reliability centered maintenance analysis - defense ... · web view2012/12/12 · reliability...
Embed Size (px)
TRANSCRIPT
LOG 211 Supportability Analysis
Student Guide
Log 211 Supportability Analysis
Student Guide
Reliability Centered Maintenance Analysis
Content
Slide 81. Lesson 8: Reliability Centered Maintenance Analysis
Welcome to Lesson 8: Reliability Centered Maintenance Analysis.
Introduction
Content
Slide 82. Topic 1: Introduction
Content
Comment by PDallosta: Slide 8-3 page 8-3 update to TMRR
Technology Maturation & Risk Reduction
Slide 83. Life Cycle Mangement Framework:
Where Are You? What Influence Do You Have?
Reliability Centered Maintenance (RCM) Analysis determines the most applicable and effective maintenance tasks for a physical asset, such as an airplane or a manufacturing production line. RCM Analysis balances an acceptable level of operability with an acceptable level of risk, considering cost and Availability.
The outputs of RCM Analysis are the inputs into:
Maintenance Task Analysis (MTA) and Technical Manual Tasks, which determine:
What is the complete definition of the maintenance task (i.e., task steps, tools, equipment, and testing)?
How often is maintenance performed?
What resources are required?
What source data is required for the development of technical manuals?
Level of Repair Analysis (LORA), which determines:
At what echelon of maintenance are the tasks performed?
What are the Operation & Support (O&S) Costs of the tasks?
Where Are You?
RCM Analysis spans the Life Cycle Management Framework, from the initial design through Operations & Support to disposal.
For competitive prototypes, initial identification of maintenance task candidates and task intervals for critical failures begins in the Technology Development –Maturation and Risk Reduction (TMRR) phase.Comment by PDallosta: Updated TMRR
RCM is conducted again during Engineering & Manufacturing Development, as the system’s design matures and is finalized.
During the Operations & Support phase, system performance and maintenance data are collected, and serve as inputs to additional RCM Analysis, as necessary. This continuous Supportability Analysis process facilitates improvements in design and promotes maintenance efficiency, suitability, and operational effectiveness.
What Influence Do You Have?
RCM Analysis is the bridge between Reliability Engineering and Product Support. While Reliability Engineers conduct RCM Analysis, the Life Cycle Logisticians (LCLs) play a prominent role in reviewing the analysis outcomes in terms of effectiveness and suitability. These outcomes are and therefore should be in lock step with the Maintenance Task Analysis, which RCM Analysis impacts directly. The LCL role is further detailed in Lesson 9: Maintenance Task Analysis (MTA).
Content
Slide 84. RCM Analysis Lesson Approach
Key questions in this lesson are:
What actions reduce the probability, identify the onset, and limit the consequences of failure?
What mitigating actions will enable the system to meet Availability KPP/KSA requirements?
Content
Slide 85. Topics and Objectives
Overview of RCM Analysis
Content
Slide 86. Topic 2: Overview of RCM Analysis
Slide 87. What Is RCM Analysis?
RCM Analysis is a logical decision process that identifies technically appropriate, cost-effective, and defensible maintenance approaches for failure modes identified in Failure Mode Effects and Criticality Analysis (FMECA) and Fault Tree Analysis (FTA).
RCM Analysis does not prevent all failures, but mitigates failure consequences in order to meet system Availability requirements. To do this, RCM recommends one or several maintenance options, creating an optimal balance. The following factors are included in maintenance option decisions:
Proactive maintenance tasks (known as “preventive” to logisticians)
Tasks that identify and address the need for maintenance before the failure occurs.
Condition-based (predictive maintenance)—Identifies the onset of failure and predicts the remaining useful life of an item. On-condition tasks are performed based upon “evidence of need,” rather than as a scheduled or planned maintenance action.
Interval-based (preventive maintenance)—Schedules maintenance on a regular basis, before failure, regardless of condition.
Reactive Maintenance Tasks (known as “corrective” to logisticians)
Allows “run-to-failure”, followed by repair to restore item.
Determines root cause of failure at lowest cost and in least time.
Mitigates consequences after failure (secondary effects).
Cost (Affordability of Repair)
Manpower
Equipment
Facilities
Other actions
Redesign for Maintainability (accessibility, modularity, testability)
Training programs
Technical manuals
Operating and Maintenance procedures
Safety and Emergency procedures
Additionally, RCM Analysis establishes the necessary maintenance task intervals, as well as cost implications for recommended maintenance tasks.
Content
Slide 88. What is RCM Analysis?: Significant Functions
An item’s functional mission significance determines the applicability of RCM Analysis; not every functional failure qualifies for RCM Analysis. All possible effects of a failure mode, including secondary effects, are considered when assessing significance.
FMECA/FTA identify criticality of functional failures, providing the data from which to determine functional significance:
Functions
Functional failures
Failure modes
Failure mechanisms
Failure effects (primary and secondary)
Criticality
A function is significant if one or more of the following criteria apply:
Does the loss have an adverse effect on operating safety?
Does the loss have an adverse effect on the environment (leading to serious violation of environmental standards/requirements)?
Does the loss have an adverse effect on operations?
Does the loss have an adverse effect on economics?
Is this function protected by an existing preventive maintenance (PM) task?
If none of the criteria apply, the function is not a candidate for further RCM Analysis, and therefore not a candidate for preventive maintenance. For non-significant functions, the assigned maintenance strategy is run-to-failure, followed by corrective action.
Content
Slide 89. What is RCM Anaysis?: Inputs & Influence
RCM Analysis functions across a larger framework of FMECA/FTA, MTA, and LORA, and serves as a refinement to the maintenance planning process.
As shown in this slide, FMECA identifies failure modes and their criticality. Non-significant failures are assigned corrective maintenance tasks, which then act as inputs directly into the MTA. Significant failures undergo RCM Analysis.
While FMECA identifies failure modes and their criticalities, RCM Analysis goes further. RCM Analysis develops mitigation strategies to reduce failure modes from cascading into catastrophic events by inserting preventive tasks or influencing remove and replace intervals. RCM Analysis outputs include both new and refined corrective and preventive maintenance tasks/frequencies. As with FMECA, both sets of RCM Analysis outputs are direct inputs to the MTA. These new tasks are added to MTA activities, while the existing tasks are modified to reflect RCM instructions.
Content
All corrective and preventive maintenance tasks documented by the MTA are reviewed and promoted to the Logistics Product Database. The Logistics Product Database can then provide this information to other requirements, such as the Level of Repair Analysis (LORA) and the technical manuals.
For RCM Analysis to be effective, it must be integrated with the MTA in this broader framework.
Content
Slide 810. What is RCM Analysis?: ASOE Model
As previously mentioned, in the Affordable System Operational Effectiveness (ASOE) Model, Technical Performance and Supportability bolster Design Effectiveness, which, in conjunction with Process Efficiency, generates Mission Effectiveness. It is through Mission Effectiveness, when coupled with Ownership Costs, that the most operationally effective, suitable, and affordable system is realized.
Through selecting the most appropriate and cost-effective maintenance tasks, RCM Analysis contributes to ASOE by optimizing design and mission effectiveness, while reducing Life Cycle Cost/Total Ownership Cost, in the following ways:
RCM Analysis Impact on Design Effectiveness
Determines the most appropriate and effective maintenance tasks to meet and sustain requirements for:
Reliability
Availability
Maintainability
Operational readiness
Achieves longer useful life for weapons system components
Enhances Human Systems Integration (safety)
Improves environmental integrity—reduces potential of failure mode that breaches OSHA, departmental or international (if NATO mission) environmental regulations
RCM Analysis Impact on Mission Effectiveness
Increases maintenance efficiency
Greater productivity
Shorter maintenance cycles
Increased quality of process
Better use of resources
Decreased logistics footprint
Provides for continuous improvement of maintenance program/ equipment performance
Provides documentation trail for maintenance program changes
RCM Analysis Impact on Life Cycle Costs/Total Ownership Costs (Design Affordability)
Reduces overall Life Cycle Costs by reducing costs in the Operations & Support phase
Content
Slide 811. ASOE Trade-Off: Reliability vs. Maintenance
This slide shows the trade-off linkage during RCM Analysis that enables Affordability and Supportability. Specifically, imperfect Reliability results in failure mode consequences. Significant failures are mitigated through maintenance task strategies designed to achieve the most efficient and effective support strategy, which in turn, reduces O&S Cost.
Content
Slide 812. What is RCM Analysis: Inputs and Outputs
This diagram provides a high-level view of RCM Analysis process inputs and outputs.
Set Up – Building a Plan and Gathering Inputs
Content
Slide 813. Topic 3: Set Up – Building a Plan and Gathering Inputs
Content
Slide 814. Set Up
Preparing for RCM Analysis includes planning for analysis activities that occur throughout the life cycle of a system, selecting a suitable RCM Analysis tool to support and manage the process, and defining and importing the data inputs required for task selection.
Content
SAE GEIA-STD-0007
Slide 815. Build a Plan: Process and Data Management
The Set Up phase is planning oriented, considering analysis activities ranging from initial task selection to refinement based on operation and maintenance data gathered during Sustainment.
Role of the Integrated Product Team (IPT)
IPT members who are responsible for RCM Analysis require a solid understanding of design, Reliability principles, and maintenance.
During the initial Set Up, the IPT:
Identifies roles: Who is doing what? Example roles include the following:
Program Manager—Program Manager responsibilities with regards to RCM Analysis are to plan, develop, program, and implement RCM processes and outputs.
Test personnel—Maintenance task choices feed the test environment (e.g., draft manual, test article selection, operator training, testing of task). Therefore, test personnel should be involved in maintenance task selection along with the engineer and logistician.
Establishes Working-level Integrated Product Team (WIPT) expectations, providing examples of the RCM Analysis process and the WIPT’s role
Content
Defines the analysis goal
Defines the schedule/timeline
Plans for Sustainment
Planning for Sustainment
An RCM Sustainment program measures essential performance requirements to demonstrate effectiveness. Operational data is collected, including maintenance, failure, and repair data. This information enables the IPT to monitor, analyze, update, and refine product design and maintenance programs, as warranted.
Examples of issues addressed by an RCM Sustainment program are:
Incorrect assumptions made on initial analysis for new programs that lacked reliable data
Equipment/hardware changes
Unexpected failures
Operating environment changes
Common Monitoring Activities
Monitoring requires organized Information Systems (IS) to conduct monitoring under actual operating conditions. Operational data include:
Performance metrics
Business: ROI/cost-benefit for initial RCM Analysis and Sustainment
Program management: training, schedules, number of systems analyzed, etc.
Technical: equipment behavior (MTBF, readiness and Availability, servicing actions, maintenance man-hours)
Trend analysis
Product Support Package and documentation reviews
Age exploration (collection of operational and test data, see DoDM 4151.22-M, June 30, 2011 Encl 2 para 2.g.(4))
Existing and emergent (future) failure modes
Top degraders (e.g., highest failure rates or impact on Availability and Maintainability) and cost drivers
Fleet leader programs (a type of test program where the weapon system is subjected to slightly accelerated operating conditions so that designated systems ‘lead’ the actual population both in time and load. The program’s intent is to provide advanced warning of serious design flaws to avert a major incident and potential loss of life)
Opportunities for process improvements and technology insertion
Changes to equipment operating profile and environment
Content
Results of Sustainment Analyses
Collection of operational data provides a feedback loop to refine analyses, brings greater confidence to recommended corrections, and validates maintenance plan cost target performance. The result: safe operations and cost-effective readiness.
Specific Sustainment analyses recommendations include:
Adjusting maintenance intervals
Adding, deleting, or modifying preventive maintenance tasks, procedures, or requirements
Modifying age exploration tasks
Providing recommendations for redesign
Changing maintenance processes
Restricting operations
Content
SAE GEIA-STD-0007
Slide 816. Determine Data Inputs
RCM Analysis Data Inputs
Design characteristics
Capability Development Document (CDD)
Built In Test (BIT)
Sensors
System configuration
Engineering data, studies, and drawings
Design reports
Product specification sheets
Production inspection records
Vendor information
Original Equipment Manufacturer (OEM)
Developmental testing results
Test result reports
Engineering investigation reports
Modeling and simulation data
Subject matter experts with knowledge of equipment and operating context
Operator
Maintainer
In-service engineer
Technical representative
Program Manager
Reliability analyses
Reliability characteristics
Time to Failure (calculated or estimated) for non-reparable items
Mean Time Between Failure (MTBF) for reparable items
Average time a system operates without failure (assuming no PM in place) under a prescribed set of conditions
Average age if allowed to run-to-failure (RTF) (without PM, under normal operating conditions)
In-service data usually not used in RCM Analysis MTBF, because some PM already in place
Prioritized failure modes that require further analysis
Determines need and frequency for PM maintenance
Time in RCM Analysis is units related to failure mode (cycles, miles, hours, landings)
Reliability Block Diagrams
Failure characteristics
Potential failure conditions
Failure distribution curve (calculated or estimate)
Wear out/life limit age
Random failures
Failure mode occurring within service life of equipment
Test data
Maintainability analyses
Mean Time Between Maintenance (MTBM)
Mean Time to Repair (MTTR)
Mean Down Time (MDT)
Mean Repair Time (MRT)
Maintenance Task Analysis
Maintainability: Engineering Considerations
Accessibility
Modularity
Testability
Built In Test architecture
Ambiguity groups/BIT effectiveness/detection rates/false reports
Failure Mode Effects and Criticality Analysis (FMECA) results
Functions, functional failures, failure modes, failure effects
Severity class for failure mode (criticality)
Fault Tree Analysis (FTA) results
Human Systems Integration (safety and hazard analysis)
Maintenance data systems
Previous maintenance plans
In-service performance data
Item repair histories
Failure Reporting, Analysis, and Corrective Action System (FRACAS)
FRACAS is system of reporting and analyzing failures, recommending corrective action
Developed from Test & Evaluation (T&E) events and field failure/repairs
Common data captured in FRACAS include field MTTR, MTBF, Reliability growth, failure analysis (incident, type, location, root cause, etc.)
Cost data
RCM Analytical Tools
Currently, there are several RCM Analysis tools in common use within Government and industry. The tools are compliant with SAE GEIA-STD-0007, which enables the exchange of Logistics Product Data between the Logistics Product Database and Supportability Analysis tools. Comment by PDallosta: update
Two tools are highlighted here:
RCM++
Data management and reporting for RCM Analysis
Full-featured FMEA/FMECA functionality
Maintenance tasks selection
Optimal interval calculation for preventive repairs/replacement
Cost comparison
Supports industry standards for RCM (e.g., ATA, MSG-3, SAE JA1011 and SAE JA1012)
MPC: Maintenance Program Creation Software
MSG-3-compliant maintenance creator tool for aircraft/aerospace industry
Analyses included for significant items, functions, failure modes, effects, causes, and tasks
Analysis – Determining Maintenance Tasks and Intervals
Content
Slide 817. Topic 4: Analysis – Determining Maintenance Taks and Intervals
Content
Slide 818. Analysis
During analysis, Reliability Engineers and logisticians determine which option or set of options best prevent failure or reduce its consequences to an acceptable level.
The RCM logic includes a two-step process:
1. Categorize the failure consequences
Evident vs. hidden failures
Safety/environment
Operational (mission) capability
Cost of operations (not including mission impact)
Determine the most appropriate and effective maintenance tasks (including appropriate interval) or other action to address consequences
Content
Slide 819. RCM Analysis: Process Map
Maintenance tasks must be both applicable and effective:
Applicable: Does the task address the characteristics of the failure? Each task option has unique criteria that determine if it is applicable.
Effective: How effective is the task in reducing the consequences of the failure? Selection criteria rests on the type of impact—safety/environmental or operational/non-operational.
Content
Slide 820. RCM Analysis: Decision Diagram
The slide highlights three decision points that act as primary drivers in the RCM decision logic tree:
Evident vs. Hidden Failures: Because hidden failures are not apparent to the operator during normal use, analysis takes into account the probability of multiple failures as a result, and the effect of these secondary failures on the system.
Category of Effects: The type of consequence (e.g., safety vs. mission loss) directly impacts trade-off decisions between failure consequences and cost (e.g., safety effects require preventive maintenance).
Note: Categorization of maintenance task risk factors also appears in operator/maintainer maintenance manuals (e.g., safety consequences are bolded and identified with NOTES, CAUTIONS or WARNINGS).
Task Selection: Failure characteristics drive decisions on the task or group of tasks selected to reduce the risk of failure.
The RCM decision diagram is where risk management and the ASOE model come together to identify (1) Where is my risk? and (2) How do I address it? You must analyze the data inputs to identify whether the evident or hidden failures impact safety, environment, operation, or economics. Recall from slide 16 that T&E on failure management and operational data are reported through FRACAS, which is the vehicle for data into RCM.
For a complete example of the R C M decision diagram, see MIL-HDBK-2173: Handbook For Reliability-Centered Maintenance Requirements For Naval Aircraft, Weapons Systems And Support Equipment.
Content
Slide 821. Categorizing Consequences: Justifying Preventive Maintenance
Safety/Environmental Consequences
All failure modes that result in potential safety hazards to personnel, equipment, or to the environment (breach of environmental law, regulation, or standard) require mitigation, which may be achieved through preventive maintenance. Run-to-failure, or corrective maintenance, is not permitted for failures with hazardous impacts.
Safety Consequence: Persons severely injured or killed; loss of system
Environmental Consequence: Significant, permanent damage to the environment, or failures that carry penalties
For safety/environmental consequences, the preventive maintenance task must reduce the probability of failure to an acceptable level (Pacc). Then, for the task to be effective, the actual probability of failure given a task must be less than the Pacc. Actual probability of failure is based on initial task intervals and failure distribution.
Operational/Non-Operational Consequences
In cases where safety is not a consequence, preventive maintenance is justified based on achieving operational capability in the most cost-effective manner. A preventive maintenance task is then desirable if the cost of implementation is less than the cost of run-to-failure:
Impact on operational capability exists
The cost for not performing a preventive maintenance task equals the sum of the cost of operational loss plus failure it prevents (repair costs)
Inputs: Failure rate, operational consequences, repair and operational costs, real applicable data
Impact is economic only
When there is no impact on safety or operations, the consideration to perform preventive maintenance is purely economic (not including mission impact)
The cost of the task must be less than the cost of the failure it prevents (repair costs)
Note: When performing an economic trade-off, such as cost-benefit ratio, normalize the cost to a common unit of measurement across maintenance options (hours, cycles). Also, include variables such as peacetime versus wartime/operational tempo.
Content
Slide 822. On-Condition Maintenance: Predictive Maintenance
On-condition maintenance is performed at the most appropriate time based on the actual condition (evidence of need) of the equipment, rather than a scheduled or planned maintenance action regardless of need.
With this maintenance strategy, equipment performance is compared against known standards and criteria. If the inspection reveals performance outside the healthy range, the potential for failure exists. Early indications of failure or impending failure allow for effective and timely response before functional failures occur. If the inspection does not indicate a potential failure, no action is required and the item continues until the next inspection.
Inspections are often geared to life limiting wear. In the example of the tire, the limitation is tread, which if worn too much (past the head of Abraham Lincoln on a penny), can pose a safety issue.
Slide 823. On-Condition Maintenance: The P-to-F Curve
On-condition maintenance is predictive in nature. The inspection detects Potential Failure (PF) conditions and then predicts the remaining useful life before a Function Failure (FF).
The time between detection of PF and FF (PF Curve) is the opportunity to conduct on-condition inspections.
The PF curve is based on progression of failure once failure begins, not the failure rate/probability of failure.
RCM Analysis provides evidence of need (failure condition) and a PF curve that together determine the most appropriate time to perform maintenance.
Choosing the Appropriate Potential Failure Condition
Multiple degradation characteristics are possible. Therefore, consider the following when selecting a condition to monitor:
Choose those conditions that are achievable/consistent with detection methods
Consider whether the length and consistency of the P to F curve between PF/FF is long enough to perform inspections or manage the consequences of failure
Consider the availability of equipment to perform the maintenance task
Consider the cost-effectiveness of the on-condition task
Examples of On-Condition Maintenance Methods and Tools
On-condition maintenance methods and tools include inspections, detection through human senses, sophisticated monitoring equipment, and continuous monitoring by sensors applied directly to equipment. Examples include:
Visual/non-destructive inspection
Vibration monitoring and analysis
Oil sample analysis
Brake-pad measurements
Applicability of the Task
A task could be selected for on-condition maintenance if it meets the following requirements:
Possible to define potential failure characteristics
Possible to detect failure with explicit task
Consistent PF interval
It is practical to monitor condition at intervals at or less than PF interval
PF interval is long enough to manage consequences to failure
Determining the Appropriate Interval
Periodic or continuous assessment of equipment condition occurs at one or more intervals between PF and FF, with frequency based on:
Consequences of failure
Effectiveness of task
Accessibility of item
Skill of personnel performing inspection
Industry standards
Specific system
Cost Formula
Cost of 1 inspection * Man-hours * Cost of Materials
Note: Assumes field maintenance
Content
Slide 824. On-Condition Maintenance: CBM+ and Prognostics and Health Management (PHM)
Condition-Based Maintenance Plus (CBM+) optimizes on-condition maintenance by providing more accurate and efficient real-time condition data, fault identification, and failure prediction. To do this, CBM+ integrates a comprehensive set of modern technology, tools, and processes, including:
Hardware
Software
Design
Processes
Communications
Tools
Typically implemented at the design stage, a CBM+ strategy requires greater up-front investment, skill level, and time. Applicability rests on several factors:
System/component maturity and complexity
Resource Availability
Cost-benefit analysis
Operational performance and experience in the field (e.g., frequency and impact of failure modes)
CBM+ Relationship to RCM Analysis
CBM+ expands RCM Analysis by providing additional tools, technologies, and processes to determine the most appropriate maintenance task.
RCM Analysis may suggest a revision to a maintenance task or redesign. At that point CBM+ may be considered (e.g., sensor, diagnostic software).
Diagnostics in CBM+
CBM+ provides diagnostic tools to compare current health conditions against known fault conditions to determine the state of a component to perform its function. Monitoring/recording devices and analysis software are used to:
Detect failures or potential failures
Assess degree of degradation
Signal need for maintenance
Identify root causes and design fixes
Assess impact on mission
Collect, store, and communicate system condition and failure data
Prognostics in CBM+
CBM+ also predicts future health and the remaining life of equipment through processes that:
Anticipate faults, problems, potential failures, and required maintenance actions
Determine lead time from detecting a failure condition to actual functional failure
Indicate out of range conditions, imminent failure probability, and proactive maintenance actions through monitoring devices/software
Improve accuracy and efficiency of failure detection
Content
Health Management in CBM+
Integrated Information Systems allow LCLs to capture, track, and analyze the health and status of systems. Acting on condition information provided by diagnostic and prognostic data, LCLs can predict when failures may occur and determine appropriate maintenance and other logical actions consistent with operational demand and available resources.
CBM+ health management involves:
User alerts
Data mining and analysis
Simulation and modeling
Decision-support systems
Content
Slide 825. CBM+ and PHM: Impact on Supportability
CBM+ supports data collection, analysis, and decision-making for successful acquisition, Sustainment, and operations. As a result, CBM+ has multiple impact points on Supportability and Supportability Analysis:
Improves Operational Availability
Identifies optimum time to perform required maintenance
Extends equipment life
Decreases down time due to maintenance
Decreases the number of non-mission capable items
Improves maintenance effectiveness
More appropriate, effective, and timely maintenance actions
Greater accuracy in predicting failures improves planning
Shorter maintenance cycles
Increased quality of process
Fewer unscheduled repairs
Fewer unnecessary maintenance tasks
Reduces Mean Down Time
Provides real-time maintenance information and accurate technical data that:
Accelerates repair and support processes
Accelerates return to operational status
Reduces overall logistics footprint
Reduced maintenance-related requirements (manpower, spares, facilities, equipment, etc.)
Reduces O&S Costs
Fewer unscheduled and unnecessary repairs
Maintenance performed at optimum time
Accurate failure prediction leads to streamlined supply chain operations by reducing downtime, labor needs
Informs resource planning, force planning, situational assessments
Content
Slide 826. Interval-based Tasks: Overview
Interval-based maintenance tasks are regularly scheduled maintenance, performed regardless of equipment condition.
Preventive maintenance is applicable to items that:
Are consumable
Are subject to wear out (including chemical breakdown)
Demonstrate a known failure pattern (i.e., statistical failure information provides a fixed schedule for overhaul)
Maintenance interval is determined by failure rate (MTBF)/probability of failure (represented in time based on cycles, hours, etc.)
Types of scheduled maintenance
Servicing and lubrication (includes filtration, such as changing air/oil filters)
Calibration
“Hard Time" removal/replacement
Failure finding
Content
Slide 827. Interval-Based Tasks: Overview, continued
This is an example of a typical maintenance schedule for a car engine. Notice the tasks inserted at specific maintenance intervals:
I = Inspect, correct, replace
R = Replace
Content
Slide 828. Servicing/Lubrication Tasks: Interval-Based Maintenance
Servicing
Servicing tasks replenish consumables expended during normal operation, such as fuel, oil, oxygen, and nitrogen.
Applicability of task
Required by system design or operational needs based on usage, environment, and convenience
Intervals
Scheduled according to need
Assign conservative interval at convenient point in maintenance program
Inputs
Equipment designs
Original Equipment Manufacturer (OEM) specifications
Operator/maintainer inputs
Maintenance publications
Lubrication
Lubrication reduces friction, protects against wear, removes dust and debris, prevents rust and corrosion, provides a seal for gases, and prevents burning.
Applicability of task
Required when lubricant is non-permanent and therefore needs periodic reapplication
Intervals
Scheduled based on predicted or measured life of lubricant, usage, and operational environment
Inputs
Equipment drawings
OEM
Maintenance publications
Operator/maintainer input
Lubricant manufacture date
Cost for Servicing and Lubrication
One servicing/lubrication task = Man-hours to perform + Cost per man-hour + Cost of materials
Content
Slide 829. Hard Time Remove/Replace: Interval-Based Maintenance
Hard time maintenance is scheduled removal for rework/restoration or discard/replace, and is performed at a predetermined, maximum age, even with no failure pending.
Applicability of task
Possible to identify characteristics of wear-out, which are sudden increase in probability of failure with operating age
Items can survive to useful life
On-condition maintenance is not applicable or effective:
Failure does not have detectable or predictable failure condition
Failure does not allow long enough PF interval to permit effective on-condition task
Intervals
Safe life limit: Used for safety/environmental consequences
Limit below which no failure will occur
Probability of failure is less than acceptable probability of failure
Economic life limit: When the cost is less than or the same as run-to-failure
Maximizes useful life
Adds risk for occasional failure
Reliability requirement
Inputs
Weibull analysis
Fatigue analysis or tests
Manufacturers recommended service life
Existing effective maintenance task
Engineering judgment based on data, operators/maintainers, similar components
Cost formula
(Man-hours * cost per man-hour) + cost of materials
Content
Slide 830. Hard Time Remove/Replace: Water Pump Example
This graph charts the Reliability of a single car's water pump again distance travelled. This is probability - taking a normal distribution, but looking at one tail. Unreliability equals 1 minus Reliability.
At which point should you take your car in to change the water pump?
Content
Slide 831. Economic Remove/Replace: Water Pump Example
This graph plots the cost of replacing the water pump against distance travelled. Here, the most economical point to replace the water pump is at 100,000 kilometers. However, is this the optimal remove/replace point?
Content
Slide 832. Hard Time Remove/Replace: Water Pump Example, continued
Water pump failure results in severe engine damage or engine failure, as major engine components overheat and seize.
The Safe Life Limit is chosen well before the probability of Wear Out.
The Economic Life Limit takes into consideration useful life and costs of deferring repairs, when roadside assistance and special repairs away from home are needed should failure occur.
Wear Out spans about 5,000 km (96,000 – 100,000 km), a zone where failure is imminent and costly.
The takeaway: Replace at the Safe Life Limit of 96,000 km, where the water pump meets a minimum Reliability of 85%.
Content
Slide 833. Failure Finding Inspections: Interval-Based Maintenance
Failure finding tasks are appropriate when the occurrence of a functional failure is not evident to the operator during normal use. Hidden failures require regularly scheduled inspection tasks to reduce the risk of multiple failures to an acceptable level.
Evident Failure—The failure is apparent on its own, under normal conditions; no other action needed to detect (e.g., visual, audio, or operational warnings, such as loss of control)
Hidden Failure—The operator has to perform any action, not within normal operating procedures, to detect the failure
Applicability of Task
Only when on-condition maintenance, hard time maintenance, or a combination of both are not applicable or effective for hidden failures
There is no way for operator/maintainer to know of failure through indicators/alarms
Failure would result in critical situation should another failure occur as a result
Built in redundancy exists
Alternative to redesign
Failure already occurred
Interval
Part of pre- and post-mission inspection checklists
Cost Formula
(Man-hours * cost per man-hour) + material cost
Content
Slide 834. Run-to-Failure: Corrective Maintenance
A decision to run-to-failure (RTF) allows the failure to occur, followed by corrective action to repair or replace the item. This type of maintenance is unscheduled and unplanned.
Applicability of task
Operational/economic failures only
When consequences of failure are tolerable
Redundancy exists
Non-critical/inconsequential failure
Unlikely to fail
No historical data
Small items
Cost
Average repair cost of item
Cost of secondary damage
Cost of multiple failures, if hidden FF
Cost of loss of operations, if applicable
Content
Slide 835. Run-to-Failure: Water Pump Example
Not all RCM Analyses are applicable to run-to-failure. In this example, the water pump is not a candidate for a run-to-failure task because risk/cost of run-to-failure far outweighs the cost of removal and replacement.
Content
Slide 836. Other Logical Actions
When run-to-failure is not the chosen outcome, but no appropriate preventive maintenance task reduces the consequences of functional failure to an acceptable level, other actions may mitigate failure consequences.
Possible actions
“Root cause” analysis
Redesign (accessibility, modularity, testability)
Improvement in Reliability
Incorporation of Prognostic Health Management (PHM)
Establishing redundancy
Operational restrictions
Change in maintenance procedures
Additional data collection
Change to training program
Change to emergency procedures
Change to supply system
Change to technical manuals
Applicability of task
Positive return on investment (ROI) on Availability, cost, and reduced exposure to hazardous conditions
Cost: Development and implementation costs
Report Findings – Data Management and Communication Paths
Content
Slide 837. Topic 5: Report Findings – Data Management and Communication Paths
Content
Slide 838. Report Findings
In the Report Findings step, an RCM Analysis summary report is submitted to the IPT for approval. Tasks are then packaged for inclusion in the MTA process.
SAE GEIA-STD-0007
Slide 839. Report & Implement Findings
Recall the RCM Analysis process chart. At this stage, the data is reviewed, approved by the IPT, and then inputted directly into MTA.
Conducted by the Life Cycle Logistician (LCL), MTA evaluates the Logistics Product Data. The results of this evaluation can reveal system design, component attributes, or maintenance processes that contribute to failing to meet Availability and Reliability requirements. It can also identify resource shortages.
Slide 840. RCM Analysis Report
The RCM Analysis report includes the following summary:
List of significant items, categorized by consequence (safety, environmental, operational, economic)
Functional failure analysis (function, failure mode, failure effect, failure cause)
Evident/hidden failures
Task selection for each cause of each failure (question tree/answers/ intervals
Maintenance task summary
Note: Recall that all maintenance not identified by RCM is corrective action (run-to-failure), by default.
Slide 841. Map Failure Modes to Tasks
RCM Analysis outputs become inputs into MTA; MTA updates the Logistics Product Database with maintenance tasks and subtasks.
Packaging Tasks for Input into MTA
Maintenance task recommendations are packaged for input into the subsequent Maintenance Task Analysis (MTA). The work package includes:
Interval-based/scheduled tasks and frequencies/intervals (preventive maintenance)
On-condition/CBM+ tasks and frequencies/intervals (predictive maintenance)
Other recommended tasks to effectively avoid, predict, and mitigate consequences of failure
Cautions and Warnings for maintenance tasks related to safety
Packaging Process
1. Confirm tasks were analyzed using the proper metrics
Structure tasks along timeline
Identify logical task groupings
Common inspection intervals
Common panel access
Common skill and maintenance levels
Determine which tasks are least flexible in adjustment
Develop final packaging
Package in phases
Package with other maintenance for convenience
Fit into existing packages
Repackaging: review of preventive maintenance tasks package
Assembling maintenance tasks into work packages minimizes equipment downtime and reduces the cost of implementing and performing maintenance by performing multiple tasks together.
Slide 842. Inspect UAV SATCOM Control Task
When a new task is designated by RCM Analysis, the LCL coordinates with the applicable IPT for the analysis outcome to be entered into the Logistics Product Database as an initial task or update to an existing task as part of the Maintenance Task Analysis (MTA).
The task includes:
Task Frequency—Hours, cycles, calendar time, pre/post operation (not shown on graph)
Task Code—SAE GEIA-STD-0007 Code detailed in Lesson 9, MTA.
Subtask Identification—Descriptive subtitle; e.g., CAUTION, INSPECT
Subtask Number—Task Step Number
Sequential Subtask Description—Task Step Narrative
Predicted Mean Elapsed Time—The average time in minutes for a maintenance tech to complete the task step
Resources—Technician, tools, test equipment and facility
The RCM Analysis outcome could impact any or all of the item’s Maintenance Task Analysis requirements.
Slide 843. RCM Analysis Results: IPT Communication Paths
RCM Analysis acts as the boundary between Reliability Engineering and maintenance, and therefore has possible impact on all Integrated Product Support Elements. The RCM Analysis functional lead must understand both areas in order to work effectively with the Product Support Management IPT and to effectively provide inputs to the Maintenance Task Analysis activity.
As issues arise due to RCM Analysis, such as possible redesign or trade-off decisions between maintenance recommendations, the IPT taking action:
Determines team member responsibilities—designates lead and supporting membership if forming a WIPT to resolve the issue
Makes recommendations—forms applicable failure consequences, maintenance task, and interval failure mitigation strategies
Coordinates solutions—implements goals and objectives through program and IPT leadership
The slide highlights two scenarios:
Technical Data: Changing an existing maintenance task, such as an interval
Systems Engineering IPT
Product Support Management IPT
Maintenance Planning & Management: Adding a new maintenance task
Test & Evaluation IPT
Systems Engineering IPT
Product Support Management IPT
Exercise and Simulation
Content
Slide 844. Topic 6: Exercise and Simulation
Content
Slide 845. Exercise and Simulation Overview
Content
Slide 846. Exercise
Content
Slide 847. Simulation
Summary
Content
Slide 848. Topic 7: Summary
Content
Slide 849. Takeaways
Content
Slide 850. Summary
Congratulations! You have completed Lesson 8: Reliability Centered Maintenance Analysis.
8-24 of 70
January 2013
Final v1.3
January 2013
Final v1.3
8-25 of 70