SLOC1 CAVITE - BATANGAS
Monthly Project Update
As of September 24, 2014
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
2/71
Project Update
BELLAVITA FIESTA MARKET
September 24, 2014
3/F Bonifacio Technology Center
Bonifacio Global City Taguig, Metro Manila
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
3/71
NAME OF PROJECT :
LOCATION :Brgy. Tapia, Gen. Trias, Cavite
SCOPE OF WORK :LAND DEVELOPMENT WORKS, MASS HOUSING & FIESTA MARKET
PROJECT OWNER : BELLA VITA LAND CORP. , Primavera Towncentre Inc.
AWARDED CONTRACT : Php 66,389,280.12 MASS HOUSING (Batch 1 - 300 units)
AWARDED CONTRACT : Php 64,009,100.52 MASS HOUSING (Batch 2 - 302 units)
AWARDED CONTRACT : Php 160,528,712.25MASS HOUSING (Batch 3 - 726 units)
AWARDED CONTRACT : Php 92,265,655.35 FIESTA MARKET
AWARDED CONTRACT : Php 52,244,260.00 LAND DEVT (Tranche 1)
AWARDED CONTRACT : Php 54,227,660.00 LAND DEVT (Tranche 2)
AWARDED CONTRACT : Php 12,972,000.00 LAND DEVT (Tranche 3)
AWARDED CONTRACT : Php 4,983,312.48 GUARD HOUSE & CLUBHOUSE
AWARDED CONTRACT : Php 5,625,000.00 ELEVATED WATER TANK
TOTAL AWARDED CONTRACT : Php 513,244,980.70
PROJECT DESCRIPTION
COMPLETED
COMPLETED
COMPLETED
COMPLETED
COMPLETED
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
4/71
Updates As of September 8, 2014
A. Guard House & Clubhouse As Per RevenueApril 2013 (Projected Start Date)
As Per Actual ConstructionJune 2013 (Actual Date Started)
PROJECTED ACCOMPLISHMENT 100.00% (Php 4,983,312.48) 100.00% (Php 4,983,312.48)
ACTUAL ACCOMPLISHMENT 97.43% (Php 4,855,241.349)
(Approval of Bridge and Gate Design)
B. Elevated Water TankAs Per Revenue
July 2012 (Projected Start Date)
As Per Actual ConstructionApril 2013(Actual Date Started)
PROJECTED
ACCOMPLISHMENT100.00% (Php 5,625,000.00) 100.00% (Php 5,625,000.00)
ACTUAL ACCOMPLISHMENT 0% (Php 0.00)
(Put on-hold due to No Permit)
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
5/71
Updates As of September 8, 2014
D. Mass Housing
(726 units)
As Per RevenueAug 2013 (Projected Start Date)
As Per Actual ConstructionSept 2013 (Actual Date Started)
PROJECTED
ACCOMPLISHMENT100.00% (Php 160,528,712.25) 100.00% (Php 160,528,712.25)
ACTUAL ACCOMPLISHMENT 73.79% (Php 118,454,136.80)
C. Mass Housing(302 units)
As Per RevenueJuly 2012 (Projected Start Date)
As Per Actual ConstructionApril 2013 (Actual Date Started)
PROJECTED
ACCOMPLISHMENT100.00% (Php 64,009,100.52) 100.00% (Php 64,009,100.52)
ACTUAL ACCOMPLISHMENT 97.50% (Php 62,408, 873.01)
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
6/71
Guardhouse and Gate
Projected Percentage of Completion: 100%
Actual Percentage of Completion : 100% (Gate 1, Guard House); 95.43% (Gate 2, Guard House)
Guardhouse & Gate
(Main Road)
Turn-over to APMC
Guardhouse & Gate
(Along NIA Road)
Along Main Road Along NIA Road
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
7/71
Progress Photo
Actual Percentage of
Completion86.20%
Perimeter Fence
Status as of September 23,
2014:
CHB installed, Plastered
On-going Perimeter Fence
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
8/71
Summary of Land Development Issues and Concerns
ITEM
NO.AGENDA ACTION REQUIRED / STATUS RESPONSIBLE REMARKS
2.0 Land Dev't
2.1 Boundaries Dispute
There were initially identified boundaries dispute in
different location which affect the land dev. & housingconstruction
CMG COG awaiting for the resolutionboundaries dispute to complete.
2.2 Flooding issue on adjacent lot
Can't be completed due to lot encroachment issue
(Medina). 98% completion as of today, balance of
work: Manhole and double barrel RCP.
CMGCOG awating for the completion
of RCE perimeter fence.
2.3 Land Dev't Utilities
CMG will forward proposed deductive CO on drainage
for tranche 1 to COG w/c is awarded to NOCONCMG
COG awaiting for the deductive
CO on drainage @ Tr. 1 for
review & evaluation.
target close out for land dev't will be end of 2014 CMG/COGCOG inquire head office the
requirement of Close out Project
2.4 Relocation of Entrance Gate in Gate 2 CMG issue SI & plan for quotation of relocation ofEntrance Gate in Gate 2.
COG COG already submitted quotationto CMG for evaluation.
2.5 Entrance Gate @ Tr. 3CMG & IDG approved the proposed typical design of
entrance gateCMG/COG
COG awating to complete the
bridge before construction
entrance gate @ Tr. 3
2.6Bridge connecting Tranche 1 and Tranche
3
CMG will prepare the Change Order CMGCOG awating for the procurement
award.
Secure requirements for building permit CMG
COG awating for the requirement
from CMG for leg works process
of permit.
2.7 Elevated Water Tank
CMG / BV transmitted the requiremnet for NWRB COG
COG awating for the further
instruction due to denied permit
to drill from SBU.
CMG / BV prepared the building permit requirement. CMG
COG Awaiting for the
requirement to apply bldg.
permit.
2.8 Clubhouse & Guardhouse Bldg. Permit CMG / BV prepared the building permit requirement. CMG
COG Awaiting for balance
requirement of Tax declaration or
Re-Classsification
2.9 Additional Site dev't at CommonsCMG will issue SI & plan for quotation of additional
site developmentCMG
COG Awaiting for SI & plan to
prepare quotation
2.10 Alteration plan on Road 3 & Road 2CMG issue SI & plan to COG on alterations of roads
due to units that didnt meet the required set backCOG
COG already submitted quotation
to CMG for evaluation.
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
9/71
Item Brief Description PersonResponsible Target Status
1. Boundary Issues There were initially identified
boundary issues in different
locations which affects the
construction of Housing, Land
Development and Fiesta Market.
SBU, CMG Stagnant BellaVita already
coordinated with
Tenants on
adjacent property
Owners.
(Waiting for
resolution from
SBU)
Area 1- RCE on
going perimeter
fence
1
2
Land Development Issues and Concerns
3
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
10/71
Land Development Issues and Concerns
Item Brief Description Person
Responsible
Target Status
2. Flooding of
Adjacent Lot
Due to the absence to drainage line
to address rain water collected inside
the adjacent lot. Water level rises
and over flows on top of the main
road of Bella Vita
SBU, CMG,
NIA, VJS and
COG3
ASAP -On hold Construction
due to lot
encroachment issue
(Balance of work:
manhole and double
barrel RCP for drainage
outfall )98%completed.
-Awaiting for RCE
completion of perimeter
fence mobilized Sept.
02,2014
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
11/71
LOWEST POINT
FLOODED
AREA
Permanent Perimeter Fence
Temporary Fence
98 % Completed
Land Development Issues and Concerns
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
12/71
Land Development Issues and Concerns
Item Brief Description Person
Responsible
Target Status
3.Drainage outfall take
over by NOCON with
deductive to VJS
CMG will forward proposed
deductive CO on drainage outfall
to COG.
CMG, COG ASAP COG awaiting for
the deductive CO
on drainage @ Tr.
1 for review &
evaluation.
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
13/71
Land Development Issues and Concerns
Item Brief Description Person
Responsible
Target Status
4.Land Devp. Project
Target Close out this
2014
Land Deveplopment @ BV was
already completed and on going
Turn Over to Bellavita APMC
CMG,COG,
APMC
On going
rectification of
punchlist of Land
Devp. to turn over
to APMC.
Fiesta
Market
Tr. 1
Tr. 2
Tr. 2
(Hold Area)
Tr. 1
(on going
rectification
of punchlist)
Tr. 3
Fiesta Market(Accepted & Turn Over to APMC Dated April 04,2014
Except balance of work @ lot enchroament issue)
Tranche 1-Accepted & Turn Over to APMC Dated March 05,2014
Tranche 2-Accepted & Turn Over to APMC Dated March 14,2014
Tranche 3-Accepted & Turn Over to APMC Dated April 25,2014
Tranche 1(along Road 8)-On going repair & rectification of punchlist
to Turn Over to APMC this coming May 23,2014
Tranche 2(along Road 12)-Completed but rectification & repair
Hold Area by Bellavita
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
14/71
Land Development Issues and Concerns
Item Brief Description Person
Responsible
Target Status
5.Relocation ofEntrance Gate @
Guarhouse 2 along
boundary line.
CMG issue SI & plan forquotation of relocation of
entrance gate 2.
CMG, COG COG alreadysubmitted
quotation to CMG
for their
evaluation.
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
15/71
Land Development Issues and Concerns
Item Brief Description Person
Responsible
Target Status
6.Entrance Gate @ Tr.
3.
CMG & IDG approved the
proposed typical design of
entrance gate.
CMG, COG COG awaiting for
the lay out of
bridge before the
construction of
Entrance gate
due to the
absence of plan
reflected the
entrance gate &
bridge.
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
16/71
Item Brief Description Person
Responsible
Target Status
7. Bridge connecting
Tranche 1 and 3
Shop drawing of the bridge
connecting Tranche 1 and 3
was already transmitted on site
CMG, VJS and
COG3
COG awaiting for
the execution
upon
procurement
dept. award to
sub con.
Location of Bridge
connecting T1 , NIA road
and T3
Land Development Issues and Concerns
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
17/71
Item Brief Description Person
Responsible
Target Status
8. Elevated Water
Tank
Elevated Water Tank cant start
drilling due to hold order of Kap.
Grepo because Nia Road restoration
was not yet done or completed.
SBU,
CMG,Joson
and COG3
NWRB denied the
permit to drill and
COG awaiting for the
futher instruction from
SBU.
Land Development Issues and Concerns
Proposed Elevated
Water Tank
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
18/71
Land Development Issues and Concerns
Item Brief Description Person
Responsible
Target Status
9.Additional Site Devt.
for Commons.
CMG will issue SI & plan for
Quotation of additional Site
Development.
CMG, COG COG awaiting for
SI & plan to
prepare quotation
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
19/71
Land Development Issues and Concerns
Item Brief Description Person
Responsible
Target Status
10.Alteration Plan @
Road 2 & 3
CMG issue SI & plan on
alteration of roads due to units
that did not meet the required set
back.
CMG COG already
submitted
quotation to the
CMG for their
evaluation.
Road 2 Alteration
Road 3 Alteration
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
20/71
Item Brief Description Person
Responsible
Target Status
11. NIA Road widening LGU and DPWH informed the
site that there will be a proposed
road widening that might affect
the development along the
marked portion of the
subdivision.
SBU, CMG,
DPWH, LGU
and COG3
Despite the fact,
still SBU
forwarded an
approved Site
Instruction to
COG.(On going
Housing
Construction Batch 3)
Land Development Issues and Concerns
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
21/71
Land Development Issues and Concerns
Item Brief Description Person
Responsible
Target Status
12. Proposed
Retaining Wall
(Housing Tranche 1
along NIA Road;
Housing Tranche 3
along Rice field)
CMG requested COG for a
topographic and cross-section of
the actual elevation for design
and costing.
CMG, COG ASAP With approved
design of
Retaining Wall
and RCE started
construction
April 01,2014 at
Tr. 3 (On going)
Proposed Retaining Wall
On-going Construction
Completed
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
22/71
Housing Update
BATCH 1 : 100.00%
BATCH 2 : 97.50%
BATCH 3 : 72.79%
Percentage of Completion:
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
23/71
BV Tapia Mass Housing Update
Item Description & Status Batch 1 Batch 2 Batch 3 Total
A
ACCEPTED UNITS259.00 166.00 6.00 431.00
1 Turn Over to Unit Owner 52.00 4.00 2 58.00
2 ccepted Units w/o Turn Over to Unit Owner 207.00 162.00 4.00 373.00
Aging of Accepted Units w/o Turn Over from date ofAcceptance
6 mos & above(Dec.2013-below) 164 0 0 05 mos(Jan.2014)
41 163 6 0
4 mos(Feb.2014)
3 mos(March 2014)2 mo(April 2014)less than a month(May 2014)
B COMPLETED UNITS41.00 45.00 - 86.00
C ON GOING- 91.00 441.00 532.00
D ON HOLD(due to Unidentified Title)- -
262.00262.00
EON HOLD(due to proposed offsetting of properties betweenBellaVita & Profriends) - -
16.0016.00
F ON HOLD(due to lot enchroachment along Fiesta Market)- -
1.001.00
TOTAL UNITS FOR HOUSING CONSTRUCTION (Awarded)300.00 302.00 726.00 1,328.00
Balance to Award from BellaVita(Batch 4) 118.00
BellaVita Model House 4.00
TOTAL NUMBER OF UNITS IN BELLAVITA 1,450.00
1st &2nd Quarter of 2014
2013
431+ 86=517 units COMPLETED
532 units ON GOING
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
24/71
Housing Update
BATCH 01
Construction Duration (Batch 1 ): June 2012Jan 2013
Percentage of Completion : 100.00%
Work Item Scope of Works No of Units
Accepted by
BellaVita204
Moved-in unitOwners 55
100%Completed (For Acceptance
by BellaVita)15
100%Completed with Punchlist
(On-going Rectification)26
TOTAL 300
Work Item Scope of Works No of Units
100% Accepted By Bellavita 166
For Acceptance byBVQA Completed 45
90.00% to 99.99%Completed With Minor
Punchlist33
80.00% to 89.99% OnGoing Completion 28
70.00% to 79.99%On - Going Finishing Work
(Painting, Fixtures & Clearing)
60.00% to 69.99%
On - Going Masonry Finishes,
Roofing Works & Ceiling
Works8
50.00% to 59.99%On - Going Structural &
Masonry Works0
TOTAL 302
BATCH 02
Construction Duration (Batch 2 ): AprilDecember 2013
Percentage of Completion : 98.40%
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
25/71
Construction Schedule for Batch 2 ( 302 Units )
Construction Schedule for Batch 2 ( 302 Units ) CATCH UP PLAN
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
26/71
Construction Schedule for Batch 2 ( 302 Units ) CATCHUP PLAN
no.1
Construction Schedule for Batch 2 ( 302 Units ) CATCH UP PLAN
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
27/71
Construction Schedule for Batch 2 ( 302 Units ) CATCHUP PLAN
no.2
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
28/71
1.Delayed / Insufficient delivery of Sub-Con Materials
Responsible: JJM Construction
CSM(contractor supply materials) - JJM Construction
CSM MaterialsRequired CSM for
Batch 2
No. of Units
(Delivered & Installed
CSM)
No. of Units (Undelivered
& Un-installed CSM)
1.Wall Form Tiles (WFT) 302 302 0
2.White sand 302 294 8
3.Gravel (S-1) 302 294 8
4.Metal Stud (C-purlins) 302 302 0
5.Facia Board Ceiling 302 294 8
6.Stuco & Skimcoat 302 294 8
7.Flat Latex Paint & Pre Mixed Paint 302 294 8
8.Electrical & Plumbing rough in materials 302 215 87
9.Electrical Fixtures & wire 302 215 87
10.Sliding Windows Aluminum (Ordinanza) 302 215 87
Cause of Delay of Batch 2 Housing
2.Weather conditionMay,June & July 2014 (Rainy Season)
d
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
29/71
Housing Update
BATCH 03
Construction Duration (Batch 3 ):August 2013DECEMBER 2014
Percentage of Completion : 73.79%
Work Item Scope of Works No of Units
Accepted by BellaVita 6
90.00% to 99.99% Completed With Minor Punchlist5
80.00% to 89.99% On
Going Completion 4270.00% to 79.99% On - Going Finishing Work (Painting, Fixtures & Clearing) 44
60.00% to 69.99%On - Going Masonry Finishes, Roofing Works & Ceiling
Works68
50.00% to 59.99% Roof framing works 95
40.00% to 49.99% Masonry works 181
20.00% to 39.99% Thickened Slab 6
0.00% to 19.99% Site Works 0
Affected Units (Tranche 2) 262
HOLD BY BELLAVITA PROPOSED OFFSETTING OF
PROPERTIES BETWEEN BELLAVITA AND PROFRIENDS 16
ENCHROACHMENT ALONG FIESTA MARKET 1
TOTAL 726
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
30/71
Construction Schedule for Batch 3 ( 726 Units )
NOTE : DUE TO TYPHOON GLENDA
ACCOMPLISHMENT RESULTS
DELAY
September 24, 2014
WFT Requirement for Batch 3
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
31/71
WFT Requirement for Batch 3
(As of April 22,2014)
WFT Requirement for Batch 3
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
32/71
WFT Requirement for Batch 3
(As of April 22,2014)
ZERO PUNCHLIST RATE
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
33/71
Summary of Turn Over by BellaVita as of July 25,2014:
Date of
Acceptance
No. of Unit w/
Punchlist
No. of Unit w/o
PunchlistTurn Over Units by
BellaVita Rate
01-Jul-13 1 5 6 83%
01-Aug-13 1 2 3 67%
01-Sep-13 0 8 8 100%
01-Oct-13 0 7 7 100%
01-Nov-13 2 4 6 67%
01-Dec-13 0 4 4 100%
01-Jan-14 0 1 1 100%
01-Feb-14 0 3 3 100%
01-Mar-14 0 0 0 0%
01-Apr-14 2 2 4 50%
01-May-14 0 3 3 100%
01-Jun-14 0 5 5 100%
01-Jul-14 0 1 1 100%
Total 51
O U C S
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
34/71
Selected Move in Unit Owners
Tr. 1 Blk. 11Lot. 11 Tr. 1 Blk. 07Lot. 07
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
35/71
Tr. 1 Blk. 14Lot. 16
Selected Move in Unit Owners
Tr. 1 Blk. 8Lot. 16
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
36/71
Selected Move in Unit Owners
Tr. 1 Blk. 7Lot. 33 Tr. 1 Blk. 14Lot. 6
P Ph t M H i t B ll it T i
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
37/71
Progress PhotosMass Housing at Bellavita Tapia
Progress Photos BATCH 1 (Mass Housing 300 Units)
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
38/71
Progress PhotosBATCH 1 (Mass Housing 300 Units)
Progress Photos BATCH 1 (Mass Housing 300 Units)
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
39/71
Progress PhotosBATCH 1 (Mass Housing 300 Units)
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
40/71
Progress PhotosBATCH 1 (Mass Housing 300 Units)
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
41/71
Progress PhotosBATCH 2 (Mass Housing 302 Units)
( )
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
42/71
Progress PhotosBATCH 2 (Mass Housing 302 Units)
h C 2 ( i 302 i )
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
43/71
Progress PhotosBATCH 2 (Mass Housing 302 Units)
P Ph BATCH 2 (M H i 302 U i )
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
44/71
Progress PhotosBATCH 2 (Mass Housing 302 Units)
Progress Photos BATCH 3 (Mass Housing 726 Units)
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
45/71
Progress Photos BATCH 3 (Mass Housing 726 Units)
Progress Photos BATCH 3 (Mass Housing 726 Units)
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
46/71
Progress Photos BATCH 3 (Mass Housing 726 Units)
Progress Photos BATCH 3 (Mass Housing 726 Units)
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
47/71
Progress Photos BATCH 3 (Mass Housing 726 Units)
Progress Photos BATCH 3 (Mass Housing 726 Units)
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
48/71
Progress Photos BATCH 3 (Mass Housing 726 Units)
Progress Photos BATCH 3 (Mass Housing 726 Units)
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
49/71
Progress Photos BATCH 3 (Mass Housing 726 Units)
Summary of Issues and Concerns ( Housing )
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
50/71
Su a y o ssues a d Co ce s ( ous g )
ITEM
NO.AGENDA ACTION REQUIRED / STATUS RESPONSIBLE REMARKS
1.0 Mass Housing
1.1 Post Con Budget / Cost to Repair97 units lapsed the warranty out of 382 Units
Accepted w/o T.O.CMG/COG
COG already rectified 3 units
with lapsed warranty.And we
will prepare & submit cost to
repair for evaluation &
approval of CMG & SBU.
1.2 Priority Units
CMG give the updated target completion ofpriority units to COG so that they can prioritize
those units for take out this June-August.
COG
COG already expedite &prioritize the priority units to
complete on target date.
1.3Hold areas / Areas with boundary
dispute(262 Units)
CMG will give update to COG for this issue CMG
CMG will update regarding
hold areas.
COG will submit proposed deductive change on
housing in ear lot areaCOG
COG will prepare & submit
Deductive Cost for evaluation
& approval of CMG & SBU.
1.4 16 units on hold @ Tranche 1
Verify to Sir Arnel Sulit if the area is alreadycleared w/ adjacent property owner (Aldrin) coz
RCE already completed the Perimeter Fence
CMGAwaiting for Site Instruction
to proceed construction
1.51 unit on hold @ Tranche 2 due lot
boundaries dispute
CMG will coordinate Arnel Sulit for any update
for the resolution of boundaries disputeCMG
Awaiting for the resolution
boundaries dispute.
1.6 Tr. 3 Housing Work Stoppaged
Kap. Grepo hold the housing construction @ tr.
3 due to no Brgy. Clearance endorsement anddemanding to pay or any donation for here
brgy.
CMG CMG will raised to Arnel Sulitand will give update.
1.7Service Entrance Post for Gemelli
Units
verify to Sir Bob Tubayan if it's included to JJM
package for housingCMG
Awaiting for the document
that proof that Service
Entrance Post included to
JJM package.
1.8 Permanent Power of MeralcoMeralco submitted the master plan to MDC BP
last July 7,2014 for review.CMG/COG
COG will check and review
the plan reflected the asbuilt
of utilities.Futher budget for
relocation of utilities needed.
1.9 Housing COO ApplicationCOC is already endorsed to BFP, quotation was
already submit to Raymart YapCMG
COO already release lastSept. 2,2014
Issues and Concerns ( Housing )
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
51/71
( g )
Item Brief Description Person
Responsible
Target Status
1.Post Con Budget /Cost to repair budget
for units lapsed
warranty
As of today 97 units lapsed thewarranty out of 382 units
accepted w/o turn over.
SBU,CMG,COG
COG alreadyrectified 3 units
w/ lapsed
warranty.COG
will prepare &
submit cost to
repair for
evaluation &
approval.
Issues and Concerns ( Housing )
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
52/71
( g )
Item Brief Description Person
Responsible
Target Status
2.Priority Units @ BVTapia
CMG give the updated targetdate of completion of priority
units last June 2014 to COG so
that they can prioritized those
units for take out this June-
August 2014.
SBU,CMG,COG
ASAP COG alreadyexpedite &
prioritized the
priority units to
complete on the
target date.
Issues and Concerns ( Housing )
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
53/71
Item Brief Description Person
Responsible
Target Status
3.Hold Order/ Affected
Areas with boundaries
dispute
CMG advised COG to put on
hold the construction of 279
units at Tranche 1 & 2 due to
unidentified titles.
COG, CMG,
BELLAVITA
-Still on-hold
-CMG will update
COG regarding
hold areas.
-COG will prepare
& submit Deductive
Cost for evaluation
& approval.
Issues and Concerns ( Housing )
Issues and Concerns ( Housing )
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
54/71
( g )
Tranche 2Tranche 1 ( Block 2 to Block 5)
Tranche 2
SUMMARY OF AFFECTED UNITS
262 UNITS ( HOLD AREA )
16 UNITS ( HOLD BY BELLAVITA PROPOSEDOFFSETTING OF PROPERTIES BETWEEN
BELLAVITA AND PROFRIENDS )
1 UNIT
( ENCHROACHMENTALONG FIESTA MARKET )
Progress Photos
BATCH 3 (Mass Housing 726 Units)Affected Units
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
55/71
Affected Units
Issues and Concerns ( Housing )
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
56/71
Item Brief Description Person
Responsible
Target Status
4.Tr. 3 Housing Work
stoppaged.
Kap. Grepo Hold the Housing
construction @ tr. 3 due to no
brgy. Clearance endorsement &
demending to pay or donation for
here brgy.
SBU,CMG CMG will raise to
Arnel Sulit and give
COG update.
( g )
Issues and Concerns ( Housing )
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
57/71
Item Brief Description Person
Responsible
Target Status
5.Service Entrance
Post for Gemelli Units
CMG will verify to sir Bob
Tubayan if itss included to JJM
package for housing.
CMG COG awaiting for
the document that
proof that service
entrance post
included to JJM
package.
Issues and Concerns ( Housing )
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
58/71
Item Brief Description Person
Responsible
Target Status
6. Housing COOApplication
Contractors tax already paid byMDC BP and OBO issue Cert. of
Comp. to BFP and BFP issue the
order of payment.
COG, CMG,BELLAVITA
ASAP COO release lastSept. 02,2014 for
Batch 1 application
456 units
Issues and Concerns ( Housing )
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
59/71
Item Brief Description Person
Responsible
Target Status
7.Damages ofTyphoon Glenda
34 units roof and roof framingtotally damage, 25 units roofing
accessories only, 102 units Wall
stud and Form tiles damage, and
10 units window glass broken.
COG asap On-goingrestoration of
damages by
Typhoon Glenda
AFFECTED AREAS AND UNITS
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
60/71
Hold Area(Smart Masonry Walls)
Area Not Affected
Due to Obstruction
from Hold Area
Roof & Roof Framing totally Damaged
RoofingAccessories OnlyWall Studs & Form Tiles Damaged (On-going Units)
Window Glasses Broken10 Units
102 Units25 Units
34 Units
Flooded Area
AFFECTED AREAS AND UNITS
Issues and Concerns ( Housing )
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
61/71
Damages of Typhoon Glenda
Issues and Concerns ( Housing )
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
62/71
On-going restoration
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
63/71
FIESTA MARKET
FIESTA MARKET at BellaVita Tapia
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
64/71
Issues and Concerns
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
65/71
Item Brief Description Remarks Person
responsible
Status
1. Additional
drainage
overflow pipes
Completion of Drainage Overflow
Pipes (proposed additional RCP for
distribution of storm rain)
Awaiting for the Resolution on boundary
problem (encroachment issues)BV, PTI, & CMG
65.00%
2. PCCP CompletionConcreting of Road
Awaiting for the Resolution on boundary
problem (encroachment issues)BV, PTI, & CMG 95.00%
3. Completion of
Parking slotsAdditional 5 Parking Slots
Awaiting for the Resolution on boundary
problem (encroachment issues) 2
Parking slot Remaining due to Boundary
Issues, though 3 slots were completed
BV, PTI, & CMG 60.00%
4. Perimeter Fence
Perimeter Fence construction
(at the rear portion of STP and
MRF)
Awaiting for the Resolution on
boundary problem (encroachment
issues)
BV, PTI, CMG 50.00%
Additional Drainage Overflow Pipes
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
66/71
Temporary Fence
g p
Actual Percentage 65%
Temporary Fence
PCCP, Parking Slot and Perimeter Fence Completion
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
67/71
g p
Temporary Fence
Balance of Work
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
68/71
Item Contractor Contract Award Balance of Works Remarks ResponsiblePercentage of
Accomplishment
1 VJS Builders Land Development
Concreting of Road
Awaiting for the Resolution on
boundary problem
(encroachment issues)
BV, PTI, &
CMG95.00%
Additional 5 Parking Slots
Awaiting for the Resolution on
boundary problem
(encroachment issues) 2
Parking slot Remaining due toBoundary Issues, though 3 slots
were completed
BV, PTI, &
CMG
60.00%
Completion of Drainage Overflow
Pipes (proposed additional RCP for
distribution of storm rain)
Awaiting for the Resolution on
boundary problem
(encroachment issues)
BV, PTI, &
CMG65.00%
2 Gigatech Electrical
Electrical & telephone going to
ATM center, (Civil works will be
awarded to a different sub-con)
Awaiting for approval of proposal
from QS to PTI. Shop drawingwas only provided last Feb. 06,
2014.
BV, PTI, &CMG
0.00%
Balance of Work
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
69/71
Item Contractor Contract Award Balance of Works Remarks ResponsiblePercentage of
Accomplishment
2 Gigatech Electrical Testing & Commissioning Awaiting for permanent power. APMC, PTI, CMG 0.00%
3 RCE Perimeter FencePerimeter Fence construction (at the
rear portion of STP and MRF)
Awaiting for the Resolution on boundary
problem (encroachment issues)BV, PTI, CMG 50.00%
4 JJM Installation ofWater Meter
3 sets of Water Meter
JJM have installed 21 sets of Water
Meter out of 24 sets. Remaining 3 setswere put on hold due to absence of wall
from Fit-Out to where it will be attached.
PTI, CMG 87.50%
5 Advatech Genset Testing and Commissioning
APMC required to test the Genset for 8
hrs for them to certify its workability. For
re-scheduling due to unavailability of
Load Bank
COG, APMC 0.00%
Balance of Work
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
70/71
Item Contractor Contract Award Balance of Works Remarks ResponsiblePercentage of
Accomplishment
For Completion of PTI
1 Signage for stalls Approved Design and CostAPMC, PTI &
CMG0.00%
2 Removal of Guying APMC 0.00%
3 Permanent Power APMC 0.00%
For POSSIBLE CHANGE ORDER:
1 Provision of Lay-by along drop off (WAO-11)Awaiting for approval of submitted quotation from QS.
ALI/PTI to issue PO prior to implementationCMG, PTI 0.00%
2Cutting of stub-out along Common Stalls and
provision of floor drain with cover (WAO-13)
Awaiting for approval of submitted quotation from QS.
PTI to issue PO prior to implementationCMG, PTI 0.00%
3 ATM Center (WAO-14)Awaiting for approval of submitted quotation from QS.
PTI to issue PO prior to implementationCMG, PTI 0.00%
-
8/10/2019 Project Update - Bellavita Septemeber 24, 2014.1.pptx
71/71