risk managament by vilas mahajan

56
1 Risk Management By Vilas Mahajan

Upload: nicmarpunenotes

Post on 13-Apr-2017

369 views

Category:

Engineering


5 download

TRANSCRIPT

Page 1: Risk managament by Vilas Mahajan

1

Risk Management

By – Vilas Mahajan

Page 2: Risk managament by Vilas Mahajan

The Risk

• Exposure to the possibility of loss, injury ,or other adverse or unwelcome circumstance ; a

chance or situation involving such a possibility ……Oxford Dictionary • ‘Effect of uncertainty on objectives’

~ Uncertainties include events (which may or not happen) and uncertainties caused by a

lack of information or ambiguity …..ISO Guide -73

Page 3: Risk managament by Vilas Mahajan

The Risk

• Future problems that can be avoided or mitigated, rather than current ones that must be immediately addressed.

• Risk can be seen as relating to the Probability of uncertain future events.

• The probable frequency and probable magnitude of future loss.

• Risk is …..the product of ( probability of a hazard resulting in an adverse event) * ( severity of event)…… -

OHSAS

Page 4: Risk managament by Vilas Mahajan

The Risk

• Risk versus Uncertainty :

~ Uncertainty is immeasurable ,not possible to calculate ,while risk is measurable.

~ One may have uncertainty without risk but not risk without uncertainty.

~ Uncertainty is the absence of information about future events

Page 5: Risk managament by Vilas Mahajan

Risk Management

What is Risk Management ?

~ Process steps that enable improvement in decision making

~ A logical and systematic approach

~ Identifying opportunities

~ Avoiding or minimising losses

Page 6: Risk managament by Vilas Mahajan

Risk Management

What is Risk Management ? ~ Risk Management is the name given to a logical and

systematic method of identifying, analyzing, treating and monitoring the risks involved in any activity or process.

~ Risk Management in Project is about proactively working with project stakeholders to minimise the risk and maximise the opportunities associated with project decisions.

Page 7: Risk managament by Vilas Mahajan

Risk Management

• The aim is not to avoid risk but to make more informed decisions to ensure that project objectives are achieved and , ideally, exceeded.

• The Challenge is not to avoid risk , but to take calculated risks, by recognising and managing effectively

• Risk Management is a proactive process of looking forward and is fundamentally different from Crisis

Management. ~ Crisis Management is reactive and backward

looking.

Page 8: Risk managament by Vilas Mahajan

Risk Management

What is Risk Management ? ~ Risk Management is a methodology that

help managers make best use of their available resources.

Page 9: Risk managament by Vilas Mahajan

Risk Management

Who uses Risk Management ?• Risk Management practices are widely used in public and the

private sectors, covering a wide range of activities or operations.

These include: ~ Finance and Investment ~ Insurance

~ Health Care

~ Public Institutions

~ Governments

Page 10: Risk managament by Vilas Mahajan

Risk Management

How is Risk Management used?

~ The Risk Management process steps are a generic guide for any organization,

regardless of the type of business, activity or function.

Page 11: Risk managament by Vilas Mahajan

Risk Management

• The basic process steps are: ~ Establish the context

~ Identify the risks ~ Analyze the risk ~ Evaluate the risk ~ Treat the risk

Page 12: Risk managament by Vilas Mahajan

Risk Management

• Risk is dynamic and subject to constant change, so the process includes continuing:

~ Monitoring and review

~ Communication & consultation

Page 13: Risk managament by Vilas Mahajan

Risk Management• The Risk Management process: ~ Establish the context : - The strategic and organizational context in

which risk management will take place

- For example, the nature of business, the risks inherent in the business and the

business priorities.

Page 14: Risk managament by Vilas Mahajan

Risk Management

• The Risk Management process: ~ Identify the risks : - Defining types of risk, for instance, ‘Strategic’ risks to

the goals and objectives of the organization. - Identifying the stakeholders, (i.e., who is involved or

affected).

- Past events, future developments.

~ Monitor and review ~ Communicate & consult

Page 15: Risk managament by Vilas Mahajan

Risk Management

• The Risk Management process: ~ Analyze the risks - How likely is the risk event to happen? (Probability and

frequency?)

- What would be the impact, cost or consequences of that event occurring? (Economic, political, social?)

~ Monitor and review ~ Communicate & consult

Page 16: Risk managament by Vilas Mahajan

Risk Management

• The Risk Management process: ~ Evaluate the risks

- Rank the risks according to management priorities, by risk category and rated by likelihood and possible cost or consequence.

- Determine inherent levels of risk.

Page 17: Risk managament by Vilas Mahajan

Risk Management

• The Risk Management process: ~ Treat the risks : - Develop and implement a plan with specific

counter-measures to address the identified risks.

~ Consider: - Priorities (Strategic and operational)

- Resources (human, financial and technical)

- Risk acceptance, (i.e., low risks)

Page 18: Risk managament by Vilas Mahajan

Risk Management

• The Risk Management process: ~ Treat the risks : - Document your risk management plan and describe the reasons behind selecting the risk and for the treatment chosen.

- Record allocated responsibilities, monitoring or evaluation processes, and assumptions on residual risk.

Page 19: Risk managament by Vilas Mahajan

Risk Management

• The Risk Management process: ~ Monitor and review : - In identifying, prioritizing and treating risks,

organizations make assumptions and decisions based on situations that are subject to change,

(e.g., the business environment, trading patterns, or government policies).

- Risk Management policies and decisions must be regularly reviewed.

Page 20: Risk managament by Vilas Mahajan

Risk Management• The Risk Management process: ~ Monitor and review : - Risk Managers must monitor activities and processes to determine the accuracy of planning assumptions and the effectiveness of the measures taken to treat the risk.

- Methods can include data evaluation, audit, compliance measurement.

~ Communicate & consult

Page 21: Risk managament by Vilas Mahajan

Risk Management• Evaluate the risks - After identifying and analyzing

the risks, you can evaluate …….• What is the likelihood of the risk event occurring? - Almost certain - Likely - Moderate - Unlikely - Rare

Page 22: Risk managament by Vilas Mahajan

Risk Management

• What is the consequence if the risk event occurs?

- Extreme - Very high - Moderate - Low - Negligible

Page 23: Risk managament by Vilas Mahajan

Risk Management

• Evaluate the risks : - Describe or quantify exactly what is the ‘Likelihood’ and ‘Consequence’ terms mean to you.

- This helps in ensuring a consistent approach in future risk assessment and review and monitoring.

- It promotes a common understanding within the Administration.

Page 24: Risk managament by Vilas Mahajan

Risk Management

• Evaluate the risks :

After establishing ‘Likelihood’ and ‘Consequence’, tabulate the workouts……..

Page 25: Risk managament by Vilas Mahajan

Risk Management• Evaluate the risks : Extreme Very high Moderate Low Negligible

Almost certain Severe Severe High Major Moderate

Likely Severe High Major Significant Moderate

Moderate High Major Significant Moderate Low

Unlikely Major Significant Moderate Low Very low

Rare Significant Moderate Low Very low Very Low

Page 26: Risk managament by Vilas Mahajan

Risk Management

• Treating the risks - Low and very low level risks can normally be accepted, subject to on-going monitoring.

- All other risks are included in the management plan.

- The plan catalogues the risks, the level of risk, and describes a treatment.

- The treatment is the action proposed, (and perhaps the resources allocated).

Page 27: Risk managament by Vilas Mahajan

Risk Management

• Treating the risks : ~ Development of Risk Profiles

~ Industry audits

~ Random examinations

~ Targeted selections

~ Physical examination

~ Compliance improvement

Page 28: Risk managament by Vilas Mahajan

28

Risk ManagementContract Risk Management

• Risks are the Chances or Probabilities of Damage or Loss.

• Risks are to be ..• Identified• Understood• Evaluated and..• Mitigated

• Risk Management is a subject of guesstimate of future.

Page 29: Risk managament by Vilas Mahajan

29

Risk ManagementContract Risk Management

• Element Causing Risks..

• “Silence” on Certain Aspects• Inadequate Specifications

• “Openness” on Certain Aspects

• Unlimited Liabilities

Page 30: Risk managament by Vilas Mahajan

30

Limitation on Liabilities Seller’s liabilities are specified under various

clauses for identified circumstances. These are : Termination of Contract - risk purchase Warranty / Guarantee - risk purchase Defects Liability Consequential & or indirect damages Indemnities Liquidated damages against delayed delivery

& shortfall in performance

Page 31: Risk managament by Vilas Mahajan

31

Limitations on Liabilities

Seller’s liabilities vary as per the stipulations of individual clauses.

Put Cap on Overall Liabilities of the Seller arising out of All Clauses in the Contract.

Page 32: Risk managament by Vilas Mahajan

Limitation of Liability

• Clause 17.6 :- FIDIC ~ Neither Party shall be liable to the other Party for loss of use of any Works ,loss of profit, loss of any

contract or for any indirect or consequential loss or damage which may be suffered by the other Party in connection with the Contract,

other than ….. (a) Under Sub-Clause16.4 (Payment on Termination)

and (b) Sub-Clause 17.1( Indemnities )

Page 33: Risk managament by Vilas Mahajan

Limitation of Liability~ The total liability of the Contractor to the Employer , under

or in connection with the Contract , other than …… (a) under Sub – Clause 4.19 (Electricity, Water, and Gas), (b) Sub –Clause 4.20 ( Employer’s Equipment and Free-

Issue Material), (c) Sub – Clause 17.1( Indemnities) and (d) Sub-Clause 17.5 (Intellectual and Industrial Property

Rights), shall not exceed the sum stated in the Particular

Conditions or ( if a sum is not so stated ) the Contract Price stated in the Contract Agreement .

Page 34: Risk managament by Vilas Mahajan

Limitation of Liability

~ This Sub – Clause shall not limit liability in any case of ……. fraud , deliberate default or reckless misconduct by the defaulting Party.

Page 35: Risk managament by Vilas Mahajan

35

Risk ManagementContract Risk Management

Force Majeure

• Unforseeable Circumstances

• Beyond Party’s Normal Business Acumen.

• Caused By An Irresistible Force.

• Unavoidable Inspite Of The Reasonable Care

• Beyond Party’s Control.

Page 36: Risk managament by Vilas Mahajan

36

Risk ManagementContract Risk Management

Force Majeure Events• Nature• Government• Wars• Public Actions

• Industrial Circumstances

• Shortage Of Inputs

Page 37: Risk managament by Vilas Mahajan

Risk Management Force Majeure

~ Clause 19.1 :- FIDIC – Definition of Force Majeure

In this Clause, "Force Majeure” means an exceptional event or circumstance :

(a) which is beyond a Party’s control,

(b) which such Party could not reasonably have provided against before entering into the Contract.

Page 38: Risk managament by Vilas Mahajan

Risk Management Force Majeure

(c) which ,having arisen, such Party could not

reasonably have avoided or overcome and,

(d) which is not substantially attributable to the other Party.

Page 39: Risk managament by Vilas Mahajan

Risk Management Force Majeure

~ Force Majeure may include ,but is not limited to, exceptional events or circumstances of the kind listed below ,so long as conditions (a) to (d) above are satisfied :

(i) war ,hostilities (whether war be declared or not ), invasion act of foreign enemies,

(ii) rebellion ,terrorism, revolution ,insurrection ,military or usurped power, or civil war,

(iii) riot ,commotion, disorder, strike or lockout by person other than the Contractor’s Personnel and other

employees of the Contractor and Sub-contractors,

Page 40: Risk managament by Vilas Mahajan

Risk Management Force Majeure

(iv) munitions of war, explosive materials, ionising

radiation or contamination by radio-activity, except as may be attributable to the Contractor’s use of such munitions ,explosives, radiation or radio- activity, and

(v) natural catastrophes ,such as earthquake, hurricane ,typhoon or volcanic activity.

Page 41: Risk managament by Vilas Mahajan

Risk Management Force Majeure

~ Clause 19.2 :- Notice of Force Majeure If a Party is or will be prevented from performing any of

its obligations under the Contract by Force Majeure ,then it shall give notice to the other Party of the event or circumstances constituting the Force Majeure and shall specify the obligations, the performance of which is or will be prevented. The notice shall be given within 14 days after the Party became aware , or should have became aware, of the relevant event or circumstance constituting Force Majeure.

Page 42: Risk managament by Vilas Mahajan

Risk Management Force Majeure

The Party shall having given notice, be excused performance of such obligations for so long as such Force Majeure prevents it from performing them.

Notwithstanding any other provision of this Clause, Force Majeure shall not apply to obligations of either Party to make payments to the Party under the Contract.

Page 43: Risk managament by Vilas Mahajan

Risk Management Force Majeure

~ Clause 19.3 :- Duty to Minimise Delay Each Party shall at all times use all reasonable

endeavors to minimise any delay in the performance of the Contract as a result of Force Majeure.

A Party shall give notice to the other Party when it ceases to be affected by the Force Majeure.

Page 44: Risk managament by Vilas Mahajan

Risk Management Force Majeure

~ Clause 19.4 :- Consequences of force Majeure If the Contractor is prevented from performing any of

his obligations under the Contract by Force Majeure of which notice has been given under Sub-Clause 19.2 [ Notice of force Majeure], and suffers delay and/or incurs Cost by reason of such Force Majeure the Contractor shall be entitled subject to Sub-Clause 20.1[Contractor’s Claims]to:

Page 45: Risk managament by Vilas Mahajan

Risk Management Force Majeure

(a) an extension of time for any such delay, if Completion is or will be delayed under Sub-Clause 8.4 [Extension of Time for Completion], And

(b) if the event or circumstance is of the kind descried in sub –paragraphs(i) to (iv) of Sub –Clause 19.1[Definition of Force Majeure] and in the case of subparagraphs (ii) to (iv) ,occurs in the Country, payment of any such Cost.

After receiving this notice,theEmpolyer shall proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or determine these matters

Page 46: Risk managament by Vilas Mahajan

Risk Management Force Majeure

~ Clause 19.5 :- Force Majeure Affecting Subcontractor

IF any Subcontractor is entitled under any contract or agreement relating to the Works to relief from force majeure on terms additional to or broader than those specified in this Clause ,such additional or broader force Majeure events or circumstances shall not excuse the Contractor’s non –performance or entitled him to relief under this Clause.

Page 47: Risk managament by Vilas Mahajan

Risk Management Force Majeure

~ Clause 19.6 :- FIIDC Optional Termination, Payment and Release If the execution of substantially all the Works in

progress is prevented for a continuous period of 84 days by reason of Force Majeure of which notice has been given under Sub-Clause 19.2 [Notice of Force Majeure],or for multiple periods which total more than 140 days due to the same notified Force Majeure ,then either Party may give to the other Party a notice of termination of the Contract.

Page 48: Risk managament by Vilas Mahajan

Risk Management Force Majeure

In this event, the termination shall take effect 7 days after the notice is given, and the Contractor shall proceed in accordance with Sub-Clause 16.3[Cessation of Work and Removal of Contractor’s Equipment]Upon such termination, the Employer shall pay to the Contractor:(a) the amounts payable for any work carried out for which a price is stated in the Contract;

Page 49: Risk managament by Vilas Mahajan

Risk Management Force Majeure

(b) the Cost of Plant and Materials ordered for the Works which have been delivered to the Contractor, or of which the Contractor is liable to accept delivery ;this Plant and Materials shall become the property of(and be at the risk of) the Employer when paid for by the Employer, and the Contractor shall place the same at the Employer’s disposal;

(c ) any other Cost or liability which in the circumstance was reasonably incurred by the Contract in the expectation of completing the Works;

Page 50: Risk managament by Vilas Mahajan

Risk Management Force Majeure

(d) the Cost of removal of Temporary Works and Contractor’s Equipment from the Site and the return of these items to the Contractor’s work in his country (or to any other destination at no greater cost );and

(e) the Cost of repatriation of the Contractor’s staff and labour employed wholly in connection with the Works at the date of termination.

Page 51: Risk managament by Vilas Mahajan

Risk Management Force Majeure

~ Clause 19.7 :- Release from Performance under the Law

Notwithstanding any other provision of this Clause ,if any event or circumstance outside the control of the Parties ( including ,but not limited to ,Force Majeure) arises which makes it impossible or unlawful for either or both Parties to fulfil its or their contractual obligations or which ,under the law governing the Contract, entitles the Parties to be released from further performance of the Contract, then upon notice by either Party to the other Party of such event or circumstance :

Page 52: Risk managament by Vilas Mahajan

Risk Management Force Majeure

(a) the Parties shall be discharged from further performance, without prejudice to the rights

Of either Party in respect of any previous breach of the Contract, and

(b) the sum payable by the Employer to the Contractor shall be the same as would have been payable under Sub – Clause 19.6 [Optional Termination ,Payment and Release ]

if the Contract had been terminated under Sub- Clause 19.6.

Page 53: Risk managament by Vilas Mahajan

Generic Formula for Variation Adjustment

= adjustment multiplier to be applied for the contract value.

a = fixed coefficient, non adjustable part of the contract value.

b, c, d….. = coefficients of percentage of each cost element.

Ln, En, Mn….. = current cost indices/ reference prices for the period ‘n’

L0, E0, M0….. = Base cost indices/ reference prices on the Base Date 53

.....

OOO

n

MMnd

EEnc

LLbaPn

Pn

Page 54: Risk managament by Vilas Mahajan

54

i20.060.020.0 XSPECHECH

BPABPAXSPSP

O

N

O

NON

Price Variation Algorithm:

• SP = Sales Price; N = New ; O = Current; i=Initial• BPA = Index Price per MT of Bisphenol A (BPA)

• ECH =Index Price per MT of Epichlorohydrin (ECH)

Where,

VARIATIONS PERTAINING TO MATERIAL COST

Page 55: Risk managament by Vilas Mahajan

55

VARIATIONS PERTAINING TO LABOUR COST

• Necessary when the supplies are labour intensive• Variation in basic wages of specified labour category • Variation in dearness allowance

Wv – WbWb

• Pv = Price variation payable; Pq = Quoted Price• Iv = Average consumer Price Index for Ind. Workers for Pune for later 2/3 rd period• Ib = Index for March (current year)• Wv =Average Minimum basic Wages of skilled worker in seller’s works for the month of completion of fabrication• Wb = Wages for March (current year)

+ 0.30 Pq xPv = 0.60 x Pq x Iv – IbIb

Page 56: Risk managament by Vilas Mahajan

56

II शुभं भवतु II