Service Procedure # 002 (Page 1 of 3) 08/05/2014 Packing and Agitator Replacement A2000/A2000I ANKOM Technology 2052 O’Neil Road Macedon, NY 14502 PH: (315) 986 -8090 FAX: (315) 986-8091 [email protected] 1. Place cardboard on a table. Lay the A2000 on it’s front. Remove the nuts that secure the clear back panel. Remove the panel. Remove the feet and mounting screws, then remove the bottom panel. 2. Loosen the top set screw on the coupler. 3. Loosen the packing nut until it is finger loose. 4. Remove the three nuts that secure the motor bracket in place 5. Unplug the motor wires and set the motor out of the way. 6. Twist and pull up to remove the agitator.

Upload: lydiep

Post on 10-Mar-2018

235 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: Packing and Agitator Replacement A2000/A2000I · PDF fileService Procedure # 002 (Page 1 of 3) 08/05/2014 Packing and Agitator Replacement A2000/A2000I Check Agitator- 1. Check the

Service Procedure # 002 (Page 1 of 3) 08/05/2014

Packing and Agitator Replacement

A2000/A2000I

ANKOM Technology 2052 O’Neil Road Macedon, NY 14502 PH: (315) 986-8090 FAX: (315) 986-8091

[email protected]

1. Place cardboard on a table. Lay the A2000 on

it’s front. Remove the nuts that secure the clear

back panel. Remove the panel. Remove the

feet and mounting screws, then remove the

bottom panel.

2. Loosen the top set screw on the coupler.

3. Loosen the packing nut until it is finger loose. 4. Remove the three nuts that secure the motor

bracket in place

5. Unplug the motor wires and set the motor out of

the way.

6. Twist and pull up to remove the agitator.

Page 2: Packing and Agitator Replacement A2000/A2000I · PDF fileService Procedure # 002 (Page 1 of 3) 08/05/2014 Packing and Agitator Replacement A2000/A2000I Check Agitator- 1. Check the

Service Procedure # 002 (Page 1 of 3) 08/05/2014

Packing and Agitator Replacement

A2000/A2000I

Check Agitator- 1. Check the agitator for wear and pitting in the shaft surface. The surface should be very smooth without grooves, pits or a

thinned diameter.

2. The agitator can be installed if the packing has not been disturbed. Push and twist until the agitator is completely seated on

the vessel bottom.

3. Replace the motor and cabinet bottom. Follow the procedure for tightening the packing on the bottom of page 3.

Note:

The Agitator Teflon

Collar must rest against

the bottom of the

Digestion Vessel when

installed.

Replacing the Packing-

1. The packing is removed using a screwdriver.

2. The packing consists of two carbon ropes and one compressed

graphite cylinder. When removed, it will look similar to the image

on the left. Ensure both ropes are removed or the new packing

will not fit.

(

ANKOM Technology 2052 O’Neil Road Macedon, NY 14502 PH: (315) 986-8090 FAX: (315) 986-8091

[email protected]

Page 3: Packing and Agitator Replacement A2000/A2000I · PDF fileService Procedure # 002 (Page 1 of 3) 08/05/2014 Packing and Agitator Replacement A2000/A2000I Check Agitator- 1. Check the

Service Procedure # 002 (Page 1 of 3) 08/05/2014

Packing and Agitator Replacement

A2000/A2000I

Packing

Packing

Bushing

.

Packing

Bushing

3. Check the packing nut after four hours of use and adjust if necessary. If assistance is needed, call

ANKOM Technology at 315-986-8090 or email technical service at [email protected].