID had already informed to UPPTCL regarding this issue. POWERGRID

representative opined that OPGW work on this line may be deleted from main contract.

However, UPPTCL assured that they would make effort to resolve Right of Way (RoW)

issue. POWERGRID representative stated that if RoW issue is not resolved shortly then they

would be constrained to delete the work from scope and the material would be handed over to

UPPTCL. Member Secretary, NRPC advised UPPTCL that they should make all out efforts

to resolve the RoW issue at the earliest as communication links are necessary.

(ii) Regarding Noida (Sector 20) – Greater Noida 400 kV line under package -V, POWERGRID

representative informed that due to non-availability of shutdown for both the circuits of mono

pole tower, this link could not be completed. POWERGRID representative raised the issue of

non-availability of tower design drawings. He informed that in spite of repeated requests

UPPTCL could not provide the drawings. UPPTCL confirmed that drawing of mono pole

tower would be provided within a week’s time.

(iii) For Bamnauli-Ballabhgarh link, of DTL under package –V , it was informed that

POWERGRID was ready to do OPGW stringing on live line condition, however DTL denied

the permission till end of Aug,’2017 citing high load condition of Delhi and other line being

on ERS.

(iv) Kishenpur-New Wanpoh (Central Sector link-balance-37Kms): This is under construction

transmission line and OPGW would be completed with transmission line completion, Severe

ROW issues are involved in this line. Tentative target for line completion is Oct’2017.

(v) Equipment installation would be completed by Dec,17 for whole package.

2.1.2.3 Regarding Package-Ia, POWERGRID representative stated that this is only off-shore supply.

Installation package had been awarded by respective Region of POWERGRID i.e. New Delhi and

Jammu. POWERGRID informed that installation work for Northern Region-I was awarded to M/s

Metric but due to non-deployment of teams, work order had been terminated and new package was

under award stage. The OPGW installation would be completed by March, 2018. For NR-II links

also installation work would be completed by March, 2018. It was also informed that due to

ongoing paddy season in Punjab and increase in scope of work the implementation was delayed.

2.1.3 Status of OPGW connection at NHPC Power Stations

2.1.3.1 NHPC representative informed that there are two links (OPGW and PLCC) for data telemetry at

Dhauliganga Power Station. OPGW link of Dhauliganga Power Station had been down since

05.04.17 and telemetry was through PLCC only, which was intermittent in nature. Representative

of POWERGRID informed that OPGW was restored but due to non availability of redundant

Page 6: ~~ ;.;=cThpaldc.org/NRPC_TeST/11/11_Minutes.pdf(ii) Regarding Noida (Sector 20) – Greater Noida 400 kV line under package -V, POWERGRID representative informed that due to non-availability

4

gateway data was being transmitted through single channel i.e. through PLCC. POWERGRID

requested NHPC to arrange for redundant gateway, and till arrangement of other gateway NHPC

may switchover the Link from PLCC to OPGW. NHPC informed that shifting of Link at

Dhauliganga Power Station was done on Saturday by Tejas and the problem could not be resolved.

POWERGRID informed that they would rectify the issue by 15/07/2017.

(Action: POWERGRID; Time line: 15/07/2017)

2.1.3.2 Regarding OPGW connectivity of Dulhasti, it was informed by POWERGRID that out of 119

KMs., work of laying OPGW has been completed only for 36 KMs. It was also informed that

approximately 8.5 KMs of erection work in Dulhasti-Kishenpur transmission line-2 is left and the

delay in completing the same is due to ROW issue. The same would be completed by August 2017.

After completion of erection work of above line the balance work for laying of OPGW for 83 KMs

would also be completed.

2.1.3.3 It was further informed that OPGW connectivity for Bairasiul and Sewa-II station has been

completed and after terminal equipment supply, link would be commissioned by Sept’ 2017.

2.1.3.4 Representative of POWERGRID informed that OPGW connectivity of Parbati-II, and Parbati-III

etc. was approved in 34th NRPC meeting held on 02nd May 2017 and NIT work under progress.

2.1.4 OPGW connectivity to NR generating stations

2.1.4.1 NRLDC representative stated that implementation schedule of OPGW connectivity to following

generating stations, which was approved in NRPC may be intimated by POWERGRID:

i. Karcham HEP

ii. Jhajjhar TPS

iii. Sorang HEP

iv. Parbati-III HEP

Representative of POWERGRID informed that OPGW connectivity of above generating stations

was approved in 34th NRPC meeting held on 2nd May, 2017 and NIT work was in progress. It would

take around three years for completion.

2.1.4.2 Representative from NRLDC requested POWERGRID to prioritize OPGW for above generating

stations . POWERGRID agreed for the same and confirmed that above links would be done on

priority in the contract.

Regarding OPGW connectivity of Nathpa Jhakri representative of POWERGRID informed that

material had been despatched to site and OPGW connectivity would be completed by July 2017.

2.1.5 Optical fibre connectivity from SLDC, Dehradun to Rishikesh:

2.1.5.1 Representative of POWERGRID informed that issue of Optical fibre connectivity from SLDC

Dehradun to Rishikesh was discussed In 10th TeST meeting, wherein PTCUL was requested to

provide Six (06) fibers on their link from Dehradun to Rishikesh, so that it can be connected to

ULDC network at Rishikesh and SDH supplied by Tejas and EPABX can be commissioned. A

Page 7: ~~ ;.;=cThpaldc.org/NRPC_TeST/11/11_Minutes.pdf(ii) Regarding Noida (Sector 20) – Greater Noida 400 kV line under package -V, POWERGRID representative informed that due to non-availability

5

letter dated 13.04.2017 was issued to PTCUL by NRPC in this regard. Subsequently, the matter was

also discussed with SE, SLDC, PTCUL, who had agreed to share the communication link.

Representative of PTCUL was not present in this meeting. Representative of POWERGRID

proposed for a team visit to PTCUL, Dehradun to understand the constraints and resolve all

telemetry and communication related pending issues. After deliberation it was agreed that a team

consisting members from POWERGRID, NRLDC and NRPC secretariat would visit Dehradun to

resolve the issues.

2.1.6 Implementation of OPGW under Package-I (a)

2.1.6.1 HPSEB informed that Under package-I (a), OPGW of about 545.335 Km was to be laid on HPSEBL

transmission network and as per LOA work was to be completed by 31.03.2017. However, only 66

km. of OPGW against 545.335 Km. has been laid on HPSEBL transmission network. He further

stated that POWERGRID, NR-II, was requested to deploy more teams for expediting OPGW

stringing work. In response, NR-II vide e-mail dated 15.05.2017 has circulated the MOM held

between PGCIL & M/s Ten Dot Net cable Pvt. Ltd., according to which:

i. M/s Ten Dot assured that 01 gang will reach at site by 12.05.2017 for 132 kV Jutogh-Maliana

line and will be completed in the month of May, 2017.

ii. M/s Ten Dot assured to deploy 02 nos. more erection gangs for HPSEBL links by end of May,

2017.

2.1.6.2 HPSEBL representative stated that neither OPGW stringing work on 132 kV Jutogh-Maliana line

had started by the firm nor 02 nos. more erection gangs for HPSEBL links has been deployed by the

firm. He requested POWERGRID that firm may be directed to deploy more teams so that stringing

of OPGW could be finished by targeted schedule i.e. September, 2017.

2.1.6.3 POWERGRID representative informed that work would be completed by Dec,2017.

2.1.7 Installation of OLTE under Package - V & Package IV (a).

2.1.7.1 Representative of HPSEB informed that, Terminal equipment (SDH & PDH) was to be installed on

14 Nos. HPSEBL locations under package-V and DCPS & battery were to be installed on 08 nos.

locations.As per LoA work was to be completed by 31.03.2017. NR-II, PGCIL through e-mail

dated 26.12.2016 had intimated tentative schedule for completion of installation of OLTE & DCPS

as under:

i) SDH& PDH: FAT from 15.01.2017 to 19.01.2017. Material expected to reach site by

15.02.2017. Commissioning & SAT by 27.03.2017.

ii) DCPS & Battery: FAT from 20.02.2017 to 01.03.2017. Material expected to reach site by

12.03.2017. Commissioning & SAT by 31.03.2017.

HPSEBL representative requested POWERGRID to update the status.

POWERGRID NR-II representative informed that:

i) SDH & PDH: Factory acceptance test (FAT) in progress and supply would be completed

Page 8: ~~ ;.;=cThpaldc.org/NRPC_TeST/11/11_Minutes.pdf(ii) Regarding Noida (Sector 20) – Greater Noida 400 kV line under package -V, POWERGRID representative informed that due to non-availability

6

by, August 2017 and installation by September 2017.

ii) DCPS & Battery: work would be completed by December 2017.

2.1.7.2 HPSEBL representative stated that under Package IV (a), terminal equipment was to be

installed on 24 Nos. HPSEBL locations and DCPS & battery were to be installed on 18 Nos.

HPSEBL locations.

Representative of POWERGRID, NR-II, informed that work would be completed by

December 2017.

2.1.8 OPGW Requirement for UP:

2.1.8.2 POWERGRID representative informed following status for package –III a in UP:

i) AGRA-1------- AGRA_PG

ii) GRK-1------- GRK_PG iii) AZAM-1------GRK

2.1.8.3 Regarding OPGW for UPPTCL under Package-1a, awarded to M/s SDGI- offshore,

POWERGRID representative informed that supply for above lines has been completed.

Installation of OPGW on Agra-Agra link has also been completed, however installation of

OPGW on balance links will be completed by Dec’ 2017

2.1.8.4 Regarding OPGW for State Sector (Package-V) in UP awarded to M/s ZTT/ECI/Steel Product ,

POWERGRID representative informed following status:

i) Agra – Hathras –Harduaganj ----expected by July, 2017

ii) Muradnagar- Sahibabad- Noida Sector 62 - Noida Sector 20 - expected by July 2017

iii) Noida Sector 20 – Greater Noida 400 kV - expected by October, 2017

2.1.8.5 Further, POWERGRID requested UPPTCL to submit drawing of tower for Noida Sector 20 –

Greater Noida 400 kV section. UPPTCL confirmed they would submit the drawing within

week’s time.

(Action: UPPTCL; Time line: 25 July,2017)

2.1.9 Training program for STU personnel on OPGW related aspects:

2.1.9.1 SE, NRPC stated that in 8th TeST meeting POWERGRID agreed to arrange a training program

for STU personnel on OPGW related aspects so that they become familiar with O&M activities

of OPGW. It was also agreed that each STU would nominate 3 to 4 Engineers for the training.

The issue was further discussed in 35th TCC and 39th NRPC meeting held on 1st and 2nd May

2017, wherein, POWERGRID had agreed to organise the training on its own expenditure.

2.1.9.2 Representative of POWERGRID stated that it would be difficult to organise training during

rainy season, as field visit is also involved. He suggested that training would be organised in

last week of September, 2017.

2.1.9.3 The sub-committee advised POWERGRID to arrange training in last week of September,2017.

(Action: POWERGRID; Timeline: Sep,2017)

Page 9: ~~ ;.;=cThpaldc.org/NRPC_TeST/11/11_Minutes.pdf(ii) Regarding Noida (Sector 20) – Greater Noida 400 kV line under package -V, POWERGRID representative informed that due to non-availability

7

2.2 Communication issues

2.2.1 Communication plan for channel redundancy and to back-up NRLDC:

2.2.1.1 NRLDC representative informed that the provision of redundant communication was discussed in

8th and 10th TeST held on 26th July 2016, and 22nd March, 2017, respectively. However, redundant

data communication at NRLDC is yet to be completed. After testing, as on 31st May 2017, only 58

out of 116 NR stations were found with data redundancy.

2.2.1.2 Representative of NRLDC further stated that out of 115 RTUs 43 were working on redundant

channel , 48 alternate channel were not working and further 24 RTU were reporting on single

channel. It was also informed that co-operation of engineers from site is required for this activity

and in most of the days the availability of the site engineers were not ensured which had led to

unnecessary delay in testing the links. Representative of POWERGRID informed that they would

co-ordinate the activity along with the sites and complete the work by October 2017. He requested

all the utilities to provide alternate port.

2.2.1.3 The sub-Committee expressed concern about non-availability of redundant channel on different

path as any damage to fiber may affect both channel resulting communication failure. The sub-

Committee advised POWERGRID to take concrete steps to provide channel redundancy and submit

action plan by 31st July to complete the task.

( Action: POWERGRID; Time line: 31.07.2017)

2.2.2 Earthing issue at 220 kV Moga station

2.2.2.1 POWERGRID representative informed that Cards of Communication equipment got faulty/burnt at

220kV Moga station of PSTCL due to earthing issue in sub-station. Cards burnt at least six (06)

times in last one and half year, however no action was taken by PSTCL to replace or separate

earthing for communication equipment, even after repeated reminders to higher officials of PSTCL.

He further stated that POWERGRID would not deploy any vendor to this sub-station for

rectification /replacement of the cards without testing and installation of new earthing, as 5-6 cards

had already been replaced ,which have financial implications. He suggested that testing of earthing

may be done through third party (SAMEER - Govt. of India).

2.2.2.2 PSTCL informed that they were in process of awarding the work for replacement of earthing at

Moga Sub-station , which is expected to be completed by 31st July 2017. Members opined that

PSTCL should go for third party audit of the earthing also, as only the replacement of earthing may

not resolve the problem. PSTCL agreed for the same.

( Action : PSTCL; Time Line: 31.08.2017)

Page 10: ~~ ;.;=cThpaldc.org/NRPC_TeST/11/11_Minutes.pdf(ii) Regarding Noida (Sector 20) – Greater Noida 400 kV line under package -V, POWERGRID representative informed that due to non-availability

8

2.2.3 Implementation of Regulation on Communication :

2.2.3.1 Formation of guideline for calculation of “Availability of Communication System”

NRLDC representative informed that the regulation on communication was issued on 15th May,

2017 with an effective date of 1st July,2017. As per the regulation 7.3 (ii) “The RPC Secretariat

shall certify the availability of communication equipment for CTU, ISGS, RLDCs, NLDC, SLDCs

based on the data furnished by RLDC”

Further, as per regulation 7.3 .(i) “ NPC shall be responsible for issuance of the guidelines with the

approval of the Commission on “Availability of Communication System” in consultation with

RPCs, RLDCs, CTU, CEA and other stakeholders within a period of two months from the date of

notification of these regulations.”

RLDC needs to keep records of the communication outage based on requirements of the guidelines

to be decided by NPC and approved by Commission since 1st July, 2017.

Representative from NPC, CEA informed that a Committee was being formed to study the possible

criteria for availability calculation. It was informed that the draft guidelines would be ready in one

month time. It was deliberated that the planning criteria would also needs to be finalized, so as to

decide the availability criteria and hence needs to be done concurrently.

( Action: NPC Division, CEA ; Time Line: 31.08.2017)

2.2.3.2 Issuance of Technical Standards for the communication system

NRLDC representative informed that as per regulation 7.1 (ii) “CEA shall formulate and notify

technical standards, cyber security requirements in accordance with the Cyber security Policy of the

Govt of India from time to time, protocol for the communication system for Power Sector within

the country including the grid integration with the grid of the neighboring countries.”

Further, guideline for interfacing requirements needs to be formulated within 60 days from the

issuance of the technical standards to be issued by CEA.

Representative from CEA informed that they are in the process of drafting technical standards.

( Action: PCD Division, CEA )

2.2.3.2 Formulation of planning criteria for the communication system

As per regulation 7.1 (i) “CEA shall formulate communication planning criterion and guidelines for

development of reliable communication system for power system of India duly considering

requisite route redundancy ,capacity, as well as requirements of smart grid and cyber security.”

Representative from CEA informed that they are process of drafting planning criteria for the

communication system and will provide suitable input for availability calculation criteria.

( Action: PCD Division, CEA; Time line: 31.08.2017)

2.2.4 UPPTCL Communication issues :

Page 11: ~~ ;.;=cThpaldc.org/NRPC_TeST/11/11_Minutes.pdf(ii) Regarding Noida (Sector 20) – Greater Noida 400 kV line under package -V, POWERGRID representative informed that due to non-availability

9

2.2.4.1 UPPTCL representative informed that supply & installation of FOTE equipment was to be done in

April,17 and commissioning was to be done by June,2017 for all UPPTCL links. But till the date of

meeting even supply of FOTE equipments was not completed. Due to this lot of problems were

faced in real time data availability from Agra 765 kV, Agra 400 kV, Agra 220 kV, Greater Noida,

Hathras Shamsabad etc. He stated that this was causing problem in real time calculation of correct

drawl from central sector resulting in financial loss on account of DSM charges.

Representative of POWERGRID informed that work would be completed by 31st July 2017.

( Action: POWERGRID; Time line: 31.07.2017)

2.2.4.2 UPPTCL representative informed that channel Routing Plan as per currently implemented

scheme was required for analyzing causes of non-reporting stations and channel redundancy

planning for smooth data reporting.

Representative of POWERGRID agreed to share the same.

( Action: POWERGRID; Time line: 31.07.2017)

2.2.4.3 UPPTCL representative informed that as agreed in 10th TeST sub-committee meeting,

POWERGRID & NRLDC were to share weekly availability report generated through NMS for

various links provided on Tejas/ Fibre home networks but this was not started.

Representative of POWERGRID and NRLDC informed that there is no specific facility available in

the present NMS provided by the communication vendor as there was no such requirement in the

specification. NRLDC tried to generate such reports from the alarm signal generated. However, the

same could not be possible as the number of alarms were very high and also not very specific.

Member Secretary, NRPC requested NRLDC to provide the details for one day for further analysis,

which was agreed to.

After deliberation, it was decided that once the requirements for the availability criteria is finalized,

the same would be taken up with the vendor so that they can provided limited input as per

requirement for the availability calculation.

(Action: NRLDC, POWERGRID)

2.2.4.4 UPPTCL representative informed that share folder links between main NRLDC to Backup SLDC

was not working. Representative of NRLDC informed that he would look into the issue and

resolve at the earliest.

( Action: NRLDC; Time line: 31.07.2017)

2.2.5 RVPNL communication issues

RVPNL representative informed following issues for necessary action by POWERGRID:

a) Configuration of additional VF channels (approx 100 nos.) at various MUX locations of

Rajasthan for up-coming RTUs.

b) Rectification of faults & repairing of faulty modules of 48 V HBL make DCPS installed at

SLDC, Heerapura.

Page 12: ~~ ;.;=cThpaldc.org/NRPC_TeST/11/11_Minutes.pdf(ii) Regarding Noida (Sector 20) – Greater Noida 400 kV line under package -V, POWERGRID representative informed that due to non-availability

10

Representative of POWERGRID requested RRVPNL to procure cards for their new requirements

as there was no scope for integration using existing cards. Further, POWERGRID informed that

faulty DCPS cards would be replaced by July, 2017 end.

( Action: POWERGRID; Time line: 31.07.2017)

2.3 RTU issues

2.3.1 Replacement of old S900 RTUs:

2.3.1.1 SE, NRPC stated that the issue regarding replacement of existing S 900 RTUs installed under

ULDC Phase – I was discussed in the 8th , 9th (special) &10th Meetings of TeST Sub-Committee.

Accordingly a group was constituted for finalising RTU specifications and short listing of RTU

models. RTU specification was finalized by the group after incorporating comments and the same

had been made available on NRPC website.

2.3.1.2 He further informed that the issue was discussed in 35th TCC and 39th NRPC meeting held on 1st

and 2nd May 2017, wherein, it was decided that the group would not shortlist the models, instead it

would only prepare specifications keeping in view compatibility requirement of RTUs with

SCADA. It was also decided that necessary action may be taken by all the concerned utilities on

their own, without delay, to replace the S900 RTUs as per their technical specification and

requirement, while ensuring compatibility of the new RTUs with SIEMENS SCADA system. The

technical specifications of the RTU, finalised by the group, may be used as reference. Same was

conveyed by NRPC secretariat to all constituents, vide letter dated 26.05.2017.

2.3.1.3 The issues related to replacement of old S900 RTUs were deliberated. Many members including

that from Central Generating Stations and DTL requested POWERGRID to reconsider their request

to procure new RTUs on their behalf.

2.3.1.4 Representative of POWERGRID informed that POWERGRID was in the process of procuring new

RTUs for its own requirement and they may consider to include constituents’ requirement with the

approval by higher management, if the quantity of RTUs is substantial .

2.3.1.5 SE, NRPC requested members to tell their requirement. In the meeting the following requirement of

92 RTUs was informed by different constituents:

NHPC- 4, NTPC- 5. THDC-1, IPGCL- 1, SJVNL-1, BBMB-11 , DTL- 25, RVPNL-19*,

PSTCL-25* and HPSEBL – 9* (Total - 92 Nos.) (* Tentative, may confirm final quantities later)

2.3.1.6 The sub-committee advised all the members to convey their exact requirement to POWERGRID

within a week, failing which it would be construed that the utility does not want to get RTUs

procured through POWERGRID.

( Action: All the generation and transmission utilities ; Time line: 17.07.2017)

2.3.1.7 Representative of POWERGRID informed that he would put up proposal to POWERGRID higher

management and inform the status by 31st July, 2017.

( Action: POWERGRID; Time line: 31.07.2017)

Page 13: ~~ ;.;=cThpaldc.org/NRPC_TeST/11/11_Minutes.pdf(ii) Regarding Noida (Sector 20) – Greater Noida 400 kV line under package -V, POWERGRID representative informed that due to non-availability

11

2.3.2 ISSUE related to PDD, J&K:

2.3.2.1 GPRS connectivity for RTU installed under J&K PDD:

Representative of POWERGRID informed that, POWERGRID had placed an order for GPRS

based system for 20 nos. of RTUs at Jammu SLDC in May, 2015 on request of J&K PDD.

However, broadband connection with static IP at SLDC, Jammu and 20 nos. of data enabled SIM

cards for RTU sites was to be arranged by J&K PDD to enable data reporting of these RTUs at

Gladani SLDC as a standby channel. This work was still pending since more than 2 years. In view

of non-availability of SIM cards and Static IP, the system could not be commissioned. He informed

that POWERGRID was going to short close the contract.

The sub-Committee noted that representative of J&K did not attended the meeting.

2.3.2.2 Non-Availability of space for replacement of existing RTU in J&K region :

Representative of POWERGRID informed that replacement of existing 13 nos. of RTU installed

during ULDC Phase-I was in process. However, due to non-availability of space at these sub-

stations, vendor was not able to install these RTUs due to space. Materials were supplied more than

a year back and installation was still pending in Srinagar & Jammu Region. He stated that PDD,

J&K should ensure the availability of space for installation of new RTUs at these stations.

The sub-Committee noted that representative of J&K did not attended the meeting.

SE, NRPC informed that the RTU issues in J&K had already been brought to the knowledge of

J&K higher authorities for necessary action.

The sub-Committee advised NRPC secretariat to take up the issue with PDD, J&K and action plan

for arrangement of static IP and SIM Cards as well as for providing space for RTUs may be

intimated to POWERGRID by PDD, J&K.

( Action: NRPC Secretariat & PDD, J&K ; Time line: 31.07.2017)

2.3.3 RTU & AMC related issues of HPSEBL

2.3.3.1 Representative of HPSEBL stated that modalities may be finalized for interfacing of additional

bays, which are not included in the BOQ, with the SIEMENS RTU. He added that POWERGRID

had informed that rate contract for interfacing additional bays would be finalized by them in due

course of time but the same was still awaited.

2.3.3.2 He further stated that as per the Article 5 1.2 (iii) ( c) of Maintenance Contract, integration of new

equipment (RTU, Workstations, Printers, Switch, Router, ICCP connection etc.) with Main and

Backup Control Centre System is included in the maintenance contract, whereas same has been

shown excluded in the AMC Contract. The relevant extract is reproduced as under:

“Integration of new equipment (RTU, Workstations, Printers, Switch, Router, ICCP

connection etc.) with Main and Backup Control Centre System” is included in the

maintenance contract.”

2.3.3.3 In reply for all above issues POWERGRID representative confirmed that scope includes integration

of additional ICCP link and RTU/SAS on payment basis as indicated in the AMC contract. It was

also clarified that any additional item for which separate LOA is being placed, should include the

AMC price also, in case, it is desired so. It was also confirmed that price of RTU integration is

available in AMC contract.

Page 14: ~~ ;.;=cThpaldc.org/NRPC_TeST/11/11_Minutes.pdf(ii) Regarding Noida (Sector 20) – Greater Noida 400 kV line under package -V, POWERGRID representative informed that due to non-availability

12

2.3.4 Signing of side letter to MoU for AMC:

Representative of POWERGRID informed that Side letter for MoU for AMC contract (RTU

maintenance, etc) had been send to Constituents as per discussion in last meeting. However, MoU

was not signed by most of the constituents.

Representative of POWERGRID requested all members to send the signed copies at the earliest.

Members informed that they are in process of approval and would send signed copies by month

end.

( Action: All Concerned Utilities; Time line: 31.07.2017)

2.4. AMC Issues of SIEMENS RTUs installed under ULDC- 2 related to DTL :

2.4.1 DTL representative stated that additional bays are required to be integrated in the RTUs of M/s

Siemens at Mehrauli, Patparganj and Wazirabad Substations ( installed under ULDC#2), however

no rates are available in the existing contracts. It was also stated that no rates are available in the

existing Contracts for procurement of RTU database software for the Siemens make RTUs

installed at Mehrauli, Patparganj and Wazirabad Substations ( installed under ULDC- 2).

2.4.2 Representative of POWERGRID informed that the SCADA vendor was requested to furnish the

rate for additional bay integration as per the request received from the Constituents and the same

would be intimated as and when received from the vendor. On query by DTL regarding availability

of price of RTU database in the present contract, it was informed that the same was not included in

the contract as the installation was in the scope of the vendor. Hence, in case the same is required

by any Constituent, the tool needs to be procured separately. The price of the same would be

communicated to Constituents on receipt of the same from Vendor.

2.4.3 The sub-committee advised POWERGFRID to follow up with the Vendor and provide the rates at

the earliest.

( Action: POWERGRID; Time line: 31.08.2017)

2.5 Role of POWERGRID in Resolution of Contractual issues with M/s Siemens:

2.5.1 Representative of DTL informed that the responsibility for implementation of ULDC#2 project in

all SLDC’s lies with POWERGRID, in which various Contracts were signed between M/s

SIEMENS and PGCIL/POSOCO/SLDCs. However, all the contracts are interlinked, such that

breach of any contract makes the Contractor liable for damages under other Contracts also.

Recently, while calculating the percentage availability of system for making payment to Siemens,

difference in the understanding of method of calculations ( as detailed out in Volume II , Technical

Specifications) emerged between Siemens and DTL, for which POWERGRID’s representative was

requested to attend a meeting along with Siemens. POWERGRID intimated that POWERGRID

had no specific role in AMC contract, which is signed between M/s Siemens and Constituents.

Page 15: ~~ ;.;=cThpaldc.org/NRPC_TeST/11/11_Minutes.pdf(ii) Regarding Noida (Sector 20) – Greater Noida 400 kV line under package -V, POWERGRID representative informed that due to non-availability

13

2.5.2 He added that on the contrary, POWERGRID issued a letter to Siemens on 09.05.17 stating that

the Defect liability period had been completed on 31.03.17 and AMC for all SLDC’s system started

from 01.04.17.

2.5.3 He stated that all the Specifications/ T&C’s have been made by POWERGRID as such, it would not

be possible to enforce the T&C of Maintenance Contract (Third Contract) without the involvement

of POWERGRID.

2.5.4 Representative of POWERGRID informed that SCADA system is in operation from 1st Jan, 2016

after successful completion of SAT . There are no pending SAT variances at DTL and AMC

contract is between DTL and Siemens w.e.f. 01.04.2017 . He stated that day to day maintenance

issues should to be resolved by the Constituents themselves. However, POWERGRID would co-

ordinate for any clarification regarding AMC issues/scope and any pending issues of

implementation phase.

2.6 Disposal of old and obsolete SCADA equipment of ULDC Phase - I.

2.6.1 Representative of BBMB informed that in the 10th Meeting of TeST, it was informed by

POWERGRID that the recovery of charges against the ULDC-I package was expected to be

completed by July,17, after which constituents can dispose of the equipment. It was agreed that

POWERGRID would issue letters to constituents indicating the exact date after which the disposal

action could be initiated by the Constituents.

2.6.2 Representative of POWERGRID informed that the matter has been taken up internally with the

commercial department regarding processing of the residual value after depreciation and the

response is expected to be received within the target period and confirmed that they would issue

the letter by 31st July 2017.

( Action: POWERGRID; Time line: 31.07.2017)

3.1 Operational issues in EMS / SCADA system

3.1.1 Calculation of actual drawal in SCADA

3.1.1.1 Representative of NRLDC informed that the error checking for the tie lines were discussed during

the last TeST meetings. It was decided to compare the SEM and SCADA data for each points and

points for which % age errors are more than 3% will be reported for correction. It was observed that

except UP & HVPNL, no report was available for discrepancy and hence it was presumed that there

was no error found at least in the tie lines on which drawal calculations are being done.

3.0 Issues in Unified Load Dispatch & Communication

scheme of NR (Phase-II):

Page 16: ~~ ;.;=cThpaldc.org/NRPC_TeST/11/11_Minutes.pdf(ii) Regarding Noida (Sector 20) – Greater Noida 400 kV line under package -V, POWERGRID representative informed that due to non-availability

14

3.1.1.2 NRLDC representative informed that the mismatch of the reported UP lines were being looked into.

He informed that one of the point i.e Bagpat ICT has been resolved. The problem of ICT #3 of

Allahabad is being analysed further. Regarding issues in Mainpuri –Parichchha line at Mainpuri

end and in Kanpur-Orai line at Kanpur end it was informed by POWERGRID that it would be

resolved by July end.

(Action: POWERGRID; Time line: 31.07.2017)

3.1.1.3 Regarding issue at Abdullapur ICT3 POWERGRID representative informed that it would be

resolved by July end. Regarding the issue at Fatehabad, it was informed that POWERGRID would

take action .

(Action: POWERGRID; Time line: 31.07.2017)

3.1.1.4 Representatives of PSTCL and RVPNL informed that there no abnormal error was found in their

system.

3.1.1.5 The sub-committee advised all constituents to verify actual drawal w.r.t. SEM data and inform

discrepancy, if any.

3.1.2 Manual replacement of calcheck data at UP SLDC end

3.1.2.1 Representative of UPPTCL informed that as per earlier decision manual replacement of data in

SCADA was to be done by NRLDC, in case of failure of RTU/SAS/Communication system of

Central sector entities. But the same is not being ensured properly. He added that manual

replacement of calcheck data at SLDC end is also a challenge as many of the POWERGRID

stations are unmanned and therefore obtaining adequate value for replacement is arduous & time

consuming. To overcome such recurrent problems a mechanism needs to be developed for timely

acknowledgment, quick response & speedy resolution to these issues.

3.1.2.2 Representative of NRLDC informed that continuous manual replacement of data in real time is a

laborious process and unwarranted. Utilities should ensure 100 percent telemetry from all stations

to minimize the manual data replacement.

3.1.2.3 The sub-Committee advised all the concerned utilities to ensure reliable telemetry.

3.1.3 Monitoring of UFR, DF/DT and SPS feeder in SCADA:

3.1.3.1 Representative of NRLDC informed that Hon’ble Central Electricity Regulatory Commission

(CERC), order dated 23rd December 2013 in petition no 221/MP/2012 had ordered as follows:

“(c) UFRs and df/dt relays also be mapped on the SCADA system of each state so that they can be

monitored from SLDC/NRLDC.

(d) All STUs and SLDCs to map/network the UFR and df/dt on their SCADA system.”

3.1.3.2 Members of all SLDCs present in this meeting informed that Mapping of UFR and DF/DT on

SCADA was completed. But non availability of display is due to some telemetry issues.

Representatives of PTCUL and J&K not attended this meeting.

3.1.3.3 NRLDC informed that Uttarakhand, is yet to send the displays. NRLDC requested Uttarakhand to

submit the schedule for availability of displays .

Page 17: ~~ ;.;=cThpaldc.org/NRPC_TeST/11/11_Minutes.pdf(ii) Regarding Noida (Sector 20) – Greater Noida 400 kV line under package -V, POWERGRID representative informed that due to non-availability

15

3.1.3.4 TeST sub-committee advised members to furnish the details regarding availability of telemetry of

all the feeders on which the UFR and DF/DT relay had been provided, if not, the schedule for

implementation of telemetry for the same.

( Action : All

STUs/SLDCs; Time line : 31.07.2017)

3.2 Networking issues of SCADA in UP :

3.2.1 UPPTCL representative informed that the issue of connectivity of Sub- LDCs (Panki, Moradabad,

Modipuram) with SLDC Lucknow was discussed in 10th Test Sub committee meeting. In 83rd

MRM it was informed by POWERGRID that new Tejas equipments had been installed at all Sub-

LDCs except Sultanpur & Varanasi. POWERGRID suggested that all sub- LDCs to SLDC/Backup

SLDC Connectivity of Remote Consoles & Terminal Servers may be shifted to Tejas. As per

POWERGRID suggestion shifting of Sub-LDC Panki, Moradabad, Modipuram & SLDC Lucknow

data on Tejas was tried by team of, Siemens, Tejas & UPPTCL Engineer between 29-05-2017 to

01-06-2017.But performance of SCADA system on Tejas was worse than through Fibre

home/MRO Tech. Networking issues of SCADA during simultaneous reporting of RTUs to Main

& Backup SLDC was still unresolved.

3.2.2 POWERGRID representative informed that the matter had again been taken up

with the communication and SCADA vendor and issues were expected to be resolved the problem

by 15th July 2017.

(Action: POWERGRID; Time line: 15.07.2017)

3.3 Availability of data regarding new element Charging :

System for dissemination of information regarding commissioning details of charging of new

element, above 132 kV, on real time basis, to all STUs/SLDCs/RLDCs through SCADA system

needs to be established.

Member Secretary NRPC explained the importance of availability of information regarding

charging of any new station to all constituents in the region and requested members to take

necessary action for display of information on real time basis

3.4 SCADA Issues raised by State SLDCs

3.4.1 Pending SCADA Issues of BBMB

3.4.1.1 Implementation of Multisite Configuration:

BBMB representative stated that the implementation of Multisite Configuration between BBMB,

SLDC and PSTCL, SLDC was pending due to non-availability of communication links.

In this meeting Representative of POWERGRID requested BBMB to give the links requirements

and they would co-ordinate for implementation of Multisite as per approved design.

(Action : BBMB, POWERGRID; Time line 31.08.2017)

3.4.1.2 Database Synchronisation:

Page 18: ~~ ;.;=cThpaldc.org/NRPC_TeST/11/11_Minutes.pdf(ii) Regarding Noida (Sector 20) – Greater Noida 400 kV line under package -V, POWERGRID representative informed that due to non-availability

16

Representative of BBMB informed that in 8th Test meeting, the difficulties being faced during

database modification and synchronization process was deliberated and to overcome these problems

some proposals were suggested, but none of them have been implemented so far. Lot of problems

are being faced in maintaining the availability of real time data at BBMB, SLDC in the absence of

proper database synchronization procedure. He mentioned that the issue was discussed in detail in

the 10th meeting of TeST and after detailed deliberations it emerged that there were several similar

issue, which needs proper coordination with concerned vendors. It was decided that a meeting

would be arranged at NRPC, New Delhi with all the concerned vendors of ULDC scheme and the

concerned State utilities to discuss and resolve the issues.

Representative of NRLDC informed that database synchronization activity was being done on

monthly basis. This only includes synchronization of domain data. However, ICCP and TNA

database is to be maintained individually by each control centers. NRLDC would share the ICCP

database before database synchronization to facilitate ICCP configuration by Constituents.

Members agreed for the same.

3.4.1.3 Running of State Estimator:

BBMB representative informed that despite 100 % telemetry, BBMB was facing problems in

keeping the State Estimator running due to Database Synchronization issues. He mentioned that

BBMB has 100% telemetry of all its stations and all the circuit breakers and isolators are wired and

reporting. However, on account of power system changes in other constituents, the TNA model is

updated by respective constituent in their own database but the same is not propagated to other

constituents.

The matter was discussed in various meetings, but issue remained unresolved. After detailed

deliberations, it was decided that training of one week duration would be arranged at each

constituent location, so that utilities are able to resolve issues in running state estimator.

BBMB representative, further requested that the underlying problems relating to database up-dation

and maintenance of TNA Model may also be resolved in consultation with M/s SIEMENS during

training so that the State Estimator can function smoothly.

It was informed that in its last meeting, NRPC had approved the training on state estimator.

However, the training could not be arranged as some of the members were of the opinion that data

synchronization issues should be resolved before training. But, M/s SIEMENS had conveyed that

updation of entire data base & synchronization can not be taken up during training due to paucity

of time. This activity is to be done by the utility himself, M/s SIEMENS may only help utilities in

carrying out this activity. It was clarified that without telemetry and updated data, running of state

estimator can not be ensured even after training.

Representative of NRLDC informed that database synchronization activity is being done by them at

NRLDC on monthly basis. This only includes synchronization of domain data. However, ICCP and

TNA database is to be maintained individually by each control centers. The State Estimator model

needs to be tuned by the constituents based on the availability of the telemetered data. It was also

clarified that the addition of stations in the network, which was prepared at the time of SAT, needs

Page 19: ~~ ;.;=cThpaldc.org/NRPC_TeST/11/11_Minutes.pdf(ii) Regarding Noida (Sector 20) – Greater Noida 400 kV line under package -V, POWERGRID representative informed that due to non-availability

17

to be done by the constituents.

After detailed deliberation representatives of all the SLDCs present in the meeting had agreed that

training should be arranged at the earliest. All the SLDCs would endeavor to resolve the issues

related to data base updation.

( Action: NRPC Secretariat; Time line : 31.08.2017)

3.4.1.4 Adoption of IPv6 on SCADA IT Network:

BBMB representative informed that in the 36th USMG Meeting held on 18.02.2014, it was brought

out by BBMB that the ministry of Communication & Information Technology, Government of

India had circulated the IPv6 Deployment Roadmap to all the Central Government

Ministry/Department/State/UTs to facilitate them in the task. He added that all the Government

Organizations were advised to follow a phased transition approach depending on the complexity

and the IPv6 readiness of their current networks and systems. Accordingly, it was suggested that the

SCADA/EMS System, which was under procurement at that time, may be got configured on IPv6.

He suggested that since the commissioning of new SCADA/EMS System has been completed,

POWERGRID may implement the roadmap for transition of SCADA/EMS IT System from IPv4 to

IPv6, which is to be completed by Dec., 2017.

Representative of POWERGRID informed that equipment in ULDC- II is compatible to IPV6 but

since most of existing network is in IPv4, it was integrated with IPv4. He opined that since

downward compatibility is not available in IPV6 , migration to IPv6 may be difficult till all

connected network migrates from IPv4 to IPv6.

The sub-Committee advised POWERGRID to take up the matter with the vendor and apprise the

sub-committee about the outcome.

( Action: POWERGRID; Time line: 31.08.2017)

3.4.1.5 Preparation of Cyber Security Policy and Cyber Crisis Management Plan for SCADA/EMS

System

BBMB representative informed that various references were being received from CEA and NHPC

(Nodal agency appointed by Ministry of Power for ensuring compliance related to Cyber Security

in Power Sector) to prepare the Cyber Security Policy at the earliest. He suggested that Cyber

Security Policy and Cyber Crisis Management Plan in respect of the SCADA/EMS System installed

under ULDC Phase – 2 needs to be prepared and got implemented at the earliest.

Chief Engineer, IT,CEA informed that formation of separate CERT for system operation was under

process. He added that this CERT would co-ordinate for Cyber security requirement of power

system control centers. The system operation CERT, would examine the SCADA/EMS, IT as well

as telecom network from Cyber Security point of view. He suggested that all the concerned

agencies involved in system operation should prepare their own Cyber Security Policy and Cyber

Crisis Management Plan. It was also informed that a workshop would be organized by CEA for

Northern Region Constituents. It was also informed that a Task force was being formed which

would include designated CISOs of the Constituents to finalize standards and implementation of

Cyber Policy.

Page 20: ~~ ;.;=cThpaldc.org/NRPC_TeST/11/11_Minutes.pdf(ii) Regarding Noida (Sector 20) – Greater Noida 400 kV line under package -V, POWERGRID representative informed that due to non-availability

18

3.4.2 SCADA Issues of H.P.

3.4.2.1 HPSEBL informed that SOE’s of the following Sub-Stations were not being generated in

the SCADA:

i) 220kv Sub-station Jeori

ii) 132kv Sub-station Darlaghat

iii) Malana HEP

iv) 132kv Sub-station Palampur

v) Phozal HEP

Representative of POWERGRID informed that in co-ordination with SCADA vendor the issue

would be resolved by 31st July 2017.

( Action: POWERGRID; Time line : 31.07.2017)

3.4.3 Issues of PSTCL:

3.4.3.1 Representative of PSTCL informed regarding non-functioning of multisite functionality. He

informed that data was being transferred through ICCP and requested POWERGRID to take up the

matter with M/s SIEMENS for its early solution.

Representative of POWERGRID informed that visit by SIEMENS would be arranged to resolve the

issue and POWERGRID would co-ordinate for implementation of Multisite as per approved design.

(Action: POWERGRID; Time line : 31.08.2017)

3.4.3.2 Third party Security audit of SCADA/EMS:

PSTCL representative informed that Third Party Security audit of SCADA/EMS planned for the

month of May, 2017 was still pending. He requested POWERGRID to take up the matter with M/s

Siemens for conducting the same.

Representative of POWERGRID informed that third party audit was conducted in October, 2016

for the last year and for this year audit would be conducted in October, 2017.

PSTCL representative stated that schedule for EMS training at SLDC Patiala was still awaited.

The deliberation on this issue is covered under item no 3.4.1.3 &3.5

3.4.4 Pending SCADA issues of UPPTCL

3.4.4.1 UPPTCL informed the following major problems to be resolved by M/s SIEMENS:

i. Testing of Multisite functionalities including complete switchover of Main& Backup SLDC.

ii. Switchover to NMS 2 is not taking place since shifting of Main SLDC from Shakti Bhawan to New

SLDC building at Gomti nagar.

iii. Commissioning of PDS is due.

iv. Functioning of EMS is pending in OTS & its consoles.

v. Non-submission of analysis reports of various incidents.

vi. Frequent Core Dump on various servers at main & backup SLDCs.

Page 21: ~~ ;.;=cThpaldc.org/NRPC_TeST/11/11_Minutes.pdf(ii) Regarding Noida (Sector 20) – Greater Noida 400 kV line under package -V, POWERGRID representative informed that due to non-availability

19

vii. Action on various problems written in defect register from Nov’16 to April’ 17 are still pending.

Even timely acknowledgement of problems written in defect register is not done by Siemens site

engineers.

viii. Non-attending of various issues reported since November’16 to February’17.

ix. Automatic transfer of historical data from Main to Backup SLDC & vice versa is not taking place

after restoration of Multisite even if the failure is for short duration. Process of manual transfer

given by M/s Siemens is also not useful for transfer of large data.

x. Proper procedure has not been developed by M/s Siemens for registering / lodging complaints.

During meeting with Siemens on 23-05-2017, it was informed that it is in implementation stage at

NRLDC and will be ready for other constituents within 15-20 days but it is still pending.

xi. Site engineers of Siemens often do not get ample & timely support form Back office team.

Moreover, there are not sufficient manpower at back office to give timely support to site engineers

due to which problems remain pending for long time.

xii. Events/messages recorded at Main & Backup SLDC are not matching even when multisite

communication link is available.

xiii. SOE of same day taken on different dates shows number of discrepancies. SOE of Main SLDC for

30-04-2017 taken on 1st, 2nd and 3rd May’17 has been emailed to Siemens on 03-05-2017 but

response/action from Siemens is still pending.

xiv. Archive message of same day taken on different dates are also different. This issue has also been

raised during 83rd MRM but Siemens response is still awaited.

xv. When suspected data is replaced in SCADA, the status of same shows O.k in eDNA report instead

of replaced status. This issue was raised in 10th TeST meeting as well as in 83rd MRM but problem

is still unresolved.

xvi. Historical Data (Values as well as message) for data before 20-04-2017 is unavailable at backup

SLDC Modipuram.

xvii. Transfer of Historical data on Tape and its replay at Main/Backup SLDC is still pending/not

demonstrated by Siemens.

xviii. Following problems of backup SLDC reported to Siemens several times are still unattended.

xix. Non Working of DG set in Auto Mode

xx. Non Working of Insight Power Management software on UPS console.

xxi. Replacement of damaged doors of server racks and E-shape table.

xxii. Maintenance of defective Router at Sub-LDC Panki, Terminal Server at Lko.

xxiii. Following EMS Application are not running since beginning and no support has been provided by

Siemens in running these applications.

a) Security Analysis

b) Security Dispatch

c) Transmission Corridor Monitoring

d) Load Forecasting

Representative of POWERGRID informed that POWERGRID is continuously coordinating with

M/s SIEMENS to resolve all SAT related pending issues. He requested UPPTCL to directly take up

the AMC related issues with M/s SIEMENS. POWERGRID informed that representative of

SIEMENS was requested to attend all UP pending issues and submit their report by 31.07.2017.

UPPTCL representative discussed the issues with representative of M/s SIEMENS Subsequently,

UPPTCL informed the status, according to which most of the above issues have been attended by

Page 22: ~~ ;.;=cThpaldc.org/NRPC_TeST/11/11_Minutes.pdf(ii) Regarding Noida (Sector 20) – Greater Noida 400 kV line under package -V, POWERGRID representative informed that due to non-availability

20

SIEMENS and closed. For EMS applications issues (sr. no xxiii a, b ,c & d) Representative of

SIEMENS informed that same will be resolved during proposed EMS training at SLDC Lucknow.

3.4.5 Delay in Database Synchronization between Constituents:

Representative of UPPTCL informed following database synchronization issues:

a) Problems in Synchronization of Network map had been observed every time and Network map

display was not in synchronism with NRLDC.

b) Synchronization with NRLDC/Constituents was to be done regularly on monthly basis.

POWERGRID informed that representative of SIEMENS was requested to attend all UP pending

issues and submit their report by 31.07.2017.

3.4.6 Time mismatch observed in SOE

Representative of RVPNL informed about time mismatch, observed in SOE generated in the

SCADA system for incidence of complete outage of Kawai-Kalisindh-Chhabra complex in

Rajasthan on 20th May-2017 (20.06 Hrs.) for 765 KV GSS Phagi and 765 KV GSS Anta.

After deliberations on this issue, representatives of NRLDC suggested RRVPNL to check

time synchronization of the gateway and inform the status. RVPNL agreed to check time

synchronization of the gateway.

(Action: RVPNL; Time line : 15.07.2017)

3.4.7 Issues of HVPNL

3.4.7.1 Website: HVPNL representative informed that Haryana SLDC website name is

www.haryanasldc.org, but it opens up with the domain namewww.haryanasldc.org/Corporate UI

.He added that M/s. Siemens may be asked that ‘Corporate UI’ should not be required with the

domain name, so that website could be accessed with its domain name www.haryanasldc.org. He

mentioned that the issue was discussed in the MRM dated 23.05.17, wherein, NRLDC had assured

to coordinate & got resolved the issue, but the problem could not be resolved.

Representative of POWERGRID agreed to take up this issue with M/s. SIEMENS and get it

resolved by 31st July 2017.

(Action: POWERGRID/NRLDC; Time line: 31.07.2017)

3.4.7.2 Wrong status depiction in eDNA: HVPNL representative stated that when suspected data is

replaced in SCADA the status of the same is shown OK in eDNA report instead of the ‘Replaced’

status. M/s. Siemens is required to rectify the same. The issue was discussed in MRM dated

23.05.17, wherein it was informed that M/s Siemens would resolve the issue with in a week's time.

But, its resolution was still pending.

Representative of POWERGRID agreed to take up this issue with SIEMENS and get it resolved by

31st July 2017.

(Action: POWERGRID; Time line: 31.07.2017)

Page 23: ~~ ;.;=cThpaldc.org/NRPC_TeST/11/11_Minutes.pdf(ii) Regarding Noida (Sector 20) – Greater Noida 400 kV line under package -V, POWERGRID representative informed that due to non-availability

21

3.4.7.3 EMS Training: HVPNL representative requested to provide the schedule of EMS training.

Deliberation on this issue is covered under item No. 3.4.1.3 & 3.5

3.4.7.4 Database Synchronization: HVPNL representative stated that the incremental ICCP data base

should be provided along with domain data while database synchronization on monthly basis, so

that changes with respect to the other constituents could become available with every database

modifications.

This issue was covered under item 3.4.1.2.

3.4.7.5 Survey off of equipment installed under ULDC PH-I: HVPNL representative stated that

POWERGRID may update the status of petition filed in CERC regarding complete transfer of

assets to the constituent States after recovery of total cost and survey-off procedure for Equipment

installed under ULDC Phase-I.

Deliberations on this issue is covered under item 2.6.

3.4.7.6 EMS tuning: HVPNL representative informed that a Junior Engineer from SCADA-EMS Divn.,

HVPNL, Panipat was deputed to NRLDC for a week-time to have hands-on session regarding EMS

tuning activity. Thereafter, continued EMS tuning activity is being carried out at SLDC System.

But in the event of some problems being faced or having any misconceptions, there was no help /

support available from M/s. Siemens Engineers deployed at SLDC, Panipat as they were not

conversant with the EMS functionality of the system. He requested that an appropriate arrangement

in this regard be made or Engineers at SLDC be made conversant with EMS functionality so that

inclusive benefits of the system features could be harnessed.

Representative of POWERGRID agreed to take up this issue with M/s SIEMENS.

(Action : POWERGRID; Timeline : 31.07.2017)

3.5 EMS Training by SIEMENS at NR SLDCs:

SE, NRPC informed that M/s SIEMENS had submitted following prerequisite/conditions to start

training at SLDCs, which would include modules on EMS modelling in IMM, State Estimator,

Dispatcher Power Flow, Security Analysis and Network Parameter Adoption:

1. Complete Data base modeling should be available in TNA in parallel with SCADA.

2. State Estimator and Dispatcher Power Flow should be running.

3. No network tuning will be done during this training session.

4. Training will be Siemens system oriented i.e. theory behind the modules is planned in training

5. The above training will be conducted in 5 days. If additional days are required for any activities

related to training, same will be charged extra.

6. Training will be provided at each constituent’s location and training time will be from 9:00Hrs to

17:00Hrs.

Page 24: ~~ ;.;=cThpaldc.org/NRPC_TeST/11/11_Minutes.pdf(ii) Regarding Noida (Sector 20) – Greater Noida 400 kV line under package -V, POWERGRID representative informed that due to non-availability

22

SE, NRPC requested all SLDCs to express their views regarding the acceptance of

prerequisite/conditions, to start the training at the earliest. Some of the members expressed concern

about the prerequisite. However, after detailed deliberations representatives of all SLDCs present in

the meeting agreed for the prerequisite and expressed their consent to start the training at the

earliest.

(Action: NRPC Secretariat; Time line: 31.08.2017)

4.1 Present Status of Telemetry :

4.1.1 Non-Availability / Reliability of Telemetry

4.1.1.1 Representative of NRLDC informed that, even though the telemetry integration is ensured before

charging the new element, the reliability of telemetry is not at all ensured at the new stations at 400

kV integrated in the system. The reliability of telemetry of the following stations is very poor ,

which includes some stations ,where telemetry is not reliable since its integration:

400 kV Hapur 400 kV Chitorgarh 400 kV Chabra 400 kV

Banauli

400 kV Muradnagar(N) 400 kV Talwandi Saboo 400 kV Bawana CCGT 400 kV

Srinagar

400 kV Nahtore 400 kV Muktshar 400 kV Kashipur 400 kV

Uri

400 kV Mathura 400 kV Nakodar 400 kV Rishikesh 400 kV

Fatehabad

400 kV Karcham Wangto 400 kV Parbati – II 400 kV Parbati - III

4.1.1.2 NRLDC representative shared the availability of the telemetry for the central sector station and

informed that the telemetry of above stations is highly intermittent causing problem in day to day

grid operation. He requested all the members to look into the matter and resolve the issues at the

earliest.

4.1.1.3 Member secretary, NRPC requested concerned Utilities to take immediate necessary action to

provide reliable telemetry from all stations.

4.1.1.4 The sub-Committee expressed concern about unreliable telemetry, which is detrimental to safe and

economic operation of the grid. It was also emphasized that non-availability of telemetry is non-

compliance of regulatory provisions. The sub-committee advised all the concerned utilities to take

immediate steps for ensuring reliable telemetry at their respective sub-station/generating stations.

Concerned utilities for providing reliable telemetry at the above mentioned stations were advised to

submit action taken report by 31st July,2017 NRPC Secretariat & NRLDC.

(Action: All the concerned transmission/generation utilities; Time line: 31.07.2017)

4.1.2 The problem in the RTU / SAS gateway :

4.1.2.1 Representative of NRLDC informed that redundant ports were not available in the following

stations even though the communication had been provided , resulting in non-availability of real

time data in case of one channel failure:

4. Telemetry Related Issues

Page 25: ~~ ;.;=cThpaldc.org/NRPC_TeST/11/11_Minutes.pdf(ii) Regarding Noida (Sector 20) – Greater Noida 400 kV line under package -V, POWERGRID representative informed that due to non-availability

23

Station Status

Kanpur 765 Port faulty

Bhiwadi(PG) Port faulty

Saharanpur Port faulty

Manasar Port faulty

Koldam Port not available

Rampur Port not available

RAPP-A Port not available

Kurushetra Automatic failover not

Available

RAPP-C Port not available

4.1.2.2 Member secretary NRPC requested concerned Utilities to take immediate necessary action for

restoration / provision of the port for reliable communication and submit action taken report to

NRPC Secretariat & NRLDC. Concerned utilities assured that they would look into the issue and

resolve at the earliest.

(Action: PGCIL,NTPC,NPCIL,NHPC; Timeline 31.07.2017)

4.1.3 Telemetry of digital status :

4.1.3.1 Representative of NRLDC informed that there is no improvement of digital telemetry status even

after regular follow up by NRLDC in previous TeST meetings. He made a presentation in this

regard. He mentioned that in 10th TeST Sub-committee meeting it was decided that the constituent

would furnish the availability status of 220 kV and above stations and improvement there of. But

the same was not furnished.

4.1.3.2 The sub-committee advised all the members to furnish the latest status of digital data telemetry of

all the 220 kV and above stations in NR and requested members to submit action plan, for 100%

availability of telemetry in Northern Region, to NRPC Secretariat and NRLDC.

( Action: All the generation and transmission utilities; Time line: 31.08.2017)

4.1.4 ICCP communication between PTCUL and NRLDC

4.1.4.1 Representative of NRLDC informed that ICCP communication link between PTCUL and NRLDC

is highly non-reliable and there is outage of days together. Till time Fibre optic connectivity is

established alternate channel may be arranged by PTCUL at the earliest.

4.1.4.2 Representative of PTCUL was not present in this meeting. Representative of POWERGRID

proposed that a team comprising members from NRPC Secretariat, NRLDC and POWERGRID

may visit to PTCUL, Dehradun to understand the constraints and resolve all telemetry and

communication related pending issues. SE, NRPC agreed to take up the matter with PTCUL.

( Action: NRPC Secretariat; Time line: 31.07.2017)

4.2 Telemetry issues of UPPTCL :

4.2.1 UPPTCL representative informed that there had been co-ordination issues with POWERGRID in

reference to calcheck data accessed from POWERGRID sub-stations. The errors/inaccuracies

Page 26: ~~ ;.;=cThpaldc.org/NRPC_TeST/11/11_Minutes.pdf(ii) Regarding Noida (Sector 20) – Greater Noida 400 kV line under package -V, POWERGRID representative informed that due to non-availability

24

observed in telemetry data obtained from sub-stations of POWERGRID persisted for long, although

regular requests were made to address the same.

He added that the inaccuracy/ mismatch (in SCADA Vs SEM) for the following calcheck points of

UP State was reported in past months but problems at POWERGRID ends were not resolved.

i) 400 /220 kV Allahabad PG ICT -III

ii) 400 /220 kV Bhagpat PG ICT –I

iii) 400 kV Mainpuri PG- Parichha

iv) 400 kV Kanpur PG -Orai

4.2.2 He proposed that a nodal officer from POWERGRID may be nominated for better co-ordination.

POWERGRID agreed to arrange local coordinator to resolve the problems.

(Action: POWERGRID; Time line: 31.07.2017)

4.2.3 Regarding non-availability/inaccuracy in real time SCADA data with SEM at 400 kV Madhura

sub-station UPPTCL requested NRLDC to resolve the problem.

NRLDC assured to look into the issues related to SCADA data mismatch with SEM and restore

accuracy of telemetry data.

(Action: NRLDC; Time line: 31.07.2017)

5.1 URTDSM Project Status:

5.1.1 Representative of POWERGRID informed that materials for PDC for 8 out of 9 nos. of SLDC

control centres had been received at site. He added that FAT for balance control centres i.e. NLDC,

NRLDC and J&K PDD was under progress and by July end materials would be delivered at site.

5.1.2 POWERGRID representative requested all the Constituents to ensure space for installation of

Servers in SLDC control rooms and to ensure availability of manpower to implement the Project

before target date, Dec, 2017.

5.1.3 Members present in this meeting agreed for the same.

5.2 Constraints in URTDSM project:

5.2.1 Representative of POWERGRID informed that there was issues in allowing shutdown required for

CT/PT termination at various station under URTDSM Project.

He added that POWERGRID was installing PMUs at various sub-stations of central and state

sector. For commissioning of PMUs at site, CT/PT and DI termination was required for existing CR

panels. CT/PT termination for most of the stations had been done in live line condition. However,

some of the stations specially generating units of NTPC and UPRVUNL were insisting for

shutdown for CT/PT termination.

5. Unified Real Time Dynamic State Measurement (URTDSM) Scheme.

Page 27: ~~ ;.;=cThpaldc.org/NRPC_TeST/11/11_Minutes.pdf(ii) Regarding Noida (Sector 20) – Greater Noida 400 kV line under package -V, POWERGRID representative informed that due to non-availability

25

After discussion with NRLDC for shutdown, vendor had been deployed 4 times at Obra-BTPS and

3 times at Singrauli station, however at last moment shutdown could not be allowed citing grid

related issues. Consequently, Vendor was very reluctant to visit again at site citing shutdown issues

and commissioning also hampered due to this. He informed that in each sub-station 30-30 min.

shutdown is needed for each of the feeder for CT/PT connections.

POWERGRID requested NTPC and UPPTCL to co-ordinate for the outages. Both constituents

agreed for the same.

( Action: NTPC,UPPTCL; Time line: 31.07.2017)

5.2.2 Space for installation of PDS / PDC at SLDC Dehradun at PTCUL:

Representative of POWERGRID informed that PTCUL did not provide space for installation of

PDS / PDC at SLDC Dehradun. PDS Materials were dispatched to Dehradun in Feb,16. However,

PTCUL officials did not take delivery of PDS materials even the matter was discussed during 7th

TeST meeting, now PDS is temporarily stored at Dehradun sub-station of POWERGRID and FAT

for PDC is going on and PDC would be dispatched in July, 2017. He added that PTCUL may

ensure space for PDC at site.

It was noted that PTCUL representative was not present in the meeting.The sub-committee advised

NRPC Secretariat to take up the matter with PTCUL.

( Action: NRPC Secretariat; Time line: 31.07.2017)

The sub-Committee advised all the concerned utilities for co-operation in implementation of

URTDSM project in time.

5.3 Latest update on URTDSM:

5.3.1 Representative of PSTCL informed that, URTDSM project for supply/installation/commissioning of

3 no. PMUs was scheduled to be completed by Mar/April 2017,as per original schedule conveyed

by POWERGRID and accordingly the same was conveyed to Punjab State Electricity Regulatory

Commission (PSERC). But works were not completed at SLDC control centre, Ablowal. He added

that as per latest updates received from POWERGRID, FAT for PDC was scheduled on 10.04.2017

but, as mentioned above, control centre activities were still pending. He requested POWERGRID to

provide latest status of this project, so that PSERC may be intimated about the same.

5.3.2 POWERGRID representative informed that URTDSM control centre hardware had been received at

site and installation work would commence shortly. Commissioning is planned by Sept, 2017.

5.4 URTDSM Communication issues:

5.4.1 UPPTCL requested POWERGRID to provide details of communication routes & availability status

and connectivity to servers at SLDC Lko., so that monitoring of communication routes may be done

and bottleneck, if any, may be removed before commissioning of URTDSM project as PMUs at

some location in UP had been installed.

5.4.2 Representative of POWERGRID informed that they would provide the communication route and

port details as required by UPPTCL by 15th July’ 2017.

Page 28: ~~ ;.;=cThpaldc.org/NRPC_TeST/11/11_Minutes.pdf(ii) Regarding Noida (Sector 20) – Greater Noida 400 kV line under package -V, POWERGRID representative informed that due to non-availability

26

( Action: POWERGRID; Time line: 31.07.2017)

5.5 BBMB URTDSM ISSUES:

5.5.1 BBMB representative informed that in the 10th meeting of TeST, POWERGRID representative

informed that FAT of PDC was scheduled in April, 17 and the delivery was expected to be done in

May, 2017. However, no equipment was received at BBMB SLDC, so far. It was also brought out

that the URTDSM equipment cannot be installed at BBMB SLDC, until the commissioning of new

UPS to be supplied at BBMB SLDC is completed.

5.5.2 BBMB requested POWERGRID to provide activity wise PERT chart of all the activities to be

carried out at BBMB SLDC under URTDSM Project so that the activities can be planned properly.

5.5.3 POWERGRID representative informed that L2 schedule provided earlier to all constituents was not

revised till that date. He added that Progress had been updated in each TeST meeting. He informed

that all PMUs under BBMB had been commissioned and PDC had been delivered . UPS would be

supplied by Sep,17 as per the commissioning target, which is Sept, 2017 . He further informed that

for the completion with SAVT target is Dec, 2017.

Additional Agenda:

A1. Status of action taken

A1.1 SE, NRPC stated that all the members were requested to submit status on the action points identified

in 10th TeST sub-Committee meeting. But only POWERGRID had intimated the status. He

requested that status may be submitted by 31.07.2017.The list of action points along with the time

line and name of concerned utility is enclosed at Annexure-II.

A2. Presentation by Vendors on Latest Developments in SCADA and Communication equipment

A 2.1 Presentation was made by ABB, GE, Motorola (MB control) and Synergy Systems and members

were apprised about the latest developments in SCADA and Communication equipment.

T1: Table Agenda by PSTCL:

1. PSTCL representative informed that Nokia Mux was phasing out. He requested for suitable

replacement to ensure healthy Communication System especially at 220kV Barnala and 220kV

Malerkotla, as no SDH is installed there, besides 220kV Lalton Kalan, 220kV Gobindgarh-1,

220kV Jamsher.

POWERGRID representative informed that replacement was not possible. He suggested that

PSTCL should take action for replacement.

2. PSTCL representative informed that 4 Nos. Battery Chargers and associated Dry Battery were

required at sites- Malerkotla, Barnala, Gobindgarh-1 and Jagraon as these stations have Lead Acid

Batteries which were installed by PGCIL during the up gradation/replacement of Microwave

Page 29: ~~ ;.;=cThpaldc.org/NRPC_TeST/11/11_Minutes.pdf(ii) Regarding Noida (Sector 20) – Greater Noida 400 kV line under package -V, POWERGRID representative informed that due to non-availability

27

Towers with OPGW system and the same were being used for OPGW till date. Now these need

replacement with Dry type VRLA Batteries as these equipments have outlived their useful lives.

POWERGRID representative informed that replacement of batteries is the responsibility of PSTCL

and requested PSTCL to take necessary action .

3. PSTCL representative informed that data transmission from 400kV Nakodar was very critical as it

is inter-state LILO point, 400kV data from Talwandi Sabo being a generator is also a crucial one

along with 400kV Muktsar data, too. Hence provision may be made so that data for afore-

mentioned 3 Nos. sub-stations may directly respond to SLDC Ablowal via 400kV Moga sub-station

instead of present data route which is being followed via 220 kV Moga.

POWERGRID representative agreed on the same and informed that they will explore the options to

consider PSTCL proposal for necessary action.

4. PSTCL informed that in order to minimise frequent tripping/burning of PDH cards at 220KV S/Stn.

Moga, separate earthing of carrier room of said S/Station. was being carried out. Planning & Design

was complete. Tenders would be opened on 10.07.2017 and work order would be issued. Separate

earthing of carrier room is likely to be completed before 31.07.2017.

This issue was covered under item 2.2.2.

5. PSTCL representative informed that names of 5 officers were conveyed to NRPC. He requested

that training may be imparted to them.

This issue was covered under item 3.5.

Page 30: ~~ ;.;=cThpaldc.org/NRPC_TeST/11/11_Minutes.pdf(ii) Regarding Noida (Sector 20) – Greater Noida 400 kV line under package -V, POWERGRID representative informed that due to non-availability

28

Annex-I

List of participants in the 11th meeting of Telecommunication, SCADA and Telemetry sub-

Committee held on 10.07.2017 in New Delhi

Organization Shri/sh DISIGNATION Email ID

NRPC Sh. MAKP Singh

Sh. Upendra Kumar

Sh. Hemant Kumar

Pandey

Sh.. K.N.M Rao

Sh. Bhanwar Kumar

Meena

Sh.Vikrant Dhillon

Member Secretary

SE(O)

SE(C )

Asst. GM

EE

AEE

[email protected]

[email protected]

[email protected]

[email protected]

[email protected]

[email protected]

CEA Sh.Vijay Meghani

Sh. Naresh Kumar

Sh.M Ramakrishna

Sh.D Rastogi

Chief Engineer

Exe. Engineer,PCD

Dy. Director, NPC

Asst. Director NPC

[email protected]

[email protected]

[email protected]

POWER

GRID

Sh. Y.K. Dixit

Sh. NK Meena

Sh. Y.S.SAI Prasad

Sh.S C Sharma

AGM(ULDC)

Sr.Engineer NR-I

DGM,NR-II,Jammu

Ch. Manager NR-I

[email protected]

[email protected]

[email protected]

[email protected]

POSOCO Sh. Debasis De

Sh.Ankur Gulati

DGM

Dy.Manager

[email protected]

[email protected]

PSTCL Sh.A.P.Singh

Sh.Ankit Bedi

Manpreet Kong

SE/SLDC

AE

AEE

[email protected]

[email protected]

[email protected]

UPPTCL Sh. P K Tiwari

Md. Irfan. Alam

Sh. AK Verma

Sh.M.N Shukla

Chief Engineer

SE(SCADA&IT)

AE(SCADA&IT)

EE

[email protected]

[email protected]

[email protected]

[email protected]

DTL Sh. Pradeep Katiyar

Parvez Khan

Anjalee Das

Sh. Daljit Singh

Sh. Mukesh Kumar

Parul Kapadia

DGM(SLDC)

Manager(T)

Manager(SCADA)

Asst. Manager(T)

AM

Manager

[email protected]

[email protected]

[email protected]

[email protected]

[email protected]

[email protected]

HVPNL Sh. Munish Satija

Sh. Rahul Singhal

EE

AEE

[email protected]

[email protected]

RVPNL Arvind Agarwal

Ajeet Singh

Bansiwal

SE(comml.)

Xen

[email protected]

[email protected]

Page 31: ~~ ;.;=cThpaldc.org/NRPC_TeST/11/11_Minutes.pdf(ii) Regarding Noida (Sector 20) – Greater Noida 400 kV line under package -V, POWERGRID representative informed that due to non-availability

29

BBMB Sh. Anil Goutam

Sh. Naveen Gupta

Sh. S Dilbagi

Director

Dy. Director/SLDC

Dy. Director

[email protected]

[email protected]

[email protected]

HPSEBL Deepak Uppal Dy. CE(ALDC) [email protected]

PTCUL Not attended --- ---

NTPC B. L.Yadav AGM

[email protected]

NHPC Sh. Rahul Ranjan

Vijay Kumar

DM(E&C)

Engineer(E&C)

[email protected]

[email protected]

THDCIL Visalakshi Malan Sr. Engineer [email protected]

SJVN Sh.Rajeev Agarwal

Sh.Sunil Parashar

Manager

Sr.Engineer

[email protected]

[email protected]

Page 32: ~~ ;.;=cThpaldc.org/NRPC_TeST/11/11_Minutes.pdf(ii) Regarding Noida (Sector 20) – Greater Noida 400 kV line under package -V, POWERGRID representative informed that due to non-availability

30

Annexure-II

1A. Action plan status, timeline and compliance of issues reported in MOM 10th TeST

meeting

Responsibility for Action plan and Time line for following issues were mentioned in Minutes of

10th TeST meeting issued on 13.04. 20017. Compliance submitted by POWERGRID are

incorporated. Other Members may inform the status of compliance.

Sl No Issue Action by Time line

Compliance status as

on 10.07.2017, as

informed by the

constituents

2.1.1B OPGW installation state

sector

POWERGRID May 2017 for

Punjab

Sept 2017 for

other states

Work in progress

2.1.2 All the states agreed to

keep the OPGW spares

with POWERGRID.

Representative of

Haryana expressed that

they would like to keep

spares with them and

agreed to convey their

decision

HVPNL 31.03.2017 HVPNL agreed to

follow all other states

to keep the OPGW

spares with

POWERGRID.

2.1.4 Revised OPGW

requirement

POWERGRID Sept 2017 Revised Qty has

already been taken care

in Amendment

2.1.5 FO Connectivity between

Sangrur & Barnala sites

with BBMB SLDC

Chandigarh

POWERGRID May 2017 Material for Malerkotla

has been supplied and

link will be

commissioned shortly.

2.1.6 AMC of the 208.438 km

of OPGW laid on BBMB

Transmission lines

POWERGRID AMC award Lines has been covered

under AMC contract

2.1.7 Training program for

STU personnel on OPGW

related aspects:

POWERGRID June 2017 NRPC secretariat is

coordinating for

training

2.2.1a Communication plan for

channel redundancy and

to back-up NRLDC

All constituents Immediate Testing have been done

for all RTU/SAS

channels under central

sector. Site visit have

been done for 45 sites,

out of this data on dual

channel reporting for

Page 33: ~~ ;.;=cThpaldc.org/NRPC_TeST/11/11_Minutes.pdf(ii) Regarding Noida (Sector 20) – Greater Noida 400 kV line under package -V, POWERGRID representative informed that due to non-availability

31

34 stations. For balance

sites, site visit is

planned with routine

maintenance of

communication

equipment.

2.2.1 b POWERGRID to provide

OPGW connectivity to

generating stn: i.

Karcham HEP ii. Jhajjhar

TPS iii. Sorang HEP iv.

Parbati-III HEP

POWERGRID After NRPC

approval

Approved in 39th

NRPC meeting dated

2nd May 2016

2.2.1 c In the existing OPGW

network connecting

Rampur and Naptha-

Jhakri HEPs , some fibres

can be used for tandem

operation and two fibres

can be utilized for RTU

and Voice data.

Representative of SJVNL

stated that he would

discuss revert back to

NRPC Sectt. and NRLDC

SJVNL 31.03.2017 Data for Rampur has

been configured on

wideband node.

2.2.2 Optical fibre connectivity

from SLDC Dehradun to

Rishikesh:

NRPC

POWERGRID

20.04.2017 On Telephonic

conversion, PTCUL

agreed to give 6 fibre to

ULDC for connectivity

however till now,

OPGW connectivity is

yet to be established.

2.2.3 Remote control of SLDC

at Maharani bagh:

POWERGRID 25.03.2017 Link has been

configured on

24.03.2017

2.2.4 a Communication issues in

UP

POWERGRID 31.03.2017 Joint testing have been

done at Lucknow on

29th May to 1st June’17

however further

investigation is

required for latency

issue.

2.2.4 b POWERGRID agreed to

provide weekly

availability repo,

generated through NMS,

POWERGRID

and NRLDC

Every week

starting from first

week of

April,2017

POWERGRID agreed

to explore the

possibility of report

generation and work

Page 34: ~~ ;.;=cThpaldc.org/NRPC_TeST/11/11_Minutes.pdf(ii) Regarding Noida (Sector 20) – Greater Noida 400 kV line under package -V, POWERGRID representative informed that due to non-availability

32

for various links provided

on Tejas network, to

NRLDC and NRLDC

would share the report

with all the concerned

still going on; within

next 10 days this will

be started.

2.2.4 c supply & installation of

FOTE equipment and

commissioning for all

UPPTCL links

POWERGRID June 2017 Equipment has been

supplied and

installation will

commence from 9th

June’ 2017

2.2.4 d Latency issues in

Telecom network from

UPPTCL Main SLDC to

Main NRLDC

POWERGRID 15.04.2017 Bandwidth has been

increased for Telecom

network from 2 mbps

to 10 mbps as per

discussion

2.2.7 Ethernet Connectivity

between Bhiwani site

with BBMB SLDC

Chandigarh

POWERGRID 15.04.2017 Ethernet connectivity

already been provided

at Bhiwani station in

microwave replacement

scheme through

Fibrehome

communication

equipment.

2.2.8 Supply of Valiant make

PDH at Charkhi Dadri,

Panipat, Dhulkote,

Barnala & Chandigarh

POWERGRID May 2017 POWERGRID has

informed that

Fibrehome PDH is

already available and

AMC vendor will

check the issue of non-

functioning, as per our

records, PDH at these

locations are working

fine and it may also be

noted that fibrehome is

installed in 2013-14

2.2.9 Disposal of old and

obsolete SCADA

equipment of ULDC

Phase - I.

POWERGRID June 2017 Life of ULDC Phase-I

equipment will be

completed in July’

2017 then these

equipment will be

property of constituents

and they can disposed

off at their own.

Page 35: ~~ ;.;=cThpaldc.org/NRPC_TeST/11/11_Minutes.pdf(ii) Regarding Noida (Sector 20) – Greater Noida 400 kV line under package -V, POWERGRID representative informed that due to non-availability

33

2.3.1 Action for Replacement

of old S900 RTUs by July

2018

NRPC

Secretariat

31.03.2017

Issue was discussed in

39th NRPC meeting

held on 2nd May 2017

and a letter dated

26.5.2017 was issued

by NRPC requesting

members to take

necessary action to

replace S 900 RTUs .

This issue was raised

again in 11th TeST

meeting agenda 2.3.1

2.3.2 AMC of old RTUs

MOU needs to be signed

with validity till

July,2018.

All STUs April 2017 POWERGRID agreed

to extend AMC validity

to July 2018 and all

utilities agreed to

submit necessary

documentation by July

2017

2.3.2

New AMC contracts for

APS, OPGW and

Wideband, etc. may also

be extended as per side

letters of MOU. side

letters may be signed

before expire of AMC

contract.

All Central and

State Utilities

July 2018 -Do-

3.1.1 Proper database

modelling

All STUs Immediate After clarification from

SIEMENs and NRLDC

STUs agreed for n/a

3.1.2 Monitoring of UFR,

DF/DT and SPS feeder in

SCADA

All STUs 30.04.2017 STUs agreed for

necessary action

3.1.3 Running of State

Estimator

All STUs 31.03.2017 STUs requested for

Training

3.1.3 Submission of cost

estimate for Training on

EMS State estimator

POWERGRID 31.03.2017 Cost estimate submitted

by POWERGRID was

approved in 39th NRPC

meeting dt 2.5.2017

3.3.2 to

3.3.6

SCADA Issues of

Delhi,H.P, PSTCL,

HVPNL,UP.

POWERGRID 15.04.2017 POWERGRID agreed

to arrange Vendor

meeting with

SIEMENS and others

to resolve SCADA

Page 36: ~~ ;.;=cThpaldc.org/NRPC_TeST/11/11_Minutes.pdf(ii) Regarding Noida (Sector 20) – Greater Noida 400 kV line under package -V, POWERGRID representative informed that due to non-availability

34

issues.

3.3.7 Networking issues of

SCADA in UP

POWERGRID

& NLDC

15.04.2017 UPPTCL resubmitted

Agenda 3.2 in 11th

TeST meeting

4.1 Non-Availability /

Reliability of Telemetry

all the utilities would

prepare the channel

details for each station

integrated with SCADA

and the type of links

provided so that the same

could be discussed in the

next meeting

All generation

and

transmission

Utilities

30.04.2017 NRLDC resubmitted

Agenda 4.1.1 in 11th

TeST meeting

4.1 POWERGRID to provide

the following status from

SVCs to facilitate better

monitoring and analysis :

i. Mode of operation of

SVC at Ludhiana ii.

Slope, Q set for voltage

control mode of SVC at

Ludhiana iii. Vmax,

Vmin, slope, Qset for Q

control mode for SVCs

for Kankroli & Ludhiana

Apart from above, a

counter/signal during

operation of PoD or

stability module would

also be explored.

POWERGRID 30.04.2017 complied

4.2 Improvement in

Telemetry of digital

status

All STUs 31.05.2017 NRLDC resubmitted

Agenda 4.1.1 in 11th

TeST meeting

4.6 Substitution of Suspected

as per field value

NRLDC,

SLDCs

Immediate UPPTCL resubmitted

Agenda 4.1.3 in 11th

TeST meeting

5.1 Status of the installation

of URTDSM system.

POWERGRID 15.04.2017 Work is in progress as

informed by

Page 37: ~~ ;.;=cThpaldc.org/NRPC_TeST/11/11_Minutes.pdf(ii) Regarding Noida (Sector 20) – Greater Noida 400 kV line under package -V, POWERGRID representative informed that due to non-availability

35

POWERGRID. agreed to

take up with the vendor

for implementation of the

visualization at NRLDC

along with necessary

archival of the data.

POWERGRID

5.4 POWERGRID confirmed

that site visit at DTL

would be done within one

week time by M/s

ALSTOM for finalising

the location for PDC

servers.

POWERGRID 15.04.2017 Complied

5.5 POWERGRID agreed to

share the activity wise

PERT chart for the

project with BBMB

POWERGRID 31.03.2017 Issue resubmitted by

BBMB in 11th TeST

meeting as Agenda 5.5