louisiana transportation conference study rapid... · geotechnical design and construct techniques...

124
Case Study: Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate Myrtle Beach, South Carolina Ed Tavera, PE Jeff Speck, PE February 17 - 20, 2013 Presented By: Louisiana Transportation Conference Big River Industries, Inc.

Upload: vuanh

Post on 01-Feb-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Case Study: Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils

Using Lightweight Aggregate Myrtle Beach, South Carolina

Ed Tavera, PE Jeff Speck, PE

February 17 - 20, 2013

Presented By:

Louisiana Transportation Conference

Big River Industries, Inc.

Page 2: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

• Project Overview & Design Requirements

• Project Constraints

• Geotechnical Challenges

• Rapid Embankment Construction

• Lightweight Aggregate Borrow Proposed

• Compaction Verification

• Lightweight Aggregate Supply & Delivery

• Automated Geotechnical Instrumentation & Results

• Project Construction Pictures

• Closing

Presentation Agenda

Page 3: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

PROJECT OVERVIEW

Page 4: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Project Location Myrtle Beach, SC

Page 5: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Project Location

Page 6: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Project Site

US17 Bypass

East

N. Myrtle Beach Murrels Inlet

SC 707

Page 7: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

• Relieve growing traffic congestion

• Provide a facility to handle future development and growth

• Construct a safe, signature project for the stakeholders (Horry County, SC)

Purpose

Page 8: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

US 17 Bypass

Farrow Parkway

SC 707

Ramp C

Ramp A

Ramp D

Ramp B

Project Layout

Page 9: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Proposed Interchange

Page 10: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

175’ 225’ 300’ 175’ 140’ 225’

Bridge Span Lengths (Bridge Length 1,240 Feet)

Page 11: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Bridge Aesthetic Features

Page 12: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Bridge Features Interior Bent Cap Extensions

Page 13: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Retaining Wall Features (Rendering)

Page 14: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Wall Features

Columbia International Airport Interchange

Page 15: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

• Local Funding - led to higher expectations for project completion

• Heavy traffic volumes necessitated accelerated construction

• Elimination of long settlement waiting period

– Led to innovative geotechnical design and construct techniques

Schedule

Page 16: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

DESIGN REQUIREMENTS

Page 17: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

AASHTO LRFD Design • Strength Limit State • Service Limit State • Extreme Event I Limit State (Seismic) • Extreme Event II Limit State (Collision)

Design Requirements

Performance Based Design

• Service Limit State

• Extreme Event I Limit State (Seismic)

• Extreme Event II Limit State (Collision)

AASHTO LRFD Design • Strength Limit State • Service Limit State • Extreme Event I Limit State (Seismic) • Extreme Event II Limit State (Collision)

Performance Based Design

• Service Limit State

• Extreme Event I Limit State (Seismic)

• Extreme Event II Limit State (Collision)

Page 18: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

US Earthquakes 1705 - 1996 Seismic Hazard

1886 Charleston Earthquake

MW 7.3

Page 19: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

• Charleston fault zone (“Woodstock” fault) and the “Zone of River Anomalies” (ZRA) fault source

• Moment magnitude from 7.0 to 7.5.

• 1886 Charleston Earthquake

SC Seismic Hazard

Page 20: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

SC Seismic Hazard

FEE PGA 0.06g @ B/C Boundary

SEE PGA 0.24g @ B/C Boundary

Page 21: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

• Safety Evaluation Earthquake (SEE), ground shaking having a 3% probability of exceedance in 75 years (2,500 year return period) PGA = 0.39g

• Functional Evaluation Earthquake (FEE), ground shaking having a 15% probability of exceedance in 75 years (500 year return period) PGA = 0.13g

Extreme Event I Limit State SC Design Earthquakes

Page 22: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

PROJECT CONSTRAINTS

Page 23: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

• High existing traffic volume

• No lane closures during summer months

• Maintaining access to numerous businesses

Traffic Control

• Complex construction traffic control plan • 8 proposed stages of construction • Maintain existing number of lanes • Temporary pavement • Multiple traffic shifts • Temporary alignments • Detour routes

Page 24: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

• Traffic Control – Maintain Existing Number of Lanes & Access to Numerous Business

• Embankment Construction – Traffic Control Stages 2, 3, and 4

• Project Geometry and Layout

– Existing Alignment

– Limited R/W

• Limited Construction Staging Areas

• Construction Time Requirements – 3.5 years

Project Constraints

Page 25: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

GEOTECHNICAL CHALLENGES

Page 26: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Fantasy Harbour

US 17/SC 707 (Backgate)

2 Miles Away!

Myrtle Beach, SC Regional Experience

Page 27: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

• 2 Miles North of US 17 /SC 707 Interchange

• New Alignment

• Bridge Over the Atlantic Intracoastal Waterway

• 3.1 Miles Roadway Approaches and Bridge

Fantasy Harbour

Page 28: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Fantasy Harbour West Abutment Subsurface Soils

SB2 RB-24 RB-25 RB-27 SB1 RB-28 RB-29

0 ft-msl

-50 ft-msl

Pee Dee Formation

Very soft to medium CLAYs (CL/CH)

Very loose to medium SANDs (SP/SC/SM)

Page 29: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Fantasy Harbour East Abutment Subsurface Soils

RB-13 SB6 SB1 RB-11 RB-16 SB2-A

SB3-A

SB5

0 ft-msl

-50 ft-msl

Very loose to medium SANDS (SP/SM/SC

Pee Dee Formation

Very soft to medium CLAYs (CL/CH)

Page 30: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

• 10’ – 42’ Embankment, Settlement 9” to 67”

• Liquefaction – Loose Sands • Embankment Slope

Instability (Static/Seismic)

Fantasy Harbour Geotechnical Experience

• Ground Improvement!!! • 2 Year Embankment Construction Contract • 2-3 Year Bridge Construction Contract

Page 31: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

North Bridge Approach

South Bridge Approach

Let’s Return To US 17/ SC707 Interchange (Backgate)

Page 32: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

South Bridge Approach Subsurface General Profile

Page 33: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

North Bridge Approach Subsurface General Profile

Page 34: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

• 30’ to 60’ - Soft to Firm Clay

• Pockets of Loose Sands in upper 10’

• Intermediate Medium Sands (253+00 to 256+00)

• Loose Sands above Dense Sands (Liquefiable)

• Pee Dee Formation

Geotechnical Challenges

Page 35: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Bridge Abutment Settlement (Normal Weight Fill 120 pcf)

Page 36: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

• Poor Site Subgrade (2’ – 3’ Bridging Required)

• Excessive Settlement – (Total & Differential)

• Static Slope Embankment Instability/Bearing

• Seismic Slope Embankment Instability (Liquefaction)

Geotechnical Challenges

Page 37: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

RAPID EMBANKMENT CONSTRUCTION

Page 38: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Geotechnical Challenges

Project Constraints

Rapid Embankment Construction

Page 39: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

• Settlement – Total & Differential

• Embankment Slope Instability / Bearing (Static/Seismic)

• Bridge Abutment Foundation Performance - Extreme Event I and II Limit States

• MSE Wall Construction Over Soft Soils

Geotechnical Key Design Issues

Page 40: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

• Lightweight Aggregate Borrow – Reduce Magnitude of Settlement

• Prefabricated Vertical Drain (PVD) / Granular Surcharges – Increase Rate of Settlement and Facilitate Rapid Construction

• Deep Soil Mixing – Improve Seismic Slope Stability and Bridge Abutment Foundation Performance

• Mechanically Stabilized Earth (MSE) Walls

2-Stage and 3-Stage MSE Wall Construction

Vertical Slip Joints

Geotechnical Design Approach

Page 41: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Granular Surcharge Properties: • = 32 degrees • Unit Weight: 125 pcf

Granular Surcharge

Lightweight Aggregate

Borrow Material

Lightweight Aggregate Properties: • = 40 degrees • Short Term Unit Weight: 60 pcf • Long Term Unit Weight: 70 pcf • MSE Wall Backfill Properties

½ Normal Weight

Normal Weight

Lightweight Aggregate

Granular Surcharge & Lightweight Aggregate Borrow

Page 42: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Lightweight Aggregate Borrow (Rotary Kiln Produced)

226,000 CY

Page 43: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

3 Million LF

PVD Installation

Page 44: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

PVD

PVD Triangular Installation Pattern

PVD

S

2’ Drainage Sand Layer

Geotextile Separator Fabric

s = 3’ and 4’

PVD Installation

Page 45: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Predrilling PVD Installation 309,000 LF

PVD Installation Obstructions!!!

Page 46: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Permanent MSE Walls • Two-Stage Construction • Three-Stage Construction (w/Drainage Structures)

Temporary MSE Walls (Welded Wire Mesh Facing)

30,500 SF

51,500 SF

MSE Walls

Page 47: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

• Seismic Slope Stabilization – Shear Key • Improved Performance of Bridge Abutment Foundations • 2013

35,600 CY

Deep Soil Mixing Columns (Overlap – Block Pattern)

Page 48: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Bridge Abutment DSM Longitudinal DSM Longitudinal DSM

Deep Soil Mixing Columns (Overlap – Block Pattern)

Page 49: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Legend

Test Lime-Cement Columns (Test LCC)

DSM-LCC Test Section 1

(Block Type Pattern)

DSM-LCC Test Section 2

(Single Line Pattern)

10 Feet Min.

10

Fe

et M

in.

Test LCC No. 1 2 3 4

Test Pile 1 (HP 14x117)

Test LCC Sampling Quadrants

1

2

4

3

Deep Soil Mixing Test Sections

Page 50: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

CONSTRUCTION SEQUENCE

Page 51: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Ramp B Stage 2

Ramp D Stage 3

Bridge Approach Embankment Stage 4

Project Construction Stages (North Abutment 252+01)

Page 52: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Bridge Abutment Construction (North Abutment – End Bent 7)

Page 53: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

HP 14x117 22 Piles/row

30 Feet

DSM-LCC Block Type Pattern MSE Wall Leveling Pad

PVD (Wick Drains)

MSE Wall Concrete Panel Facing

Bridge Wing Wall Vertical Slip Joints

Bridge Abutment Construction

Page 54: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

LIGHTWEIGHT AGGREGATE

BORROW PROPOSED

Page 55: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Lightweight Aggregate Borrow (Proposed New Material)

Page 56: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Lightweight Aggregate Borrow (Rotary Kiln Produced)

Page 57: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

0

10

20

30

40

50

60

70

80

90

100

0.0100.1001.00010.000100.0001000.000

% P

assi

ng

Grain Size (mm)

LWF Min

LWF Max

713 Min

713 Max

BR Min

BR Max

LWA (S15922)

Section 713 MSE Wall

Big River Proposed Lightweight Aggregate

1 ½" ¾" 3/8" # 4 # 100 # 40 # 30 # 200

Grain Size Curve

Page 58: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Lightweight Aggregate Borrow Soil Properties (Item 2033020)

Soil Properties SCDOT Specified Proposed

Minimum: Dry Unit Weight, gDry (pcf) 55 43*

Maximum: Dry Unit Weight, gDry (pcf) 60 45**

Minimum: Wet Unit Weight, gWet (pcf) 60 55**

Maximum: Wet Unit Weight, gWet (pcf) 70 60**

* 95% Maximum Density **Estimated based on laboratory testing submitted by Big River Industries

Lightweight Aggregate Density Properties

Page 59: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

• Higher Fines Content

• Lower Dry Unit Weight

• Total Unit Weight 15% Less Than Designed

• High Absorption

• Gradation – Coarse Sand Vs. Aggregate

• Compaction Verification Required by SCDOT

Lightweight Aggregate Borrow (Proposed New Material Differences)

Page 60: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Test Section #1 (Dry)

Page 61: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Test Section #1 (Wet)

Page 62: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Granular Surcharge

Granular Backfill

Lightweight Aggregate

Borrow Material

• Design Team Performed a Redesign

• Reduced the Lightweight Quantity by 15%

• Saved Horry County $2 Million

Granular Surcharge & Lightweight Aggregate Borrow

Page 63: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

COMPACTION VERIFICATION

Page 64: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Interparticle Moisture

Interparticle Voids

Particle Absorbed Moisture

Particle Pore Voids

Particle Ceramic Solids

Lightweight Aggregate Borrow Compaction Verification Challenges

Page 65: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

• Laboratory Compaction Curves

• Target 95% Max Dry Density = 43 pcf

• Moisture Content Varied Significantly for the same Dry Density

Compaction Control

Page 66: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

• Test Section #2 - Evaluate Compaction Control Methods

• Compaction Control - 1 Cu. Ft. Steel Box, Calibrated Nuclear Density Gauge, Sand Cone, and EDG.

Test Section #2 Compaction Control

Page 67: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

SC = Sand Cone NG = Nuclear Gauge EDG = Electric Density Gauge STB = Steel Test Box

EDG-1

Compacted Lightweight Aggregate

Borrow MC-3

STB

EDG-2 SC-1

SC-2

SC-3

MC = Hot Plate & Oven Moisture Content MT = Moisture Tester MTB = Moisture Tester in Steel Box

MC-1 MC-2

EDG-3

NG-1

NG-2

NG-3

MT-1

MT-2

MT-3 MT-4

MTB-1 MT-5 MT-6

MT-7 MT-8 MTB-2

MTB-3

Test Section #2 Field Testing Set

Page 68: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Test Section #2 1 Cu. Ft Steel Box (Control Test)

Page 69: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Test

Set Moisture Added Process Compaction Effort

1 As delivered Compact 3 passes with vibratory roller

2 No Water Added Scarify & Compact 4 passes with a vibratory roller

3

Added Water - 1 Pass Scarify & Compact 8 passes with a walk behind

vibratory flat plate compactor

4 Added Water - 2 Passes Scarify & Compact 3 passes with a vibratory roller

5 No Water Added Scarify & Compact 4 passes with a vibratory roller

6 No Water Added Scarify & Compact 8 passes with a vibratory roller

7

Added Water- 2.5 Passes

(Saturated) Scarify & Compact

3 passes with a vibratory roller

Test Section #2 Field Testing Sets

Page 70: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Test Section #2

Page 71: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Compaction Control Calibrated Nuclear Gauge

Page 72: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

LIGHTWEIGHT AGGREGATE

SUPPLY & DELIVERY

Page 73: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Big River Industries Livingston, AL – Myrtle Beach, SC

Page 74: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Big River Industries 500 Mile Radius – Livingston, AL

Page 75: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Livlite Big River Industries

Page 76: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Lightweight Aggregate Borrow Pre-conditioning

Page 77: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Lightweight Aggregate Borrow Pre-conditioning

Page 78: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

CONSTRAINTS

Ramp B Construction Pre-conditioned Lightweight Aggregate

Page 79: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

CONSTRAINTS

Ramp B Construction Pre-conditioned Lightweight Aggregate

Page 80: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

GEOTECHNICAL INSTRUMENTATION

Page 81: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Settlement Monitoring • 4 Magnetic Extensometer • 10 Settlement Plates • 12 VW Settlement Sensors • 17 VW Piezometers • 2 VW Data Collection Centers

Slope Stability • 6 Slope Inclinometers

Geotechnical Instrumentation

Page 82: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Spider Magnet Pre-Assembled ME Telescoping Section

VW Magnetic Extensometers

Page 83: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

-70

-60

-50

-40

-30

-20

-10

0

10

20

-10.0-9.0-8.0-7.0-6.0-5.0-4.0-3.0-2.0-1.00.01.0

Ele

vati

on

(fe

et)

Settlement (Inches)

12/1/2011

12/7/2011

12/14/2011

12/19/2011

12/21/2011

12/27/2011

12/29/2011

1/4/2012

1/12/2012

1/18/2012

1/25/2012

2/1/2012

12-22-2011 Embankment Construction

Finished

-8

-7

-6

-5

-4

-3

-2

-1

0

1

2

3

4

5

6

7

8

9

10

11

12

0 7 14 21 28 35 42 49 56 63 70

Emb

ankm

en

t H

eig

ht

(Fe

et)

Days

EmbankmentHeightTop of LWF

Datum Magnet

SA-1

SA-2

Sett

lem

en

t (I

nch

es)

Instrumentation Results ME Extensometers

Page 84: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

VW Piezometers

Page 85: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Instrumentation Results VW Piezometers

Page 86: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Settlement Plates

Page 87: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

VW Settlement Sensors

Page 88: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

VW Settlement Sensor Data Collection

Page 89: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

VW Data Collection

Logger

VW Settlement

Sensors

VW Piezometers Engineer

Internet

Power Source (Solar Power)

Database Server

Cellular Phone

VW Device Connection

Board

VW Data Collection Center

Automated Data Collection

Page 90: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

VW Devices connected to 16-channel Board

VW Device Connections

Page 91: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

iSite Logger with Solar Controller Charging Battery

Inside DCC Enclosure & Solar Panel

Data Collection Center

Page 92: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

X-Section End Bent 1 (South Bridge Abutment, 237+50)

Page 93: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Ramp A

Settlement Transverse Profile (South Bridge Abutment – 237+83)

Page 94: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Ramp A Settlement Measurements

2-12-2011 Embankment Construction

Finished

2-14-2012 Surcharge Removed

-6

-5

-4

-3

-2

-1

0

1

2

3

4

5

6

7

8

9

10

11

12

13

14

0 7

14

21

28

35

42

49

56

63

70

77

84

91

98

10

5

11

2

11

9

12

6

13

3

14

0

14

7

15

4

16

1

16

8

17

5

18

2

18

9

19

6

20

3

21

0

21

7

22

4

23

1

23

8

Emb

ankm

en

t H

eigh

t (F

eet)

Days Since VWSS Installed

US-17 Bypass Settlement Sensor A-VWSS-2

Embankment Height

Lightweight Fill Height

SS Reading No. 1- 5:00

SS Reading No. 2- 12:00

SS Reading No. 3- 19:00

SS Reading No. 4- 23:00

Sett

lem

en

t

Page 95: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Ramp C

Settlement Transverse Profile (South Bridge Abutment – 237+83)

Page 96: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Ramp C Settlement Measurements

9-13-2012 Emankment Construction Finished

12-14-2012 Surcharge Removed

-3

-2

-1

0

1

2

3

4

5

6

7

8

9

10

11

12

13

0 7

14

21

28

35

42

49

56

63

70

77

84

91

98

10

5

11

2

11

9

12

6

13

3

14

0

14

7

15

4

16

1

16

8

17

5

18

2

18

9

19

6

20

3

21

0

21

7

22

4

Emb

ankm

en

t H

eigh

t (F

eet)

Days Since VWSS Installed

Embankment Height

Lightweight Fill Height

SS Reading No. 1- 5:00

SS Reading No. 2-11:00

Sett

lem

en

t (I

nch

es)

Page 97: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

X-Section End Bent 7 (North Bridge Abutment, 250+26)

Page 98: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Ramp B

Settlement Transverse Profile (North Bridge Abutment - 250+26)

Page 99: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

12-22-2011 Embankment Construction

Finished

4-10-2012 Surcharge Removal

-12

-11

-10

-9

-8

-7

-6

-5

-4

-3

-2

-1

0

1

2

3

4

5

6

7

8

9

10

11

12

0 7

14

21

28

35

42

49

56

63

70

77

84

91

98

10

5

11

2

11

9

12

6

13

3

14

0

14

7

15

4

16

1

16

8

17

5

18

2

18

9

19

6

20

3

21

0

21

7

22

4

23

1

23

8

24

5

25

2

25

9

26

6

Emb

ankm

en

t H

eigh

t (F

eet)

Days Since VWSS Installed

Settlement Sensor

Embankment Height

Lightweight Fill Height

SS Reading No. 1 - 5:0:0

SS Reading No. 2 - 12:0:0

SS Reading No. 3 - 19:0:0

SS Reading No. 4 - 23:0:0

Sett

lem

en

t

Ramp B Settlement Measurements

Page 100: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Ramp D

Settlement Transverse Profile (North Bridge Abutment - 250+26)

Page 101: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Ramp D Settlement Measurements

10-26-2012 Emankment

Construction Finished

2-5-2013 Surcharge Removed

-14-13-12-11-10

-9-8-7-6-5-4-3-2-10123456789

101112131415161718192021222324

0 14 28 42 56 70 84 98 112 126 140 154 168 182

Emb

ankm

en

t H

eigh

t (F

eet)

Days Since VWSS Installed

EmbankmentHeightLightweight FillHeightSS Reading No. 1-5:00SS Reading No. 2-12:00SS Reading No. 3-19:00

Sett

lem

en

t

Page 102: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

PROJECT CONSTRUCTION

Page 103: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

• MSE Walls • Lightweight Aggregate Borrow Material • 2’, and 3’ Granular Surcharge (Normal Weight) • 3’ and 4’ Triangular Spacing PVD • Geotechnical Instrumentation

Ramp B Ramp A

Traffic Control Stage 2

Page 104: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Traffic Control Stage 2

Ramp A Construction

US 17 Bypass NB

Page 105: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Traffic Control Stage 2

Ramp B Construction

US 17 Bypass NB

Page 106: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Construction Ramp A & B (PVD Installation)

Page 107: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Construction Ramp A & B (PVD Installation)

Page 108: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Construction Ramp A & B (MSE Wall Embankment Construction)

Page 109: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Construction Ramp A & B (MSE Wall Embankment Construction)

Page 110: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

2 Feet Thick Cover of Borrow Silty or Clayey Soil Materials

Lightweight Aggregate Borrow Material

4 Feet Long Biaxial Geogrids Placed on 2 Feet Vertical Spacing

Sloped Lightweight Aggregate Embankment

Page 111: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Sloped Lightweight Aggregate Embankment

Page 112: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Ramp C Ramp D

• MSE Walls • Lightweight Aggregate Borrow Material • 1’, 2’, and 4’ Granular Surcharge (Normal Weight) • 3’ and 4’ Triangular Spacing PVD • Geotechnical Instrumentation

Traffic Control Stage 3

Page 113: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Constructed Ramps A/B (Completed – Stage 2)

Existing NB = Stage 3 SB

Ramps C/D Under Construction -Stage 3

Traffic Control Stage 3 (Ramps A & B Completed)

Page 114: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Traffic on Ramp A

Existing NB = Stage 3 SB

Traffic Control Stage 3 (Ramps A & B Completed)

Page 115: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Traffic on Ramp C

Construction Ramp C

US 17 Bypass SB

Page 116: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Traffic on Ramp C

Construction Ramp C

US 17 Bypass SB

Page 117: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Ramp D

Construction Ramp C

US 17 Bypass SB

Page 118: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Traffic on Ramp B

Ramp D

Construction Ramp D

Page 119: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

South Bridge Approach North Bridge Approach Backgate Bridge

• MSE Walls • Lightweight Aggregate Borrow Material • 1’, 2’, and 3’ Granular Surcharge (Normal Weight) • 3’ Triangular Spacing PVD • Geotechnical Instrumentation • Bridge Abutment DSM (South 30’ x 133’ x 50’deep – North 30’ x 141’ x 70’deep ) • Longitudinal DSM (South 5’ Wide / North 8’ Wide)

Traffic Control Stage 4

Page 120: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

CLOSING

Page 121: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Project Status

• Preliminary Engineering: 2008 - 2009

• Right of Way Acquisition: 2009 - 2011

• Construction: 2011 – 2014

– Approximately 33% complete

Page 122: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Under Construction

• Traffic Stage 3 – Ramps C/D have been constructed and will be ready to be paved in the near future

• Traffic Stage 4 – Scheduled to Start April 2013

– Deep Soil Mixing : Test Section / Test Pile / Production

– Bridge Abutment Foundation Construction

– Construct Bridge Approach Embankment & MSE Walls

Page 123: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

• Geotechnical techniques are speeding up construction

• Positive feedback regarding construction traffic congestion and shifts

• Estimated project completion: Fall 2014

• Project Cost $75.8 Million

Closing

Page 124: Louisiana Transportation Conference Study Rapid... · geotechnical design and construct techniques Schedule . DESIGN ... •Deep Soil Mixing ... Settlement Sensor A-VWSS-2

Thank You Any Questions?