water supply and sewerage design

48
CE 465 Water Supply and Sewerage System Design Water Supply and Sewerage Design Term Project Anthony Fang, Jeremy Molayem, Viv Pitter, Kirsten Rice, Ryan Williams Professor C.C. Wang 30 April 2013 Spring 13

Upload: jeremy-molayem

Post on 23-Nov-2015

81 views

Category:

Documents


5 download

DESCRIPTION

Design a water supply/distribution system and sewerage conveyance system for a small community. Software used is publicly available EPA-NET and EPA SWMM. Both theoretical calculations and computational modelling is available.

TRANSCRIPT

  • C E 4 6 5 W a t e r S u p p l y a n d S e w e r a g e S y s t e m D e s i g n

    Water Supply and Sewerage Design

    Term Project Anthony Fang, Jeremy Molayem, Viv Pitter,

    Kirsten Rice, Ryan Williams Professor C.C. Wang

    30 April 2013

    Spring 13

  • Design Proposal 2

    2

    Table of Contents I. Executive Summary....................3 II. Water Demand.......4

    i) Residential. ii) Coecial....4 iii) Industrial ... iv) Fie Flow........ III. Water Supply System................................6

    i) Pipe Size...6 ii) Pipe Material.....6 iii) Water Tower and Reservoir Designs... iv) Pump Design...7 v) Fire Hydrant Locations ...8 vi) Valves 9 IV. Sanitary Sewer System........10

    i) Pipe Size.10 ii) Pipe Velocity.10 iii) Pipe Material...10 iv) Pipe Connections.11 v) Manholes .12 V. Storm Sewer System.......13

    i Muicipal Need.13 ii Desig Paaetes.13 iii) Stormwater Software ad Desig Methods..14 iv) Storm Intensity and Duratio Data .17 v) Ratio Flow to Full Flow Paaete.17 vi) Miiu Slope Paaete..9 vii) Minimum Velocity Paramete. iix) Minimum Diameter Parameter and Mateials Used.. ix) Hydraulic Profiles.. Sua of Results.. VI. Utility Cross Sections....25 VII. Works Cited......26 VIII. Appendix.........27

    Executive Summary

  • Design Proposal 3

    3

    Our average and maximum daily flows were calculated for residential areas based on a

    per capita consumption of 100 gallons per day. We selected a food processing industry for our

    industrial zone calculations, and calculated the flows based upon consumption rate data found

    through research (Water and Wastewater Use in the Food Processing Industry). The

    commercial demand was based on consumption rates for malls based on estimated visitors per

    day (George), as we decided to have one large shopping complex located in this area.

    The water distribution system consists of 55 pipes with 38 junctions, and was designed

    using EPANET after draw-offs at each node were calculated. The largest required flows are

    located at the industrial and commercial areas, and therefore the major pipelines are located in

    this area. The system was designed for three different scenarios: both a pumping station and a

    water tower supply water to the community, the water tower fails and only the pumping

    station is in operation, and lastly, the pumping station supply is cut off and the water tower

    supplies all water. The last arrangement was the worst-case scenario, and therefore

    determined the water supply model created and diameters of the pipelines selected.

    The sanitary sewer system was detailed using an Excel sheet for calculations to

    determine pipe diameter and manhole elevations required for the acceptable range of

    velocities, and then modeled using these results. The modeling does not include wastewater

    treatment specifications, which would be needed but are outside the scope of this project. The

    storm drain system was designed using EPA SWMM (Storm Water Management Model), and

    both systems run south to north to follow the natural grade of the area in consideration.

  • Design Proposal 4

    4

    Overall System Layouts

    Water Demand

    Residential

    The residential area was calculated by hand totaled to 66.281 acres. A population density

    assumption of 40 people/acres was made based on the design parameters given, which equates

    to an expected population of 2652 people for the region. The average consumption of the

    residential area is 2.652 x 105

    gpd, the peak day consumption is about 5.304 x 105 gpd and the

    peak hour consumption is about 1.608 x 106 gpd based on a consumption rate of 100 gpcd.

    Commercial

    The Commercial zone was a shopping center that took up the entire area of B and C, which

    totaled to 3.2881 acres. The shopping center included parking, retail, and grocery stores. The

    water consumption was calculated using equations based on population use (George).

    Assumptions of the shopping area operating 10 hours a day and about 15% of the population,

    or 389 people, visiting the shopping center daily were made. It was assumed that 50 employees

    worked at the shipping center daily. Visitors consumption was approximately 497.5 gpd while employee consumption was about 10,000 gpd. Thus the total demand for the shopping center

    came to 10,497.5 gpd with a flow rate of 17.5gpm. The peak day flow rate was 35 gpm.

    Industrial

    The industrial zone consists of a vegetable and fruit processing facility. The nature of a fruit

    processing facility can consume large quantities of water, in washing including peeling and

    pitting practices, blanching, fluming the produce after blanching, sorting, and conveying the

    product within the plant. Reducing size, coring, slicing, dicing, pureeing, and juicing process

    steps, as well as filling and sanitizing activities after processing, also contribute to the water use

  • Design Proposal 5

    5

    (Water and Wastewater Use in the Food Processing Industry). The industrial area consisted of

    3.2881 acres with a population density of 20 people/acre giving a total population of 66.

    These activities consume water relative to the type of vegetable or fruit being as well as the

    quantity being processed. Therefore, it is reasonable to believe that the design criteria of 2000

    gpm for 8 hours a day on working days and peak hour consumption of 3000 gpm would be

    sufficient to supply this type of industry with the required water supply.

    Fire Flow

    Fire Flow was calculated based on the following equation NFF = (Ci)(Oi)[(1.0+(X+P)i].

    Assumptions were based off photos of fruit and vegetable processing plants. The Construction

    of the building was assumed to be a single story wood frame structure. Most of the work is

    done in a warehouse and large packing sheds leading to exposed walls of over 400 feet. The

    layout of structures on the site are spread out anywhere from 31-60 feet. Total processing

    space was assumed to be 50,000 sq. ft. out of the total space in the industrial zone of 143,230

    sq. ft. The influence of the occupancy in this case being fruit and vegetables was assumed to be

    noncombustible. Given this information the fire was calculated to be 5200 gpm or 3.12 Mgd

    (for a 10 hour duration). The 10 hour duration was chosen in order to provide a conservative

    estimate. (See Appendix for Calculations)

  • Design Proposal 6

    6

    Water Supply System

    Pipe Size

    Each node was designated an area to which water would be supplied. The total demand for the

    node was determined by the constraints of the designated area such as population and land

    use. The sum of the demand at each node equaled the total demand of the community. The

    distribution system was designed to meet a minimum pressure of 20 psi and a maximum

    pressure of 80 psi. To achieve this standard, pipes were sized from 12 inches in diameter to 16

    inches in diameter. The larger pipes were located closer to the water supply sources (water

    tower and reservoir) because these pipes were required to carry more flow. The standards for

    velocity ranged from 3 fps to 6 fps.

    Pipe Material

    Since all of the pipes were 12 inches to 16 inches in diameter, ductile iron was selected as the

    pipe material. Ductile iron pipes are strong, durable, and resist to corrosion, making them a

    long lasting, reliable selection for a water distribution system. The Hazen-Williams coefficient

    used during design was C=130.

    Water Tower and Reservoir Design

    Part of the community will be supplied with water from an elevated water storage tower. The

    water tower will have a height of 310 feet to meet the pressure requirements for the best-case

    scenario (for when both water tower and reservoir are in operation) and for the worst case

    scenario (for when the pump fails at the reservoir). The volume required for the water tower

    design is based on the max day flow + fire flow assuming the demand is split evenly between

    the water storage tower and the reservoir, which gives 2.75MG required storage. This gallon

    storage will translate to roughly 367,622 cubic feet of storage. The actual water storage unit on

    the tower will have a diameter of 50 feet and a design height of 187 feet. The reservoir should

    also have a storage capacity of 2.75MG, so 367,622 cubic feet as well.

  • Design Proposal 7

    7

    Pump Design

    The pups ee desiged to full suppl the ouits ate dead fo the eseoi. Although the water tower and pump would work together to supply the community on a daily

    basis, it was important to design the system to be able to fulfill needs in the case of water

    tower failure. Pumps were designed based on the TDH of the system (TDHH = 305 ft), the total

    demand (Q = 3606 GPM), and an assumed pump efficiency (= .65). The total horsepower needed 427.28 HP, thus 500 HP pumps were selected. The system was designed with two

    pumps, the second would serve as a standby pump.

    Pump Curve During Best Case Scenario (Everything Working)

    Pump Curve During Water Tower Failure

  • Design Proposal 8

    8

    Fire Hydrant Locations

    Standard regulation requires that the location of all fire hydrants serving the residential and

    commercial zones will be 300 feet apart. For industrial areas, fire hydrants should be located no

    more than 150 feet apart. All fire hydrant locations shown on the following map are located so

    to provide maximum area coverage.

    Fire Hydrant Map

  • Design Proposal 9

    9

    Valves

    Gate valves are located throughout the system with three at each tee junction, four at each

    cross intersection and one at each hydrant. The ensures optimal control of water supply so that

    each pipe can be isolated for any needed maintenance or shut off in the case of emergencies.

    Check valves are to be located alongside gate valves to prevent backflows. This applies to all

    zones for standard practice and the protection of public health. Air relief valves were placed at

    system high points to reduce pressure build-up, while blow-off valves are located at system low

    offs to control sedimentation build-up.

    Gate & Check Valve Map

  • Design Proposal 10

    10

    Sanitary Sewer System Pipe Size

    A gravity system was chosen for separating the wastewater, with the goal of keeping the depth

    in the pipe no greater than 50% of the diameter. The sanitary sewer system was designed to

    handle both process water from industry as well as wastewater from residential and

    commercial zones. This led to a substantial increase in pipe diameter for pipes flowing through

    the main corridor. For smaller pipes a minimum design criteria of 8 inches was chosen.

    However, pipes carrying the main outflow were not calculated based on being half full allowing

    for the diameter to be decreased substantially, following the guidelines in the textbook

    (McGhee). The largest pipe diaete as foud to e ad as loated near the food processing industry, as this represents the largest point source of wastewater in the system.

    Pipe Velocity

    Velocity in the system was designed to maintain a minimum of 2 ft/s in an effort to keep

    suspended solids from settling, while a maximum design velocity of 10 ft/s was chosen to limit

    damage to the pipes. An exception was made for the first few pipes in the system (line numbers

    1-4) which fall below the minimum velocity, due to low flow in the pipes. It was decided that

    the additional cost that would be required to excavate the pipe further, and thus increase

    velocity, would be greater than providing some additional maintenance in the future.

    Pipe Material

    Concrete was chosen as the pipe material since it provides the necessary strength when buried

    at greater depths. For pipes that have a diameter larger than 24 inches reinforced concrete

    (Class II) pipe will be used. Corrosion is a major concern in sanitary sewer systems, in this case it

    is assumed that the location is suitable in terms of temperature and sewage characteristics.

    Normally, clay pipes are superior in terms of corrosion resistance but given the depth of buried

    pipes and large diameter concrete was the best alternative. The roughness (n) for the concrete

    pipes was assumed to be 0.015 resulting in a more conservative calculation.

  • Design Proposal 11

    11

    Pipe Connections

    Pipe joints will be designed using compression rings as recommended for sewage applications.

    This kind of connection allows for less infiltration to occur.

    Figure of Pipe Diameters

    Figure Cross-sectional view of sewer system

  • Design Proposal 12

    12

    Figure Summary of Design Analysis

    Manholes

    Manholes are spaced at 300 to 500 feet along straight segments of the pipe, or where the pipe

    changes in size, direction, or grade. Manholes will be standardized and built with a 24 inch

    opening. The frame will extend down to the bottom of the sewer pipe and rest on brickwork.

    The walls will be 8 inches thick for depths up to 12 feet and an additional 4 in for each

    additional 6 foot drop (McGhee, 2007). Drop manholes will be used where smaller tributary

    sewer branches meet with the mainline. For large drops and high flow areas in the vicinity of

    the industrial and commercial zones horizontal plates will be put into place to reduce the

    kinetic energy of the flowing water. Covers will weigh around 540 pounds to adequately

    support the weight of street traffic.

    * Please see additional sanitary sewer attachment printed separately to maintain formatting

    Pipe Material PVCMin. Velocity 2 ft/sMax Velocity 10 ft/sRoughness (n) 0.015Min Ground Cover 6 ftPercentage Full 50%Min. Pipe Diameter 8 in.Max Pipe Diameter 40 inMax Velocity (Actual) 7.6 ft/sMax Depth 22 ft.

  • Design Proposal 13

    13

    Storm Sewer System

    Municipal Need

    Stormwater management systems are important to the safety and the quality of life of

    residents and businesses. A primary purpose of stormwater systems is to prevent dangerous

    flooding which can disrupt buildings, crops, transportation, and a wide range of other human

    involvement in an urban center. In viewing the model city, it is evident from the municipal

    elevations that Canter Street and Acorn Street will experience a high level of runoff from

    neighboring subcatchments. Residents and businesses along these streets may have to deal

    ith high uoff eloities due to thei steets gadiet o floodig ea thei popet. While environmental and regulatory concerns are important for stormwater management, the

    prevention of damage and destruction from flooding is the primary purpose for an urban

    conveyance system.

    Design Parameters

    For design of the municipal stormwater conveyance system, a number of design criteria were

    considered to safely and efficiently channel stormwater from the city. The following table on

    page 14 outlines criteria that were taken into consideration.

  • Design Proposal 14

    14

    Desig Criteria Value Miiu Value Maiu Flo Velocit ft/s ft/s Slope .% % Depth of Coer ft elo sufae N/A Diaeter ft N/A Roughess Coefficiet N/A N = . Capacit* N/A , . Horizotal Distace fro Drikig Water Lies**

    ft N/A

    Vertical Distace fro Utilities**

    ft

    Pipe Material PVC fo diaete less tha ihes

    Reifoed Coete Pipe fo diaete geate tha ihes

    *atio of flo depth to full depth **fo Haestad Methods, Stoate Coeae Modelig ad Desig

    Desig Restitios Other design considerations to ensure an optimal conveyance system are as follows:

    1) Hydraulic Gradient Lines should be below surface elevation at all times.

    2) Curved storm sewers are unacceptable due to flow and maintenance problems

    3) Depth of cover should be at least 5 ft deep to prevent the crushing of pipes due to loads

    Stormwater Software and Design Methods

    The program used to design the municipal stormwater system was EPA Storm Water

    Management Model (SWMM). The model provided a relatively straightforward process. First,

    the image of the city was able to be added as a backdrop to the program. This made it easier to

    interpret and map the following:

    a) locations of the subcatchments

    b) street and possible conduit locations

  • Design Proposal 15

    15

    c) optimal catch basin locations (for example, basins are best near intersections)

    d its topogaph ad eleatios With this backdrop, the basic structure of the municipal was mapped and ready for

    design. Subcatchments were added for residential and commercial regions, subcatchments

    were plotted, and conduits inserted. Subcatchment area was designed using acres (ac) and

    conduit lengths were designated using (ft). Both area and length were calculated based on the

    fat that o the ap as eual to fo the atual legth. Next, the storm data was inserted using a 5 minute duration interval and an intensity

    curve was drawn based on the data. This storm data allowed the EPA SWMM program to

    calculate all necessary parameters. Once storm data was inserted, simulations were conducted.

    Data was analyzed to ensure design parameters were satisfied. If, for example, pipe capacity

    was greater than 75% or velocity was less than 3 fps, the program issued notifications for the

    conduits that violated design conditions. Conduits which did not meet design conditions

    concerning slope, velocity, diameter, length, capacity, depth of cover, and other pertinent

    factors were specifically designed to ensure a proper stormwater conveyance model.

  • Design Proposal 16

    16

  • Design Proposal 17

    17

    Storm Intensity and Duration Data

    Ratio Flow to Full Flow Parameter

    The following figure is the result of an initial simulation. The parameter being analyzed is the

    ratio of flow to full flow or capacity. Capacity must be less than 75%. The figure shows conduits

    on Canter St. (main trunk), Acorn St., Forest Avenue, and Redwood Street which are causing an

    excessive flow. Excessive flow is a violation of our conveyance design.

    Duration, Min Intensity, In/Hr

    5 7

    10 5.5

    15 5

    20 4.3

    25 3.9

    30 3.75

    35 3.5

    40 3.35

    45 3.2

    50 3.15

    55 3.125

    60 3.1

  • Design Proposal 18

    18

    Fig. Notes: all coduit diaetes set to . Red coduits idicatig isufficiet pipe sizes that ae causing overcapacity. Figure shows ratio of flow to full flow. Capacity is unitless.

    Once the conduits which did not satisfy design parameters were found, they were

    incrementally changed to meet design. Conduits were enlarged to the next commercially

    available size. Twelve-inch pipes ee adjusted to to eet desig. If desig as ot satisfied, it as adjusted to the the ad so and so forth until capacity was met. Theefoe, ou a diaete as o . The folloig shos the atios of flo afte pipe sizes were adjusted:

  • Design Proposal 19

    19

    Fig. Notes: Ratio of flow to full flow after all pipe diameters were adjusted.

    75% Flow Satisfied.

    Minimum Slope Parameter

    The following figure shows the result of simulation with slope as a parameter. The design

    specifications indicate that the slope of our system must be greater than 0.2% and the

    American Society of Civil Engineers (ASCE) recommends a storm sewer slope of no greater than

    10%. Originally, some conduits violated the slope condition; certain links were less than 0.2%

    which makes flow difficult in some links. To correct for this, elevations of nodes and conduits

    were adjusted to ensure a proper slope. For example, for the main trunk which included Canter

    St., the conduit had to be buried deeper or the depth of cover had to decrease for downstream

    conduits. In other words, the gradient between upper manhole and lower manhole was

    increased by lower the invert elevation of the lower manhole. This ensured that pipe slopes

    were accurate. The following figure indicates the slopes of all pipes in the system.

  • Design Proposal 20

    20

    Fig. Notes: all pipe slopes are satisfied. All gradients between upper manhole and lower

    manhole have proper slope to allow for sufficient flow. Minimum 0.2% slope satisfied.

    Minimum Velocity Parameter

    The following simulation shows the velocities in each conduit. Units are feet per second. The

    design criteria specified are to ensure that velocity is greater than 3 fps and lower than 15 fps.

    The max velocity (15 fps) is recommended by the ASCE. To increase velocity, other parameters

    such as conduit slope, elevation, and diameter were adjusted to increase or in some instances

    decrease velocity. For example, velocity in the conduit lining Forest Avenue was at around 20

    fps during one simulation. Twenty-feet per second velocity can cause problems for

    maintenance and conduit upkeep. The following figure indicates the velocity in all pipes in the

    system.

  • Design Proposal 21

    21

    Fig. Notes: Velocities of all pipes in the system. Units are in feet per second (fps). Greater

    velocities occur at lower elevations (main trunk). Minimum velocity of 3 fps in each conduit

    satisfied.

    Minimum Diameter and Materials Parameters

    The following simulation shows the pipe diameters in the system. The design parameters

    speif that the iiu pipe size i the oeae sste should e . The speifiatios also state that Polyvinyl Chloride (PVC) pipes should be used for sizes less tha ad Reifoed Coete Pipes RCP should e used fo sizes geate tha . Theefoe, the conduits that are on the main trunk should be made with reinforced concrete while the lateral

    lies that hae diaetes of should e desiged ith PVC material. It is important to note that many engineers state that pipe diameters should increase or remain constant as flow

    moves downstream. If pipe diameter decreases than creates differences in pressure, velocity,

    and flow. For example, the conduit on Canter St. shows a 3 ft conduit transitioning into a 1 ft

    conduit. As flow is moving downstream, this 3 ft to 1 ft decrease will increase velocity and flow

    which can be problematic for the system.

  • Design Proposal 22

    22

    Fig. Notes: All pipes show conduit diameter in feet ft. Lagest diaete is o ft. Minimum diaete of is satisfied.

    Hydraulic Profiles

  • Design Proposal 23

    23

  • Design Proposal 24

    24

    Summary of Results

    Pipe Material

    PVC or Reinforced Concrete

    (D>18'')

    Min. Velocity 3.72 fps

    Max. Velocity 12.3 fps

    Roughness n=0.013

    Min Ground Cover 5 ft

    Max Capacity 75% fullness

    Min. Pipe Diameter 12 inches

    Max. Pipe Diameter 36 inches

    Max Depth 22 ft

  • Design Proposal 25

    25

    Utility Cross Section

    The storm and sewer lines were spaced 6 ft horizontally from the water distribution line with 1

    ft and 2 ft of vertical clearance, respectively. This distance protects each line from cross-

    contamination and facilitates maintenance. The water distribution was given 3 ft of cover to

    reduce live loading, while the storm line has an average cover of 5 ft. The six foot depth of the

    sewer line minimizes risk of overflow of the pipeline onto the surface in the event of rupture or

    damage to the pipeline. Please note that while the sewer and storm pipes are depicted as

    flowing full in the cross section figure, they flow at 50% and 75% full, respectively, in the

    designs.

  • Design Proposal 26

    26

    Works Cited

    George, Ron. "Estimating Cold Water Demand for Buildings." 2011. Web. .

    "Guide for Determination of Needed Fire Flow." Www.ecs.umass.edu. ISO Properties, Apr.

    2008. Web. 15 Mar. 2013.

    "Water and Wastewater Use in the Food Processing Industry." Knowledge Industry. North

    Carolina Department of Environment and Natural Resources, 6 July 2010. Web. 2 Apr. 2013.

    .

  • Design Proposal 27

    27

    Appendix

    Water demand calculations:

    Residential Area: 2887215.2 ft^2 = 66.281 acres Residential population density = 40 people/acre Populatio = .* = . people Average Consumption = 100 gal/capita-day Maximum day consumption = 200% avg daily consumption Maximum hour consumption = 400% avg daily consumption Residential average consumption = 2.652*10^5 gpd Residential maximum day consumption = 5.304*10^5 gpd Residential maximum hour consumption = 1.0608*10^6 gpd A= 143230 ft^2 B= 142500 ft^2 C=90000 ft^2

    Industrial Area: 143230 ft^2*(1 acre/43560ft^2) =3.2881 acres Idustial populatio desit = people/ae = . people Average Consumption = 2,000 gpm for 8 hrs on weekdays (no other consumption) Peak hourly consumption in any hour (?) = 3,000 gpm Industrial consumption on weekday (8 hr period) = 3000 gpm*60 min/hr*8hr = 1.44*10^6 gal Industrial peak hour consumption = 3,000 gpm*60 = 1.8*10^5 gal

    Commercial zone Shopping Center Area: B+C = 142500+90000 = 232500 ft^2*(1 acre/43560ft^2) =5.3375 acres Industrial Area: 143230 ft^2*(1 acre/43560ft^2) =3.2881 acres Use: 10 hours per day Visitors: 15% of population visits the shopping center per day. 0.15*2652 = 398 visitors per day Employees: 50 people per day Water consumption for customers per day = customers per day x 1.25 gallons per day per customer

    = 398*1.25= 497.5 gpd/customer Water consumption for employees = numbers of employees per day x 20 gallons per day per

    employee = 50*200= 10,000gpd/employee Total=10,497.5 gpd Average flow rate = total gallons per day/ 600 minutes per day = avg flow rate = 10,497.5/600= 17.5

    gpm

  • Design Proposal 28

    28

    Peak day flow rate = average flow rate x 2 = 35 gpm

    Water Supply Network Demand, Head, and Pressure:

    Pump and Water Tower Working:

    Network Table - Nodes

    Demand Head Pressure

    Node ID GPM ft psi

    Junc 7 7.89 303.06 41.58

    Junc 6 7.34 303.08 41.11

    Junc 5 6.33 303.15 40.36

    Junc 3 7.89 304.58 32.75

    Junc 4 6.19 303.53 37.06

    Junc 11 7.43 303.23 39.92

    Junc 15 5.76 302.91 41.99

    Junc 13 574.2 302.91 40.39

    Junc 9 7.19 303.23 39.1

    Junc 14 571.24 302.88 40.89

    Junc 18 571.46 302.85 43.31

    Junc 19 3.83 302.88 43.88

    Junc 28 571.79 302.89 43.67

    Junc 30 11.37 303.02 43.12

    Junc 31 6.57 303.03 42

    Junc 21 5.54 303.04 41.4

    Junc 20 5.54 303.04 41.4

    Junc 12 571.36 302.99 40.16

    Junc 26 574.08 303.03 42.82

    Junc 27 3.29 302.96 42.97

    Junc 10 8.64 303.23 39.1

    Junc 25 3.46 303.33 43.3

    Junc 17 3.82 303.35 42.83

    Junc 16 4.25 303.45 44.17

    Junc 23 4.34 303.54 43.78

    Junc 22 5.12 303.71 45.59

    Junc 33 6.69 303.9 40.17

    Junc 39 5.11 303.02 41.69

    Junc 38 4.19 303.05 41.19

    Junc 29 5.7 302.98 43.62

    Junc 37 4.35 303.14 40.88

    Junc 36 2.93 303.33 41.22

    Junc 24 1.98 303.42 42.86

    Junc 35 2.18 303.44 41.27

  • Design Proposal 29

    29

    Junc 34 5.12 303.67 40.59

    Junc 40 6.72 303.02 41.61

    Junc 8 2.83 303.05 41.97

    Junc 32 2.38 303.04 42

    Resvr 1 -1973.35 310 0

    Resvr 2 -1632.76 305 0

    Pump Failure

    Network Table - Nodes

    Demand Head Pressure

    Node ID GPM ft psi

    Junc 7 7.89 288.83 35.41

    Junc 6 7.34 288.92 34.98

    Junc 5 6.33 289.21 34.32

    Junc 3 7.89 293.44 27.92

    Junc 4 6.19 290.39 31.36

    Junc 11 7.43 288.98 33.74

    Junc 15 5.76 288.66 35.82

    Junc 13 574.2 288.67 34.22

    Junc 9 7.19 288.95 32.91

    Junc 14 571.24 288.62 34.72

    Junc 18 571.46 288.48 37.08

    Junc 19 3.83 288.5 37.65

    Junc 28 571.79 288.49 37.43

    Junc 30 11.37 288.65 36.9

    Junc 31 6.57 288.73 35.8

    Junc 21 5.54 288.74 35.2

    Junc 20 5.54 288.76 35.21

    Junc 12 571.36 288.69 33.97

    Junc 26 574.08 288.5 36.53

    Junc 27 3.29 288.5 36.7

    Junc 10 8.64 288.95 32.91

    Junc 25 3.46 288.55 36.89

    Junc 17 3.82 288.58 36.43

    Junc 16 4.25 288.56 37.72

    Junc 23 4.34 288.55 37.29

    Junc 22 5.12 288.55 39.02

    Junc 33 6.69 288.55 33.51

    Junc 39 5.11 288.56 35.43

    Junc 38 4.19 288.54 34.9

    Junc 29 5.7 288.57 37.38

    Junc 37 4.35 288.54 34.55

  • Design Proposal 30

    30

    Junc 36 2.93 288.54 34.81

    Junc 24 1.98 288.55 36.42

    Junc 35 2.18 288.55 34.81

    Junc 34 5.12 288.55 34.03

    Junc 40 6.72 288.58 35.35

    Junc 8 2.83 288.81 35.79

    Junc 32 2.38 288.74 35.81

    Resvr 1 -3606.11 310 0

    Water Tower Failure

    Network Table - Nodes

    Demand Head Pressure

    Node ID GPM ft psi

    Junc 7 7.89 296.14 38.58

    Junc 6 7.34 296.12 38.1

    Junc 5 6.33 296.08 37.3

    Junc 3 7.89 296.1 29.08

    Junc 4 6.19 296.07 33.83

    Junc 11 7.43 296.19 36.87

    Junc 15 5.76 296.01 39

    Junc 13 574.2 295.97 37.38

    Junc 9 7.19 296.28 36.08

    Junc 14 571.24 295.97 37.9

    Junc 18 571.46 296 40.34

    Junc 19 3.83 296.03 40.92

    Junc 28 571.79 296.12 40.74

    Junc 30 11.37 296.18 40.16

    Junc 31 6.57 296.16 39.02

    Junc 21 5.54 296.15 38.41

    Junc 20 5.54 296.15 38.41

    Junc 12 571.36 296.08 37.17

    Junc 26 574.08 296.74 40.1

    Junc 27 3.29 296.41 40.13

    Junc 10 8.64 296.28 36.08

    Junc 25 3.46 297.73 40.87

    Junc 17 3.82 297.73 40.4

    Junc 16 4.25 298.22 41.91

    Junc 23 4.34 298.63 41.65

    Junc 22 5.12 299.42 43.73

    Junc 33 6.69 300.23 38.58

    Junc 39 5.11 296.39 38.82

    Junc 38 4.19 296.61 38.4

    Junc 29 5.7 296.18 40.68

  • Design Proposal 31

    31

    Junc 37 4.35 297.03 38.23

    Junc 36 2.93 297.76 38.81

    Junc 24 1.98 298.12 40.56

    Junc 35 2.18 298.25 39.02

    Junc 34 5.12 299.24 38.67

    Junc 40 6.72 296.35 38.71

    Junc 8 2.83 296.14 38.97

    Junc 32 2.38 296.15 39.02

    Resvr 2 -3606.11 305 0

    Pump Design

    HP=QxH/(3960*n)

    Q= 3606 GPM

    H=305ft

    n=65%

    HP= 427.28 HP (500 HP pump needed)

    Stormwater Results:

    EPA STORM WATER MANAGEMENT MODEL - VERSION 5.0 (Build 5.0.022)

    --------------------------------------------------------------

    *********************************************************

    NOTE: The summary statistics displayed in this report are

    based on results found at every computational time step,

    not just on results from each reporting time step.

    *********************************************************

    ****************

    Analysis Options

    ****************

    Flow Units ............... CFS

    Process Models:

    Rainfall/Runoff ........ YES

    Snowmelt ............... NO

    Groundwater ............ NO

    Flow Routing ........... YES

    Ponding Allowed ........ YES

    Water Quality .......... NO

    Infiltration Method ...... CURVE_NUMBER

    Flow Routing Method ...... KINWAVE

    Starting Date ............ MAR-18-2013 00:01:00

    Ending Date .............. MAR-18-2013 01:00:00

    Antecedent Dry Days ...... 0.0

  • Design Proposal 32

    32

    Report Time Step ......... 00:59:00

    Wet Time Step ............ 00:05:00

    Dry Time Step ............ 01:00:00

    Routing Time Step ........ 30.00 sec

    *************

    Element Count

    *************

    Number of rain gages ...... 2

    Number of subcatchments ... 38

    Number of nodes ........... 42

    Number of links ........... 40

    Number of pollutants ...... 0

    Number of land uses ....... 0

    ****************

    Raingage Summary

    ****************

    Data Recording

    Name Data Source Type Interval

    -------------------------------------------------------------

    northwest SampleStorm INTENSITY 5 min.

    northeast SampleStorm INTENSITY 5 min.

    ********************

    Subcatchment Summary

    ********************

    Name Area Width %Imperv %Slope Rain Gage Outlet

    -------------------------------------------------------------------------------------------------------

    Ash 2.85 300.00 25.00 0.5000 northwest Ash1

    ash_east 2.65 350.00 25.00 0.5000 northwest acorn1

    sycamore_west 1.61 500.00 25.00 0.5000 northwest sycamore

    sycamore_east 1.47 500.00 25.00 0.5000 northwest acorn2

    forest_west 1.51 500.00 25.00 0.5000 northwest forest

    forest_east 1.57 500.00 25.00 0.5000 northwest acorn3

    cedar_west 2.70 350.00 25.00 0.5000 northwest cedar1

    cedar_east 2.11 300.00 25.00 0.5000 northwest cedar2

    elm_sw 1.92 200.00 25.00 0.5000 northwest forest1

    elm_se 0.23 100.00 25.00 0.5000 northeast forest2

    birch_west 1.74 200.00 25.00 0.5000 northwest birch1

    birch_east 1.66 200.00 25.00 0.5000 northeast canter4

    66 0.82 300.00 25.00 0.5000 northeast canter2

    elm_west 1.48 200.00 25.00 0.5000 northwest elm

    elm_east 1.31 200.00 25.00 0.5000 northeast elm1

    69 2.47 300.00 25.00 0.5000 northwest oak

  • Design Proposal 33

    33

    70 0.93 300.00 25.00 0.5000 northeast oak3

    71 2.30 300.00 25.00 0.5000 northwest oak2

    72 1.60 300.00 25.00 0.5000 northwest maple1

    73 1.91 300.00 25.00 0.5000 northwest maple2

    74 1.40 400.00 25.00 0.5000 northwest maple3

    75 2.03 300.00 25.00 0.5000 northwest main1

    76 1.88 300.00 25.00 0.5000 northwest main2

    77 1.25 100.00 25.00 0.5000 northwest main3

    78 2.35 400.00 25.00 0.5000 northeast canter8

    79 2.17 400.00 25.00 0.5000 northeast maple4

    82 1.53 250.00 25.00 0.5000 northeast walnut1

    83 1.49 250.00 25.00 0.5000 northeast walnut

    84 1.02 200.00 25.00 0.5000 northeast forest3

    85 1.31 200.00 25.00 0.5000 northeast forest4

    86 2.07 200.00 25.00 0.5000 northeast birch

    87 0.64 50.00 25.00 0.5000 northeast cedar

    88 0.79 150.00 25.00 0.5000 northeast ashmount

    89 0.75 150.00 25.00 0.5000 northeast aspen1

    90 0.46 200.00 25.00 0.5000 northeast ashmount0

    93 1.77 400.00 25.00 0.5000 northeast canter1

    94 1.65 300.00 25.00 0.5000 northeast ashmount1

    98 3.02 100.00 25.00 0.5000 northeast 155

    ************

    Node Summary

    ************

    Invert Max. Ponded

    Name Type Elev. Depth Area

    ------------------------------------------------------------------------------

    Ash1 JUNCTION 210.00 1.00 0.0

    acorn1 JUNCTION 205.00 1.00 0.0

    acorn2 JUNCTION 202.00 1.75 0.0

    sycamore JUNCTION 205.00 1.00 0.0

    forest JUNCTION 205.50 1.00 0.0

    acorn3 JUNCTION 200.00 2.25 0.0

    cedar1 JUNCTION 213.00 1.00 0.0

    cedar2 JUNCTION 201.60 1.00 0.0

    canter2 JUNCTION 196.00 3.00 0.0

    ashmount1 JUNCTION 206.00 1.00 0.0

    canter4 JUNCTION 195.00 1.00 0.0

    birch1 JUNCTION 201.20 1.00 0.0

    canter5 JUNCTION 191.00 2.25 0.0

    forest4 JUNCTION 201.70 1.00 0.0

  • Design Proposal 34

    34

    walnut1 JUNCTION 201.20 1.00 0.0

    forest1 JUNCTION 198.00 2.25 0.0

    maple4 JUNCTION 180.00 2.75 0.0

    canter8 JUNCTION 184.00 2.75 0.0

    maple2 JUNCTION 197.00 1.00 0.0

    maple1 JUNCTION 203.60 1.00 0.0

    oak2 JUNCTION 198.00 1.00 0.0

    aspen1 JUNCTION 205.00 1.00 0.0

    main1 JUNCTION 207.00 1.00 0.0

    main2 JUNCTION 203.00 1.25 0.0

    main3 JUNCTION 200.00 1.25 0.0

    acorn JUNCTION 204.00 1.50 0.0

    canter1 JUNCTION 200.00 3.00 0.0

    cedar JUNCTION 199.00 1.00 0.0

    birch JUNCTION 202.00 1.00 0.0

    forest3 JUNCTION 194.00 1.00 0.0

    elm1 JUNCTION 193.00 2.25 0.0

    forest2 JUNCTION 195.00 2.00 0.0

    oak JUNCTION 202.00 1.00 0.0

    oak3 JUNCTION 186.00 2.25 0.0

    maple3 JUNCTION 188.00 1.50 0.0

    ashmount0 JUNCTION 201.50 1.00 0.0

    ashmount JUNCTION 203.00 1.00 0.0

    walnut JUNCTION 189.00 1.00 0.0

    elm JUNCTION 201.00 1.00 0.0

    154 JUNCTION 205.00 1.00 0.0

    155 JUNCTION 195.00 1.00 0.0

    outfall OUTFALL 175.00 2.75 0.0

    ************

    Link Summary

    ************

    Name From Node To Node Type Length %Slope Roughness

    ------------------------------------------------------------------------------------------

    ash2 Ash1 acorn1 CONDUIT 472.0 1.0594 0.0130

    acorn3 acorn2 acorn3 CONDUIT 300.0 0.6667 0.0130

    canter1 canter2 canter5 CONDUIT 200.0 2.5008 0.0130

    maple4 canter8 maple4 CONDUIT 400.0 1.0001 0.0130

    sycamore sycamore acorn2 CONDUIT 472.0 0.6356 0.0130

    forest forest acorn3 CONDUIT 380.0 1.4475 0.0130

    cedar cedar2 canter2 CONDUIT 400.0 1.4001 0.0130

    forest1 acorn3 forest1 CONDUIT 600.0 0.3333 0.0130

    aspen aspen1 canter2 CONDUIT 370.0 2.4332 0.0130

  • Design Proposal 35

    35

    birch birch1 canter4 CONDUIT 500.0 1.2401 0.0130

    maple maple1 maple2 CONDUIT 600.0 1.1001 0.0130

    main2 main2 main3 CONDUIT 500.0 0.6000 0.0130

    main3 main3 maple4 CONDUIT 450.0 4.4488 0.0130

    acorn cedar1 acorn CONDUIT 200.0 4.5046 0.0130

    acorn1 acorn acorn2 CONDUIT 240.0 0.8334 0.0130

    61 acorn1 acorn CONDUIT 65.0 1.5386 0.0100

    cedar1 cedar canter2 CONDUIT 50.0 6.0108 0.0130

    birch1 birch canter4 CONDUIT 90.0 7.8014 0.0130

    elm3 forest4 forest3 CONDUIT 240.0 3.2100 0.0130

    elm2 forest3 canter5 CONDUIT 50.0 6.0108 0.0130

    elm1 elm1 canter5 CONDUIT 400.0 0.5000 0.0130

    forest2 forest1 forest2 CONDUIT 80.0 3.7526 0.0130

    oak oak oak2 CONDUIT 320.0 1.2501 0.0130

    oak1 oak2 oak3 CONDUIT 525.0 2.2863 0.0130

    maple1 maple2 maple3 CONDUIT 375.0 2.4007 0.0130

    maple3 maple3 canter8 CONDUIT 75.0 5.3409 0.0130

    ashmount2 ashmount0 canter2 CONDUIT 400.0 1.3751 0.0130

    canter canter1 canter2 CONDUIT 370.0 1.0811 0.0130

    ashmount ashmount1 ashmount CONDUIT 300.0 1.0001 0.0130

    ashmount1 ashmount canter1 CONDUIT 50.0 6.0108 0.0130

    forest3 forest2 elm1 CONDUIT 180.0 1.1112 0.0130

    walnut walnut1 walnut CONDUIT 400.0 3.0514 0.0130

    elm elm elm1 CONDUIT 380.0 2.1057 0.0130

    oak2 oak3 canter8 CONDUIT 370.0 0.5405 0.0130

    canter2 canter5 canter8 CONDUIT 600.0 1.1667 0.0130

    110 walnut canter8 CONDUIT 400.0 1.2501 0.0100

    outfall maple4 outfall CONDUIT 400.0 1.2501 0.0130

    113 main1 154 CONDUIT 325.0 0.6154 0.0130

    114 154 main2 CONDUIT 325.0 0.6154 0.0130

    117 155 oak3 CONDUIT 100.0 9.0367 0.0130

    *********************

    Cross Section Summary

    *********************

    Full Hyd. Max. No. of Full

    Conduit Shape Depth Area Rad. Width Barrels Flow

    ---------------------------------------------------------------------------------------

    ash2 CIRCULAR 1.00 0.79 0.25 1.00 1 3.67

    acorn3 CIRCULAR 1.75 2.41 0.44 1.75 1 12.94

    canter1 CIRCULAR 1.50 1.77 0.38 1.50 1 16.61

    maple4 CIRCULAR 2.75 5.94 0.69 2.75 1 52.89

    sycamore CIRCULAR 1.00 0.79 0.25 1.00 1 2.84

  • Design Proposal 36

    36

    forest CIRCULAR 1.00 0.79 0.25 1.00 1 4.29

    cedar CIRCULAR 1.00 0.79 0.25 1.00 1 4.22

    forest1 CIRCULAR 2.25 3.98 0.56 2.25 1 17.88

    aspen CIRCULAR 1.00 0.79 0.25 1.00 1 5.56

    birch CIRCULAR 1.00 0.79 0.25 1.00 1 3.97

    maple CIRCULAR 1.00 0.79 0.25 1.00 1 3.74

    main2 CIRCULAR 1.25 1.23 0.31 1.25 1 5.00

    main3 CIRCULAR 1.00 0.79 0.25 1.00 1 7.51

    acorn CIRCULAR 1.00 0.79 0.25 1.00 1 7.56

    acorn1 CIRCULAR 1.50 1.77 0.38 1.50 1 9.59

    61 CIRCULAR 1.00 0.79 0.25 1.00 1 5.75

    cedar1 CIRCULAR 1.00 0.79 0.25 1.00 1 8.73

    birch1 CIRCULAR 1.00 0.79 0.25 1.00 1 9.95

    elm3 CIRCULAR 1.00 0.79 0.25 1.00 1 6.38

    elm2 CIRCULAR 1.00 0.79 0.25 1.00 1 8.73

    elm1 CIRCULAR 2.25 3.98 0.56 2.25 1 21.90

    forest2 CIRCULAR 2.00 3.14 0.50 2.00 1 43.82

    oak CIRCULAR 1.00 0.79 0.25 1.00 1 3.98

    oak1 CIRCULAR 1.00 0.79 0.25 1.00 1 5.39

    maple1 CIRCULAR 1.00 0.79 0.25 1.00 1 5.52

    maple3 CIRCULAR 1.50 1.77 0.38 1.50 1 24.28

    ashmount2 CIRCULAR 1.00 0.79 0.25 1.00 1 4.18

    canter CIRCULAR 3.00 7.07 0.75 3.00 1 69.35

    ashmount CIRCULAR 1.00 0.79 0.25 1.00 1 3.56

    ashmount1 CIRCULAR 1.00 0.79 0.25 1.00 1 8.73

    forest3 CIRCULAR 1.75 2.41 0.44 1.75 1 16.70

    walnut CIRCULAR 1.00 0.79 0.25 1.00 1 6.22

    elm CIRCULAR 1.00 0.79 0.25 1.00 1 5.17

    oak2 CIRCULAR 2.25 3.98 0.56 2.25 1 22.77

    canter2 CIRCULAR 2.25 3.98 0.56 2.25 1 33.45

    110 CIRCULAR 1.00 0.79 0.25 1.00 1 5.18

    outfall CIRCULAR 2.75 5.94 0.69 2.75 1 59.13

    113 CIRCULAR 1.00 0.79 0.25 1.00 1 2.79

    114 CIRCULAR 1.00 0.79 0.25 1.00 1 2.79

    117 CIRCULAR 1.00 0.79 0.25 1.00 1 10.71

    *********************

    Control Actions Taken

    *********************

    *********************** Volume Depth

    Runoff Quantity Continuity acre-feet inches

    ************************** --------- -------

    Total Precipitation ...... 19.846 3.815

    Evaporation Loss ......... 0.000 0.000

  • Design Proposal 37

    37

    Infiltration Loss ........ 14.279 2.745

    Surface Runoff ........... 4.995 0.960

    Final Surface Storage .... 0.775 0.149

    Continuity Error (%) ..... -1.023

    ***********************Volume Volume

    Flow Routing Continuity acre-feet 10^6 gal

    ************************** --------- ---------

    Dry Weather Inflow ....... 0.000 0.000

    Wet Weather Inflow ....... 4.778 1.557

    Groundwater Inflow ....... 0.000 0.000

    RDII Inflow .............. 0.000 0.000

    External Inflow .......... 0.000 0.000

    External Outflow ......... 4.184 1.363

    Internal Outflow ......... 0.407 0.133

    Storage Losses ........... 0.000 0.000

    Initial Stored Volume .... 0.000 0.000

    Final Stored Volume ...... 0.297 0.097

    Continuity Error (%) ..... -2.281

    ********************************

    Highest Flow Instability Indexes

    ********************************

    Link outfall (13)

    Link forest2 (10)

    Link canter2 (9)

    Link acorn3 (9)

    Link elm1 (8)

    *************************

    Routing Time Step Summary

    *************************

    Minimum Time Step : 30.00 sec

    Average Time Step : 30.00 sec

    Maximum Time Step : 30.00 sec

    Percent in Steady State : 0.00

    Average Iterations per Step : 3.36

    ***************************

    Subcatchment Runoff Summary

  • Design Proposal 38

    38

    ***************************

    --------------------------------------------------------------------------------------------------------

    Total Total Total Total Total Total Peak Runoff

    Precip Runon Evap Infil Runoff Runoff Runoff Coeff

    Subcatchment in in in in in 10^6 gal CFS

    --------------------------------------------------------------------------------------------------------

    Ash 3.81 0.00 0.00 2.74 0.95 0.07 4.68 0.250

    ash_east 3.81 0.00 0.00 2.74 0.96 0.07 4.48 0.251

    sycamore_west 3.81 0.00 0.00 2.74 0.97 0.04 2.83 0.255

    sycamore_east 3.81 0.00 0.00 2.74 0.97 0.04 2.59 0.256

    forest_west 3.81 0.00 0.00 2.74 0.97 0.04 2.66 0.255

    forest_east 3.81 0.00 0.00 2.74 0.97 0.04 2.76 0.255

    cedar_west 3.81 0.00 0.00 2.74 0.96 0.07 4.56 0.251

    cedar_east 3.81 0.00 0.00 2.74 0.96 0.06 3.60 0.252

    elm_sw 3.81 0.00 0.00 2.74 0.95 0.05 3.14 0.250

    elm_se 3.81 0.00 0.00 2.74 0.98 0.01 0.41 0.257

    birch_west 3.81 0.00 0.00 2.74 0.96 0.05 2.90 0.251

    birch_east 3.81 0.00 0.00 2.74 0.96 0.04 2.78 0.251

    66 3.81 0.00 0.00 2.74 0.98 0.02 1.45 0.256

    elm_west 3.81 0.00 0.00 2.74 0.96 0.04 2.51 0.252

    elm_east 3.81 0.00 0.00 2.74 0.96 0.03 2.25 0.252

    69 3.81 0.00 0.00 2.74 0.96 0.06 4.14 0.251

    70 3.81 0.00 0.00 2.74 0.97 0.02 1.64 0.255

    71 3.81 0.00 0.00 2.74 0.96 0.06 3.89 0.251

    72 3.81 0.00 0.00 2.74 0.97 0.04 2.79 0.253

    73 3.81 0.00 0.00 2.74 0.96 0.05 3.28 0.252

    74 3.81 0.00 0.00 2.74 0.97 0.04 2.46 0.255

    75 3.81 0.00 0.00 2.74 0.96 0.05 3.47 0.252

    76 3.81 0.00 0.00 2.74 0.96 0.05 3.23 0.252

    77 3.81 0.00 0.00 2.74 0.95 0.03 1.95 0.248

    78 3.81 0.00 0.00 2.74 0.96 0.06 4.07 0.253

    79 3.81 0.00 0.00 2.74 0.97 0.06 3.77 0.253

    82 3.81 0.00 0.00 2.74 0.96 0.04 2.63 0.253

    83 3.81 0.00 0.00 2.74 0.96 0.04 2.57 0.253

    84 3.81 0.00 0.00 2.74 0.97 0.03 1.78 0.253

    85 3.81 0.00 0.00 2.74 0.96 0.03 2.24 0.252

    86 3.81 0.00 0.00 2.74 0.95 0.05 3.35 0.250

    87 3.81 0.00 0.00 2.74 0.95 0.02 0.99 0.248

    88 3.81 0.00 0.00 2.74 0.97 0.02 1.37 0.253

    89 3.81 0.00 0.00 2.74 0.97 0.02 1.31 0.253

    90 3.81 0.00 0.00 2.74 0.98 0.01 0.81 0.257

    93 3.81 0.00 0.00 2.74 0.97 0.05 3.10 0.254

    94 3.81 0.00 0.00 2.74 0.96 0.04 2.86 0.253

  • Design Proposal 39

    39

    98 3.81 0.00 0.00 2.74 0.91 0.07 4.04 0.239

    ******************

    Node Depth Summary

    ******************

    ---------------------------------------------------------------------

    Average Min Max Time of Max

    Depth Depth HGL Occurrence

    Node Type Feet Feet Feet days hr:min

    ---------------------------------------------------------------------

    Ash1 JUNCTION 0.64 1.00 211.00 0 00:09

    acorn1 JUNCTION 0.73 1.00 206.00 0 00:09

    acorn2 JUNCTION 1.18 1.75 203.75 0 00:10

    sycamore JUNCTION 0.51 0.82 205.82 0 00:10

    forest JUNCTION 0.38 0.57 206.07 0 00:10

    acorn3 JUNCTION 1.37 2.25 202.25 0 00:10

    cedar1 JUNCTION 0.38 0.56 213.56 0 00:10

    cedar2 JUNCTION 0.46 0.71 202.31 0 00:10

    canter2 JUNCTION 0.72 1.10 197.10 0 00:11

    ashmount1 JUNCTION 0.44 0.68 206.68 0 00:10

    canter4 JUNCTION 0.92 1.00 196.00 0 00:05

    birch1 JUNCTION 0.43 0.63 201.83 0 00:10

    canter5 JUNCTION 1.52 2.25 193.25 0 00:11

    forest4 JUNCTION 0.28 0.41 202.11 0 00:10

    walnut1 JUNCTION 0.31 0.45 201.65 0 00:10

    forest1 JUNCTION 1.32 1.88 199.88 0 00:12

    maple4 JUNCTION 1.95 2.75 182.75 0 00:12

    canter8 JUNCTION 1.92 2.75 186.75 0 00:11

    maple2 JUNCTION 0.54 1.00 198.00 0 00:11

    maple1 JUNCTION 0.42 0.64 204.24 0 00:10

    oak2 JUNCTION 0.70 1.00 199.00 0 00:09

    aspen1 JUNCTION 0.23 0.33 205.33 0 00:10

    main1 JUNCTION 0.61 1.00 208.00 0 00:09

    main2 JUNCTION 0.80 1.25 204.25 0 00:10

    main3 JUNCTION 0.75 1.14 201.14 0 00:21

    acorn JUNCTION 0.97 1.50 205.50 0 00:09

    canter1 JUNCTION 0.46 0.65 200.65 0 00:11

    cedar JUNCTION 0.17 0.23 199.23 0 00:10

    birch JUNCTION 0.28 0.40 202.40 0 00:10

    forest3 JUNCTION 0.32 0.47 194.47 0 00:10

    elm1 JUNCTION 1.40 2.25 195.25 0 00:12

    forest2 JUNCTION 1.36 2.00 197.00 0 00:11

    oak JUNCTION 0.54 1.00 203.00 0 00:10

  • Design Proposal 40

    40

    oak3 JUNCTION 0.86 1.09 187.09 0 00:10

    maple3 JUNCTION 0.53 0.88 188.88 0 00:13

    ashmount0 JUNCTION 0.21 0.30 201.80 0 00:10

    ashmount JUNCTION 0.44 0.66 203.66 0 00:11

    walnut JUNCTION 0.51 0.80 189.80 0 00:10

    elm JUNCTION 0.34 0.49 201.49 0 00:10

    154 JUNCTION 0.60 1.00 206.00 0 00:10

    155 JUNCTION 0.33 0.43 195.43 0 00:15

    outfall OUTFALL 1.80 2.40 177.40 0 00:25

    *******************

    Node Inflow Summary

    *******************

    -------------------------------------------------------------------------------------

    Max Max Lateral Total

    Lateral Total Time of Max Inflow Inflow

    Inflow Inflow Occurrence Volume Volume

    Node Type CFS CFS D/HR/MIN 10^6 gal 10^6 gal

    -------------------------------------------------------------------------------------

    Ash1 JUNCTION 4.68 4.68 0 00:10 0.071 0.071

    acorn1 JUNCTION 4.48 8.29 0 00:11 0.066 0.134

    acorn2 JUNCTION 2.59 14.92 0 00:11 0.037 0.264

    sycamore JUNCTION 2.83 2.83 0 00:10 0.041 0.041

    forest JUNCTION 2.66 2.66 0 00:10 0.038 0.038

    acorn3 JUNCTION 2.76 19.07 0 00:11 0.040 0.333

    cedar1 JUNCTION 4.56 4.56 0 00:10 0.068 0.067

    cedar2 JUNCTION 3.60 3.60 0 00:10 0.053 0.053

    canter2 JUNCTION 1.45 14.75 0 00:11 0.021 0.221

    ashmount1 JUNCTION 2.86 2.86 0 00:10 0.042 0.041

    canter4 JUNCTION 2.78 8.63 0 00:11 0.041 0.135

    birch1 JUNCTION 2.90 2.90 0 00:10 0.043 0.043

    canter5 JUNCTION 0.00 39.84 0 00:12 0.000 0.689

    forest4 JUNCTION 2.24 2.24 0 00:10 0.033 0.033

    walnut1 JUNCTION 2.63 2.63 0 00:10 0.038 0.038

    forest1 JUNCTION 3.14 21.11 0 00:12 0.048 0.370

    maple4 JUNCTION 3.77 66.80 0 00:12 0.055 1.252

    canter8 JUNCTION 4.07 62.72 0 00:13 0.059 1.123

    maple2 JUNCTION 3.28 5.66 0 00:11 0.048 0.087

    maple1 JUNCTION 2.79 2.79 0 00:10 0.040 0.040

    oak2 JUNCTION 3.89 7.86 0 00:11 0.058 0.118

    aspen1 JUNCTION 1.31 1.31 0 00:10 0.019 0.019

    main1 JUNCTION 3.47 3.47 0 00:10 0.051 0.051

  • Design Proposal 41

    41

    main2 JUNCTION 3.23 5.80 0 00:12 0.047 0.095

    main3 JUNCTION 1.95 7.12 0 00:14 0.031 0.122

    acorn JUNCTION 0.00 10.29 0 00:10 0.000 0.190

    canter1 JUNCTION 3.10 7.05 0 00:11 0.045 0.105

    cedar JUNCTION 0.99 0.99 0 00:10 0.016 0.016

    birch JUNCTION 3.35 3.35 0 00:10 0.051 0.051

    forest3 JUNCTION 1.78 3.96 0 00:10 0.026 0.058

    elm1 JUNCTION 2.25 22.34 0 00:12 0.033 0.419

    forest2 JUNCTION 0.41 21.50 0 00:13 0.006 0.375

    oak JUNCTION 4.14 4.14 0 00:10 0.062 0.062

    oak3 JUNCTION 1.64 10.75 0 00:10 0.024 0.203

    maple3 JUNCTION 2.46 7.97 0 00:13 0.035 0.121

    ashmount0 JUNCTION 0.81 0.81 0 00:10 0.012 0.012

    ashmount JUNCTION 1.37 4.08 0 00:11 0.020 0.060

    walnut JUNCTION 2.57 5.05 0 00:10 0.037 0.075

    elm JUNCTION 2.51 2.51 0 00:10 0.037 0.037

    154 JUNCTION 0.00 3.02 0 00:11 0.000 0.049

    155 JUNCTION 4.04 4.04 0 00:15 0.072 0.071

    outfall OUTFALL 0.00 62.11 0 00:25 0.000 1.229

    **********************

    Node Surcharge Summary

    **********************

    Surcharging occurs when water rises above the top of the highest conduit.

    ---------------------------------------------------------------------

    Max. Height Min. Depth

    Hours Above Crown Below Rim

    Node Type Surcharged Feet Feet

    ---------------------------------------------------------------------

    Ash1 JUNCTION 0.18 0.000 0.000

    acorn1 JUNCTION 0.33 0.000 0.000

    acorn2 JUNCTION 0.20 0.000 0.000

    acorn3 JUNCTION 0.04 0.000 0.000

    canter4 JUNCTION 0.91 0.000 0.000

    canter5 JUNCTION 0.21 0.000 0.000

    maple4 JUNCTION 0.30 0.000 0.000

    canter8 JUNCTION 0.27 0.000 0.000

    maple2 JUNCTION 0.04 0.000 0.000

    oak2 JUNCTION 0.27 0.000 0.000

    main1 JUNCTION 0.11 0.000 0.000

    main2 JUNCTION 0.19 0.000 0.000

    acorn JUNCTION 0.10 0.000 0.000

  • Design Proposal 42

    42

    elm1 JUNCTION 0.02 0.000 0.000

    forest2 JUNCTION 0.35 0.000 0.000

    oak JUNCTION 0.03 0.000 0.000

    154 JUNCTION 0.13 0.000 0.000

    *********************

    Node Flooding Summary

    *********************

    Flooding refers to all water that overflows a node, whether it ponds or not.

    --------------------------------------------------------------------------

    Total Maximum

    Maximum Time of Max Flood Ponded

    Hours Rate Occurrence Volume Volume

    Node Flooded CFS days hr:min 10^6 gal 1000 ft3

    --------------------------------------------------------------------------

    Ash1 0.18 0.98 0 00:10 0.002 0.000

    acorn1 0.33 2.53 0 00:11 0.011 0.000

    acorn2 0.20 1.97 0 00:11 0.005 0.000

    acorn3 0.04 1.08 0 00:11 0.001 0.000

    canter5 0.21 6.07 0 00:13 0.014 0.000

    maple4 0.30 6.28 0 00:12 0.027 0.000

    canter8 0.27 9.76 0 00:13 0.037 0.000

    maple2 0.04 0.12 0 00:12 0.000 0.000

    oak2 0.27 2.38 0 00:12 0.008 0.000

    main1 0.11 0.64 0 00:10 0.001 0.000

    main2 0.19 0.79 0 00:12 0.002 0.000

    acorn 0.10 0.65 0 00:11 0.001 0.000

    elm1 0.02 0.22 0 00:12 0.000 0.000

    forest2 0.35 4.63 0 00:13 0.023 0.000

    oak 0.03 0.13 0 00:10 0.000 0.000

    154 0.13 0.23 0 00:12 0.000 0.000

    ***********************

    Outfall Loading Summary

    ***********************

    -----------------------------------------------------------

    Flow Avg. Max. Total

    Freq. Flow Flow Volume

    Outfall Node Pcnt. CFS CFS 10^6 gal

    -----------------------------------------------------------

    outfall 90.76 50.92 62.11 1.229

    -----------------------------------------------------------

  • Design Proposal 43

    43

    System 90.76 50.92 62.11 1.229

    ********************

    Link Flow Summary

    ********************

    -----------------------------------------------------------------------------

    Maximum Time of Max Max Max/ Max/

    |Flow| Occurrence |Veloc| Full Full

    Link Type CFS days hr:min ft/sec Flow Depth

    -----------------------------------------------------------------------------

    ash2 CONDUIT 3.96 0 00:11 5.51 1.08 1.00

    acorn3 CONDUIT 13.93 0 00:11 6.27 1.08 1.00

    canter1 CONDUIT 14.72 0 00:12 10.64 0.89 0.73

    maple4 CONDUIT 56.59 0 00:12 10.38 1.07 1.00

    sycamore CONDUIT 2.64 0 00:12 4.21 0.93 0.76

    forest CONDUIT 2.56 0 00:11 5.75 0.60 0.56

    cedar CONDUIT 3.46 0 00:11 6.05 0.82 0.69

    forest1 CONDUIT 18.20 0 00:12 5.21 1.02 0.87

    aspen CONDUIT 1.26 0 00:11 5.77 0.23 0.32

    birch CONDUIT 2.76 0 00:12 5.51 0.70 0.61

    maple CONDUIT 2.60 0 00:12 5.23 0.70 0.61

    main2 CONDUIT 5.39 0 00:21 4.80 1.08 0.95

    main3 CONDUIT 7.11 0 00:14 10.92 0.95 0.78

    acorn CONDUIT 4.55 0 00:10 10.12 0.60 0.56

    acorn1 CONDUIT 10.07 0 00:15 6.33 1.05 0.93

    61 CONDUIT 6.16 0 00:25 8.41 1.07 1.00

    cedar1 CONDUIT 0.99 0 00:10 7.40 0.11 0.23

    birch1 CONDUIT 3.34 0 00:10 11.47 0.34 0.40

    elm3 CONDUIT 2.22 0 00:10 7.41 0.35 0.41

    elm2 CONDUIT 3.96 0 00:10 10.85 0.45 0.47

    elm1 CONDUIT 21.62 0 00:12 6.35 0.99 0.84

    forest2 CONDUIT 21.14 0 00:13 13.86 0.48 0.49

    oak CONDUIT 4.18 0 00:11 5.93 1.05 0.90

    oak1 CONDUIT 5.82 0 00:25 8.09 1.08 1.00

    maple1 CONDUIT 5.82 0 00:13 8.21 1.05 0.91

    maple3 CONDUIT 7.92 0 00:13 12.26 0.33 0.39

    ashmount2 CONDUIT 0.77 0 00:12 4.10 0.18 0.29

    canter CONDUIT 6.95 0 00:12 6.32 0.10 0.21

    ashmount CONDUIT 2.77 0 00:11 5.06 0.78 0.66

    ashmount1 CONDUIT 4.09 0 00:11 10.94 0.47 0.48

    forest3 CONDUIT 17.88 0 00:28 8.07 1.07 1.00

    walnut CONDUIT 2.56 0 00:11 7.57 0.41 0.45

    elm CONDUIT 2.44 0 00:11 6.53 0.47 0.48

  • Design Proposal 44

    44

    oak2 CONDUIT 10.69 0 00:16 5.64 0.47 0.48

    canter2 CONDUIT 36.19 0 00:14 9.83 1.08 0.96

    110 CONDUIT 4.97 0 00:11 7.59 0.96 0.78

    outfall CONDUIT 62.11 0 00:25 11.61 1.05 0.94

    113 CONDUIT 3.02 0 00:11 4.17 1.08 0.96

    114 CONDUIT 2.99 0 00:17 4.18 1.07 0.93

    117 CONDUIT 4.03 0 00:15 12.67 0.38 0.43

    *************************

    Conduit Surcharge Summary

    *************************

    ----------------------------------------------------------------------------

    Hours Hours

    --------- Hours Full -------- Above Full Capacity

    Conduit Both Ends Upstream Dnstream Normal Flow Limited

    ----------------------------------------------------------------------------

    ash2 0.13 0.17 0.14 0.05 0.17

    acorn3 0.10 0.19 0.10 0.21 0.19

    maple4 0.20 0.26 0.20 0.07 0.26

    forest1 0.01 0.03 0.01 0.03 0.03

    main2 0.01 0.18 0.01 0.18 0.18

    acorn1 0.01 0.09 0.01 0.09 0.09

    61 0.26 0.32 0.26 0.32 0.32

    elm1 0.01 0.01 0.01 0.01 0.01

    oak 0.01 0.03 0.01 0.02 0.03

    oak1 0.23 0.26 0.23 0.04 0.26

    maple1 0.01 0.03 0.01 0.03 0.03

    forest3 0.27 0.34 0.27 0.07 0.34

    canter2 0.01 0.20 0.01 0.21 0.20

    outfall 0.01 0.29 0.01 0.30 0.29

    113 0.01 0.10 0.01 0.12 0.10

    114 0.01 0.12 0.01 0.12 0.12

    Analysis begun on: Sat Apr 20 21:07:16 2013

    Analysis ended on: Sat Apr 20 21:07:16 2013

    Wastewater calculations:

    Domestic Wastewater Calculations:

    Domestic wastewater calculations were found by taking 70% of the max hour consumption.

    Sample Calculations from spreadsheet:

    Increment Population = (Increment of Area) x (40 persons/acre)

    Sample: 2.3 acres x 40 persons/acre = 92 persons

  • Design Proposal 45

    45

    Total Tributary Population => Cumulative Sum of Increment Population

    Sewage Flow = (Total Tributary Pop.) x 0.7 x 4 x 100gpcpd/(24hrs x 60min)

    Assumes max hourly use at 400%

    Assumes only 70% of which is wastewater

    Sample = 92 people x 0.7 x 4 x 100/(24x60) = 17.89

    Commercial and Industrial Design Wastewater Flow Calculations:

    Commercial and Industrial wastewater flows were found by fixture unit method as shown

    below:

    For a shopping center the following tables were used to calculate the fixture units for 3

    restaurants and 2 offices.

    Restaurant Fixture Unit Estimate = 25 F.U.

    Office Building Fixture Unit Estimate = 10 F.U.

    Figure of Fixture units for various plumbing devices

  • Design Proposal 46

    46

    Figure Relationship between discharge and number of fixture units

    From the table above corresponding flow rates for the number of fixture units were found to

    be :

    25 F.U. => 40 gpm x 3 (Restaurants) = 120 gpm

    10 F.U. => 30 gpm x 2 (Offices) = 60 gpm

    Total = 180 gpm

    Industry

    For industry wastewater calculations 70% of the water used during the peak hour governed the

    design flow.

    For Industry = (3000gpm) x (70%) = 2100 gpm

    Final Design Parameters:

    Commercial = 180 gpm => 180gpm/5.471acres = 33gpm/acre

    Industry = 2100 gpm => 2100gpm/2.792acres = 752gpm/acre

    Adjusted Sewage Flow

    Certain portions of the sewage layout included commercial and industrial portions. To account

    for this the fraction of area estimated to be industrial, commercial, or residential corresponds

    to the wastewater flow of that particular zone.

    Example: Zone with 1/3 industry, 1/3 commercial, and 1/3 residential would be calculated as

    (1/3 x Increment Area x 752gpm/acre) + (1/3 x Area x 33gpm/acre) + (Residential Sewage

    Flow**) = Adjusted Sewage Flow

    ** Residential Sewage flow is adjusted by (area) x (Pop. Per Capita) x (1/3)

    Upper and Lower Manholes (Inverted Elevations)

    Manholes were dropped by the diameter plus a minimum of 6 ft. ground cover.

  • Design Proposal 47

    47

    Fall of Sewer

    Fall of Sewer =( UpperManhole Elev.) (Lower Manhole Elev.) Grade of Sewer

    Grade of Sewer = (Fall of Sewer)/(Length of Pipe)

    Capacity Flowing Full

    Usig Maigs Euatio: Velocity Flowing Full Ratio of Q to Qfull Ratio of V to Vfull

    Values were determined by from Graph of Hydraulic Elements for Circular Sewers

    Velocity

    V =

    Additional Drop and Adjusted Drops

    Additional drop values reflect additional drop in feet of the lower manhole to increase the

    grade of sewer. Adjusted drops are calculations provided to ensure that pipes were matched at

    the crowns.

    Sewer Diameter (in) Min Slope6 0.00438 0.0033

    10 0.002512 0.001915 0.001418 0.001121 0.0009224 0.00077

  • Design Proposal 48

    Fire Flow Calculations

    NFFi = the needed fire flow in gallons per minute (gpm)

    Ci = a factor related to the type of construction

    Oi = a factor related to the type of occupancy

    X = a factor related to the exposure buildings

    P = a factor related to the communication between buildings

    Building Parameters

    Industrial Area Total = 143,230 sq. ft.

    Assume: 50,000 sq ft. of processing

    1- Story

    Wood Frame (Class 1) => F=1.5

    Oi (C-1) Noncombustable = 0.75

    Distance to exposed building => 31-60 ft. => Xi = 0.15

    Length of Facing Wall = Over 400 ft.

    Unprotected Openings Pi = 0

    Calculations

    Ci=18F(Ai)0.5 = = 6037 gpm NFFi = (Ci)(Oi)[1.0+(X+P)i] = 6037x0.75[1+0.15] = 5207 gpm x 10 hour duration = 3.12 Mgd

    Fire Flow

    5200 gpm or 3.12 Mgd